PT PLN-NP UNIT MAINTENANCE REPAIR & OVERHAUL

No Dok :
PLN-NP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit :
FORM UJI Revisi :
BATTERY CHARGER Hal :
Site : PLTU PAITON Manufaktur : SIEMENS TAHUN QP No. FU No.
Unit :2 Inspeksi : SE 2023 OEM Doc No.

AC Voltage Test
Result Acceptance Value
No Object Notes
Volt (V) Freq (Hz) Volt (V) Freq (Hz)

1 AC Input L1 - L2 399.1 49.97 342-418 49,5-50,5


2 AC Input L2 - L3 399.2 49.98 342-418 49,5-50,5
3 AC Input L3 - L1 395.4 49.98 342-418 49,5-50,5

DC Voltage Test
Result Acceptance Value
No Object Notes
Volt (V) Ripple (mV) Volt (V) Ripple (%)

1 DC Output 111.5 2 99-121 < 1.0

Visual Check
No Indicator Result Notes
1 Each terminal is tight? YES

Function Test
No Indicator Result Notes
Control system and protection is normal?
1 YES

ACCEPTED/REWORK/REPLACE
RECOMENDATION
(by Quality Control)

MEASURING TOOL AVOMETER

Description Tested/Measured Coordinator Quality Control Witness


Name M Miftakhul F Fauzi Rachmat K Hendri Yanuar A Andi Susilo

Signature

Date 5/11/2023 5/11/2023 5/11/2023 5/11/2023


99
PT PLN-NP UNIT MAINTENANCE REPAIR & OVERHAUL
No Dok : 0
PLN-NP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit : 0
0
FORM UJI Revisi : 0
BATTERY CHARGER Hal :
Site : PLTU PAITON Manufaktur : SIEMENS TAHUN QP No. FU No.
Unit :2 Inspeksi : SE 2023 OEM Doc No.
#REF! No Dok ###
:
#REF! Tgl. Terbit ###
:
#REF!
#REF! Revisi ###
:
#REF! Hal :
Site :### Manufaktur : ### TAHUN #REF! FU No.
Unit : ### Inspeksi : ### #REF! OEM Doc No.
ACCEPTED/REWORK/REPLACE
RECOMENDATION
(by Quality Control)

MEASURING TOOL AVOMETER

Description Tested/Measured Coordinator Quality Control Witness


Name M Miftakhul F Fauzi Rachmat K Hendri Yanuar A Andi Susilo

Signature

Date 5/11/2023 5/11/2023 5/11/2023 5/11/2023


PT PLN-NP UNIT MAINTENANCE REPAIR & OVERHAUL
No Dok :
PLN-NP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit :
FORM UJI Revisi :
Hal :
Site : PLTU PAITON Manufaktur : SIEMENS TAHUN QP No. FU No.
Unit :2 Inspeksi : SE 2023 OEM Doc No.

Prim 100 Measured Error (A)


Injected Expected Result (OK/
Sec 1 Current (A) Current (A) Current (A) Measured Max NOK) Notes
R R 0 ### OK
S S 0 ### OK
0 ### T T 0 ### OK 0.5%x2CT
R R 0 ### OK
S S 0 ### OK
0 ### T T 0 ### OK 0.5%x2CT
R R 0 ### OK
S S 0 ### OK
CT W1 3Ph 0 ### T T 0 ### OK 0.5%x2CT

Prim Measured Error (A)


Injected Expected Result (OK/
Sec Current (A) Current (A) Current (A) Measured Max NOK) Notes
0 ### 0 ### OK
0 ### 0 ### OK
CT 1Ph 0 ### 0 ### OK 0.5%x2CT
PT PLN-NP UNIT MAINTENANCE REPAIR & OVERHAUL
No Dok :
PLN-NP INTEGRATED MANAGEMENT SYSTEM Tgl. Terbit :
FORM UJI Revisi :
Hal :
Site : PLTU PAITON Manufaktur : SIEMENS TAHUN QP No. FU No.
Unit :2 Inspeksi : SE 2023 OEM Doc No.
ACCEPTED/REWORK/REPLACE
RECOMENDATION
(by Quality Control)

MEASURING TOOL

Description Tested/Measured Coordinator Quality Control Witness


Name

Signature

Date

You might also like