TOIFM-HM-RPSB-L008 - Site Progress Report For Server Room

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

TOTAL IFM SDN BHD (487350-T)

Website : www.tofm.com.my
Social :TOFMSdnBhd total-ifm
NORTHERN: No.64 & 64A, Susuran Anjung Tawas, Anjung Tawas Sinaran, Off Jalan Kuala Kangsar, 30010 Ipoh Perak Email: northro@tofm.com.my 605-2921308
CENTRAL: Building Information Centre, P2-05, Lot 2, Jalan 51A/243, 46100 Petaling Jaya, Selangor Email: centralro@tofm.com.my 603-78729067
EASTMALAYSIA:1st Floor, No.41, Block C, Wisma Nation Horizon, Jalan Petanak,93100 Kuching, Sarawak Email: srwro@tofm.com.my 6082-252279
EASTERN: Lot 1287E, Kampung Pauh, Jalan Telok, Panji 16100 Kota Bharu, Kelantan Email: kltnro@tofm.com.my 609-7640757

Ref No : TOIFM/HM/RPSB/ICT/2303.L008
Date : 15th March 2023
R Synegy Sdn Bhd
Hospital Miri Site Office
Jalan Cahaya, 9800 Miri, Sarawak, Malaysia.
Attn : Mr. Lo Khin Kiong / Mr. Aldrin Sik
Dear Sir,
PEMBINAAN BANGUNAN TAMBAHAN HOSPITAL MIRI DI ATAS LOT 523 BLOCK 17, KUALA
BARAM LAND DISTRICT, MIRI SARAWAK (REKA DAN BINA)
- Site Progress Report for Level 5 Server Room, DB Room & CDU Room.

We would like to inform that we had prepared our Material’s and Equipment’s will be delivery on April
& May 2023 for installation work and termination work on Server Room.

We also would like to highlights the findings during site visit with our principal, please refer to the
attached photo report.

We truly appreciate your kind assistance and cooperation in providing the support on time for us to
complete the above mentioned.

Please do not hesitate to contact us should you require any further clarification.

Thank you.

Yours sincerely,

For and on behalf of


TOTAL IFM SDN BHD

…………………………
P.S Moo
Senior Project Manager

Energy Management &


Asset & Facility Renewable Energy& Biomedical
Solid /Clinical Waste
Management Green Building Index Engineering
Management

ICT Project / Cleaning & Mechanical & Electrical (Chiller, Civil, Structure and
BAS/BMS Housekeeping Led, Pumps, Blowers, Valves Architecture
Engineering
PROJECT : PEMBINAAN BANGUNANTAMBAHAN HOSPITAL MIRI, SARAWAK (REKA DAN BINA) - TENDER SEMULA
Subject : Site Walk & Coordination for ICT Server Room.

Date : 09th & 10th March 2023

Item Description Remark


Level 5 - IT Operationg Room (IT5402)
• Additional 1no 13Amp SSO for ICT 50 inch TV
(Server Monitoring System)
• Additional 2nos 13Amp SSO for Server Monitoring
Computer (Below table 300mm FFL).

1
50" ICT TV
1no 13A SSO

Level 5 - IT Operationg Room (IT5402)


• Pending House Keeping.
• Pending Ceiling Installation work.
• Pending Painting Work.
• Pending Safety Lock (Door) & Painting work.
2 • Pending ELV System to complete installation &
Activation System (Card Access, Public Address,
SMATV System)
• Pending LV System to complete installation of
Lighting work.

Level 5_IT Operating (IT5402) Page 1 / 4


PROJECT : PEMBINAAN BANGUNANTAMBAHAN HOSPITAL MIRI, SARAWAK (REKA DAN BINA) - TENDER SEMULA
Subject : Site Walk & Coordination for ICT Server Room.

Date : 09th & 10th March 2023

Item Description Remark


Level 5 - Server Room (IT5401)
• Pending FAP Panel Making for ICT EMS System link
to FAP.

Level 5 - Server Room (IT5401)


• Pending PU Foam Insulation to Slab Soffit.
• Pending LV System to complete installation of
Lighting work.

Level 5 - Server Room (IT5401)


• Pending Fanal Painting for Wall.

Level 5 - Server Room (IT5401)


• FM200 Dropper Pipe to Raised Floor need to offset to
nearer wall (Blocking access route to Server Rack).

Level 5_Server Room (IT5401) Page 2 / 4


PROJECT : PEMBINAAN BANGUNANTAMBAHAN HOSPITAL MIRI, SARAWAK (REKA DAN BINA) - TENDER SEMULA
Subject : Site Walk & Coordination for ICT Server Room.

Date : 09th & 10th March 2023

Item Description Remark

Level 5 - Server Room (IT5401)


• Server Room need to tidiness

Level 5 - Server Room (IT5401)


• Pending others trade to complete ducting work &
Fire Alarm work. (Above slab area).
• Pending ELV Services to complete installation &
Activation System (Card Access, Public Address,
8
SMATV System).
• Pending Lighting & SSO installation work by LV Contractor.
Lighting work.

Level 5 - Server Room (IT5401)


• Pending Copper Cable & Earth Bar by LV Contractor.

Level 5_Server Room (IT5401) Page 3 / 4


PROJECT : PEMBINAAN BANGUNANTAMBAHAN HOSPITAL MIRI, SARAWAK (REKA DAN BINA) - TENDER SEMULA
Subject : Site Walk & Coordination for ICT Server Room.

Date : 09th & 10th March 2023

Item Description Remark


Level 5 - DB Room (Near Server Room)
• Pending Wooden Door Installation with Painting work.
• Pending Painting work inside DB Room.
• Pending ELV Services to complete installation &
Activation System (Public Address)
• Pending Lighting & SSO installation work by LV Contractor.
10
Lighting work.

Level 5 - CDU Room (IT5403)


• This wall is installation Ring Circuit System for Inrow
Cooling, please did not any services on this wall.
• Pending floor screening & Painting work.

11

Level 5 - CDU Room (IT5403)


• Pending Incoming Supply & Return Water Pipe for
Ring Circuit System (Inrow Cooling).

12

Level 5 - CDU Room (IT5403)


• Pending floor trap with curved for discharge inrow cooling.
• Pending Door Curved & House keeping.

13