JOB SAFETY ANALYSIS

Job / Activity: Earth Cable laying & Thermo Weld , Termination.


JSA Ref. No. JSA/KO
Permit No.
Type of Activity: Worksite: RM7 Equipment: Not Applicable
Critical /Non-Critical Date:
Personal Protective Equipment & Tools: Hard Hat, Safety Shoes, Safety Goggles, Hand Gloves, Personnel Gas monitor, Ear plug,, Insulated Hand Tools etc...
Initial Risk Residual Ri
Sequence of Basic Job
Potential Hazards Precautions
Steps Severity Likelihood Risk Rating Severity

• Plan the work involving permit Applicant, Permit Issuer & worksite
Lack of Communication Supervisor.

• Get authorization for Cold Work Permit


Non-compliance of KOC • Ensure KOC HSEMS Procedure Doc. No. SA.KOC.027- Electrical
-HSEMS Procedures Work Safety Procedure, KOC.SA.004- Permit to work procedure are
followed.

Planning & Preparation


In-appropriate • Ensure the correct tools & required PPEs are ready to use prior to
tools & PPE carrying instrument installation.

• Obtain the permit from asset Owner.


• Ensure the installation to be carried out by authorized and
Unauthorized installation competent working crew.
• Approved drawings available for installation.

Presence of Toxic gas


• Ensure atmospheric gas test to be carried out and recorded.

• Ensure Proper trained and Experienced personnel at work.


• Tool Box talks
• Ensure trenches are free from obstacles
Personal Injury
• Ensure the right tools & required materials are available.
• Use of Proper hand tools and appropriate PPE.
Earth Cable laying & • Ensure the work location free from "Line of Fire " hazards, Sharp
termination. edges of cable tray, stored energy, etc.,

Improper installation of
• Ensure the start and end position of the cable to be laid before
cables.
laying.

• Ensure all the work area is free from insects and reptiles.
Biological Hazards

Improper PPE • Use of Proper hand tools and appropriate PPE.

• Ensure the equipment and cables to be Weld is isolated prior to start


• Personal injury during the work. Use safety hand gloves during work.
Thermo welding. • Personnel shall be briefed by Tool box talks about existing and
generating hazards and allowable Thermo Weld and recorded.

• Presence of • Ensure the Area is free from flammable/Toxic gases


Flammable/Toxic gases • Ensure Gas Monitoring before satrt up of work
Thermo Weld
In-appropriate usage of • Use of proper usage of hand tools & equipment for glanding and
equipment termination.

• Keep suitable fire extinguishers ready


• Display emergency contact number in the work area
• Fire & Explosion
construction/HSE team by phone and PMC KOC controlling team and
KOC unified emergency number 160.
• Clear all the tools and Scattered materials
Post Work Scattered Material • Maintain good housekeeping

Additional Hazards
(Other than indicated above)

JSA Done (by Worksite Name: Designation


Supervisor) & Employee Id: Company. Controlling Team: Signature:
JSA Reviewed (by Permit Name: Designation
Applicant) & Employee Id: Company. Controlling Team: Signature:

JSA Authorized (by Permit Name: Designation


Company. Controlling Team: Signature:
Issuer) & Employee Id:
ETY ANALYSIS
JSA Ref. No. JSA/KOC
Permit No.
Date:
and Gloves, Personnel Gas monitor, Ear plug,, Insulated Hand Tools etc...
Residual Risk

Likelihood Risk Rating

Signature: Date:
Signature: Date:

Signature: Date:

You might also like