Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 7

STRATCOST SAMPLE PROBLEMS REVIEWER

Problem 1.
Fred Company uses a standard cost system for its production process and applies overhead based
on direct labor hours. The following information is available for August when Fred made 4,500
units:

Standard: Actual:

DLH per unit Direct labor hours


2.50 10,000 hrs
Variable overhead per DLH Variable overhead
P1.75 P26,250
Fixed overhead per DLH Fixed overhead
P3.10 P38,000
Budgeted variable overhead
P21,875
Budgeted fixed overhead
P38,750

Analysis of Factory Overhead Variances


Using 4 way, 3 way, 2 way methods

Problem 2.
Jeff Corporation uses a standard cost system, applying manufacturing overhead on the basis
of machine hours. The company's overhead standards per unit are shown below.

Variable overhead: 4 hours at P9 per hour


Fixed overhead: 4 hours at P6* per hour

*Based on planned monthly activity of 120,000 machine hours

Actual data for May were:


Number of units produced: 29,000
Number of machine hours worked: 125,000
Variable overhead costs incurred: P1,085,000
Fixed overhead costs incurred: P755,000

Required:
A. Calculate the spending and efficiency variances for variable overhead.
B. Calculate the budget and volume variances for fixed overhead.
C. Analyze Variances using the three-way and two-way methods
Problem 3.
Different management levels in Cates, Inc., require varying degrees of managerial accounting
information. Because of the need to comply with the managers' requests, four different variances
for manufacturing overhead are computed each month. The information for the September
overhead expenditures is as follows:

Budgeted output units 3,200 units


Budgeted fixed manufacturing overhead P20,000
Budgeted variable manufacturing overhead P5 per direct labor hour
Budgeted direct manufacturing labor hours 2 hours per unit
Fixed manufacturing costs incurred P26,000
Direct manufacturing labor hours used 7,200
Variable manufacturing costs incurred P35,600
Actual units manufactured 3,400

Required:
a. Compute a 4-variance analysis for the plant controller.
b. Compute a 3-variance analysis for the plant manager.
c. Compute a 2-variance analysis for the corporate controller.
Standard setting
THEORIES: 5. The best basis upon which cost standards
Standard cost system should be set to measure controllable
production inefficiencies is
1. A primary purpose of using a A. Engineering standards based on ideal
standard cost system is performance.
A. To make things easier for managers in the B. Normal capacity
production facility. C. Engineering standards based on attainable
B. To provide a distinct measure of cost performance.
control. D. Practical capacity
C. To minimize the cost per unit of
production. 6. A company employing very tight (high)
D. b and c are correct. standards in a standard cost system should
expect that
2. Which one of the following statements is A. No incentive bonus will be paid.
true concerning standard costs? B. Most variances will be unfavorable.
A. Standard costs are estimates of costs C. Employees will be strongly motivated to
attainable only under the most ideal attain the standard.
conditions, but rarely practicable. D. Costs will be controlled better than if
B. Standard costs are difficult to use with a lower standards were used.
process-costing system.
C. If properly used, standards can help 7. To measure controllable production
motivate employees. inefficiencies, which of the following is
D. Unfavorable variances, material in the best basis for a company to use in
amount, should be investigated, but large establishing the standard hours allowed for
favorable variances need not be the output of one unit of product?
investigated. A. Average historical performance for the
last several years
3.Which of the following is the purpose of B. Engineering estimates based on ideal
standard costing? performance.
A. Determine “breakeven” production level. C. Engineering estimates based on attainable
B. Control costs performance.
C. Eliminate the need for subjective D. The hours per unit that would be
decisions by management. required for the present workforce to
D. Allocate costs with more accuracy. satisfy expected demand over the long run

4. When evaluating the operating 8. Which of the following statements about


performance management sometimes uses the selection of standards is true?
the difference between expected and A. Ideal standards tend to extract higher
actual performance. This refers to: performance levels since they give
A. Management by Deviation employees something to live up to
B. Management by Control B. Currently attainable standards may
C. Management by Objective encourage operating inefficiencies.
D. Management by Exception
C. Currently attainable standards A. Zero
discourage employees from achieving B. Favorable
their full performance potential. C. Unfavorable
D. Ideal standards demand maximum D. Either favorable or unfavorable,
efficiency which may leave workers depending on the budgeted overhead.
frustrated, thus causing a decline in
performance. Types of standards

Standard costs vs. budgeted costs 12.The absolute minimum cost possible
under the best conceivable operating
9. A difference between standard costs used conditions is a description of which type of
for cost control and the budgeted costs standard?
representing the same manufacturing A. Currently attainable (expected)
effort can exist because B. Normal
A. standard costs must be determined C. Theoretical
after the budget is completed. D. Practical
B. standard costs represent what costs
should be while budgeted costs represent 13.Standards, which are difficult to achieve
expected actual costs. due to reasons beyond the individual
C. budgeted costs are historical costs performing the task, are the result of firm
while standard costs are based on using which of the following methods to
engineering studies. establish standards?
D. budgeted costs include some “slack” A. Ideal Standards
or “padding” while standard costs do not B. Lax Standards
C. Practical Standards
Process costing D. Employee Standards

