Material Requisition Guideline
Material Requisition Guideline
2. PURCHASE PROCEDURE
2.1 General guideline for purchase requisition
It is the responsibility of the respective employee to notify the Purchase department/ relevant department
head/ Director through E-mail/ prescribed “PURCHASE REQUISITION FORM” with detail information of the
need to Purchase items as per requirement with referenced detail of the need and other information. Based
on written request of the user/requester, the Purchase department/ relevant department head shall
process the requisition maintaining further guideline of this policy, keeping the Purchase recorded in a
register file (Soft Copy/ Hard Copy) & maintain those for further audit.
Best-cost does not always mean the lowest bid rather it is a compromise between price and
quality. For the greater interest of the organization and receiving qualitative and timely
services/goods, Procurement committee may give any kind of justified recommendation to
issue work order/Purchase order but justification must be recorded as future reference.
2.9.2 Procurement Committee members should be involved in all RFQ process as per guideline of
Top Management member in specific purchase or service request following through to CS,
evaluation, negotiation, recommendation and approval process before placing the PO for
final purchase. Inspection and quality assurance is an integral part of this whole process.
2.10.1 When the enlisted vendors are not available for a particular item and the general
suppliers are unable to meet the specific requirements.
2.10.2 When some small Purchase of urgent nature, repair, maintenance, sanitary,
cleaning and carpentry works for which no enlisted vendor is available and payment
is to be made on completion of the job by cash.
This policy must be re-prepared, approved and duly authorized whenever any change in method of operation
or any other circumstance, indicates the need as per Management view. It must be reviewed time to time from
the date of issue, in the light of current practice, to determine whether any revision is necessary.
P a g e 3|7