Protection Philosophy/Protocol of Northern Region: (Developed in Compliance of IEGC 2023)
Protection Philosophy/Protocol of Northern Region: (Developed in Compliance of IEGC 2023)
Protection Philosophy/Protocol of Northern Region: (Developed in Compliance of IEGC 2023)
of Northern Region
(developed in compliance of IEGC 2023)
Version: 2.0
(approved in 71st NRPC meeting held on 29.01.2024)
January 2024
Protection Philosophy/Protocol of Northern Region
(approved in 71st NRPC meeting held on 29.01.2024)
Time setting:
i. 0.35 second
(considering LBB time of 200mSec, CB open
time of 60ms, resetting time of 30ms and
safety margin of 60ms)
400kV LINES/CABLE:
Low set stage (Stage-I): 110% - 112%
(typically 110%) with a time delay of 5 seconds.
High set stage (Stage-II): 140% - 150% with a time
delay of 100 milliseconds.
*****