10.When standard costs are used in a Two way variances Volume variance
process-costing system, how, if at all, are
equivalent units involved or used in the cost 16.A company uses a two-way
report standard? analysis for overhead variances: budget
A. Equivalent units are not used. (controllable) and volume. The volume
B. Equivalent units are computed using a variance is based on the
“special” approach. A. Total overhead application rate
C. The actual equivalent units are multiplied B. Volume of total expenses at various
by the standard cost per unit. activity levels
D. The standard equivalent units are C. Variable overhead application rate
multiplied by the actual cost per unit. D. Fixed overhead application rate
Normal costing
17.Assuming that the standard fixed
11.The fixed overhead application rate is a overhead rate is based on full capacity,
function of a predetermined “normal” the cost of available but unused productive
activity level. If standard hours allowed for capacity is indicated by the:
good output equal this predetermined A. Factory overhead cost volume variance
activity level for a given period, the B. Direct labor cost efficiency variance
volume variance will be C. Direct labor cost rate variance
D. Factory overhead cost controllable variance be further evaluated as to price and
variance usage?
A. There is no need to further evaluate the
18. In analyzing manufacturing overhead total materials variance if it is favorable.
variances, the volume variance is the B. Generally accepted accounting
difference between the: principles require that all variances be
A. Amount shown in the flexible budget and analyzed in three stages.
the amount shown in the debit side of the C. All variances must appear in the annual
overhead control account. report to equity owners for proper
B. Predetermined overhead application rate disclosure.
and the flexible budget application rate. D. To allow management to evaluate
C. Budget allowance based on standard the efficiency of the purchasing and
hours allowed for actual production for production functions.
the period and the amount budgeted
to be applied during the period. Labor variances
D. Actual amount spent on overhead items 26.Which of the following unfavorable cost
during the period and the overhead amount variances would be directly affected by
applied to production during the period the relative position of a production
times actual hours worked. process on learning curve?
A. Materials mix
Responsibility for variances B. Materials price
C. Labor rate
23.Which department is customarily D. Labor efficiency
held responsible for an unfavorable
materials usage variance? 27.Which of the following is the most
A. Quality control probable reason with a company would
B. Engineering experience an unfavorable labor rate
C. Purchasing variance and favorable labor efficiency
D. Production Variance analysis variance?
A. The mix of workers assigned to the
24.Which of the following should be least particular job was heavily weighted toward
considered when deciding whether to the use of highly paid, experienced
investigate a variance? individuals.
A. Whether the variance is favorable or B. The mix of workers assigned to the job
unfavorable. was heavily weighted toward the use of new,
B. Significance of the variance relatively low paid, unskilled workers.
C. Cost of investigating the variance C. Because of the production schedule,
D. Trend of the variances over time Total workers from other production areas
materials variance were assigned to assist in this
particular process.
25.If the total materials variance D. Defective materials caused more labor to
(actual cost of materials used compared be used to produce a standard unit.
with the standard cost of the standard
amount of materials required) for a given
operation is favorable, why must this
Two-way overhead variance 31.Favorable fixed overhead volume
variance occurs if:
28.The budget for a given cost during a A. There is a favorable labor efficiency
given period was P1,600,000. The actual variance.
cost for the period was P1,440,000. B. There is a favorable labor rate variance.
Considering these facts, it can be said that C. Production is less than planned.
the plant manager has done a better than D. Production is greater than planned.
expected job in controlling the cost if:
32.The unfavorable volume variance may be
A. The cost is variable and actual production due to all but which of the following
was 90% of budgeted production. factors? A. Failure to maintain an even flow
B. The cost is variable and actual of work.
production equaled budgeted production. B. Machine breakdowns
C. The cost is variable and actual production C. Unexpected increases in the cost of
was 80% of budgeted production. utilities
D. The cost is discretionary fixed cost D. Failure to obtain enough sales orders.
and actual production equaled budgeted
production Budget variance. Three-way Overhead variance

29.The budget variance for fixed 35. During 2006, a department’s three-
factory overhead for the normal- variance overhead standard costing
volume, practical-capacity, and expected- system reported unfavorable spending
activity levels would be the: and volume variances. The activity
A. Same except for normal volume level selected for allocating overhead to
C. Same except for expected activity. the product was based on 80% of practical
B. Same except for practical capacity capacity. It 100% of practical capacity had
D. Same for all three activity levels been selected instead, how would the
Volume variance reported unfavorable spending and
volume variances be affected?
30.You have leased a 5,000-gallon storage Spending Variance Volume Variance
tank for P5,000 per month. You stored 4,000 A. Increased Unchanged
gallons of liquid in the tank during the B. Increased Increased
month. The cost of storage was P1.25 per C. Unchanged Increased
gallon, rather than P1.00 per gallon. D. Unchanged Unchanged
based on 5,000-gallon capacity. Therefore,
the cost of storing 4,000gallons was P1,000
more (P.25 x 4,000) in total than if you
had stored 5,000 gallons of liquid in the
tank. Which variance is being described?
A. Variable-overhead efficiency variance
B. Fixed-overhead spending variance.
C. Variable-overhead spending variance
D. Fixed-overhead volume variance.

You might also like