SHOP DRAWING

TABLE OF CONTENTS SHOP DRAWING_BUILDING BUILDING

PAGE PAGE
CODE DRAWING NAME CODE DRAWING NAME
SDB- 01 3D RENDER EXTERIOR SDB- 36 FACADE VIEW 1 & SECTION A-A' Principal
SDB- 02 3D RENDER EXTERIOR SDB- 37 Angelina Deviana S.Ds
SECTION B-B'
Drawn by
SDB- 03 3D RENDER EXTERIOR SDB- 38 LAYOUT PLANTER OUTDOOR, SECTION C-C', SECTION D-D', VIEW A, VIEW B Firman & Meylie

SDB- 04 3D RENDER EXTERIOR SDB- 39 FACADE VIEW 2&3 JIKA DISATUKAN Date 30 January 2024

SDB- 05 3D RENDER INTERIOR SDB- 40 FACADE VIEW 2


!! ATTENTION !!
SDB- 06 3D RENDER INTERIOR SDB- 41 SECTION E-E'
ALL RIGHT RESERVED. PART OF ANY
SDB- 07 3D RENDER INTERIOR SDB- 42 DETAIL PERTEMUAN VIRIDI 1 & 2 FAIR DEALING FOR THE PURPOSE OF
INDIVIDUAL PROJECT, MAJOR
SDB- 08 SDB- 43 SECTION F-F' PROJECT, CRITICISM OR REVIEW AS
3D RENDER INTERIOR OUR PERMITTED. NO PART OF THIS
SDB- 09 SDB- 44 FACADE VIEW 3, SECTION G-G' DESIGN AND DRAW MAY BE
3D RENDER INTERIOR REPRODUCED OR TRANSMITTED IN
SDB-10 SDB- 45 ANY FORM BY ANY MEANS. NO
3D RENDER INTERIOR SECTION H-H' PHOTOCOPYING , RECORDING OR
OTHERWISE WITHOUT OUR WRITTEN
SDB-11 SITEPLAN SDB- 46 FACADE VIEW 4 PERMISSION.
SDB-12 LAYOUT FURNITURE SDB- 47 FACADE VIEW 5 CONTRACTOR LIABLE TO CHECK
DIMENSIONS IN THE FIELD AND IF
SDB-13 DETAIL PENEBALAN 1, 2, 3 SDB- 48 FACADE VIEW 6, 7, 8, 9 THERE ANY DISCREPANCY SHOULD
BE REPORTED TO PLANNER.
SDB-14 FLOOR PLAN SDB- 49 SECTION 1-1' & SECTION 1-1' PART A
BEFORE WORK EXECUTED, THE
SDB-15 DETAIL CURVE DINDING ENTRANCE SDB- 50 SECTION 1-1' PART B & DETAIL A CONTRACTOR LIABLE TO MAKE A
FORM OF COORDINATION
SDB-16 DETAIL RAMP OUTDOOR SDB- 51 SECTION 1-1' PART C DRAWING EXAMPLE AND
SUBMITTING MATERIAL PLANNER
SDB-17 DETAIL SUSUNAN F2 TERHADAP F1 (PART A) SDB- 52 SECTION 2-2' & SECTION 2-2' PART A AND REQUESTING APPROVAL.

SDB-18 DETAIL SUSUNAN F2 TERHADAP F1 (PART B) SDB- 53 SECTION 2-2' PART B MISMATCHES EVERY FIELD IN MUST
IMMEDIATELY CONSULT AND SEEK
SDB-19 DETAIL LANTAI KERIKIL SDB- 54 APPROVAL OF PLANNER.
DETAIL B
SDB- 20 CEILING PLAN SDB- 55 SECTION 3-3'
The Pound Cake
SDB- 21 CEILING SECTION A-A' (DETAIL ATAP) SDB- 56 VIEW 1 S. Parman
SDB- 22 CEILING SECTION 1-1' & CEILING SECTION 1-1' PART A SDB- 57 VIEW 2
APPROVAL
SDB- 23 CEILING SECTION 1-1' PART B SDB- 58 VIEW 3
SDB- 24 CEILING SECTION 2-2' & CEILING SECTION 2-2' PART A SDB- 59 Name :
VIEW 4
Date :
SDB- 25 CEILING SECTION 2-2' PART B & DETAIL A SDB- 60 DETAIL PINTU TOILET A-A'
SDB- 26 CEILING SECTION 3-3' , DETAIL B, DETAIL C SDB- 61 VIEW 5
SDB- 27 CEILING SECTION 4-4' & DETAIL D SDB- 62 VIEW 6
(sign here)

ADDITIONAL INFORMATION
SDB- 28 MODUL CANOPY OUTDOOR SDB- 63 VIEW 7
SDB- 29 VIEW CANOPY DARI ATAS SDB- 64 VIEW 8
SDB- 30 ME PLAN A SDB- 65 VIEW 9
SDB- 31 ME PLAN B SDB- 66 VIEW 10
SDB- 32 SDB- 67 DRAWING NAME
ME NUMBERING GAS STATION - LAYOUT
SDB- 33 ME PLAN (POSISI TOTEM) SDB- 68 GAS STATION - ME PLAN 3D RENDER EXTERIOR

SDB- 34 ME OVERLAY FURNITURE SDB- 69 SECTION I-I' & VIEW 1


PAGE CODE SCALE
SDB- 35 ME OVERLAY CEILING PLAN SDB- 70 SECTION J-J'
DAFTAR ISI 1N.T.S.
SHOP DRAWING
TABLE OF CONTENTS SHOP DRAWING_BUILDING BUILDING

PAGE
CODE DRAWING NAME
SDB- 71 SECTION K-K' Principal
SDB- 72 Angelina Deviana S.Ds
GAS STATION - VIEW 2 & VIEW 3
Drawn by
SDB- 73 GAS STATION - VIEW 4 & VIEW 5 Firman & Meylie

SDB- 74 GAS STATION - VIEW 6 Date 30 January 2024

SDB- 75 SECURITY ROOM - LAYOUT


!! ATTENTION !!
SDB- 76 SECURITY ROOM - FLOOR PLAN
ALL RIGHT RESERVED. PART OF ANY
SDB- 77 SECURITY ROOM - ME PLAN FAIR DEALING FOR THE PURPOSE OF
INDIVIDUAL PROJECT, MAJOR
SDB- 78 SECTION L-L' PROJECT, CRITICISM OR REVIEW AS
OUR PERMITTED. NO PART OF THIS
SDB- 79 SECTION M-M' DESIGN AND DRAW MAY BE
REPRODUCED OR TRANSMITTED IN
SDB- 80 ANY FORM BY ANY MEANS. NO
SECTION N-N' & SECTION O-O' PHOTOCOPYING , RECORDING OR
OTHERWISE WITHOUT OUR WRITTEN
SDB- 81 SECURITY ROOM - VIEW 1 PERMISSION.
SDB- 82 SECURITY ROOM - VIEW 2 CONTRACTOR LIABLE TO CHECK
DIMENSIONS IN THE FIELD AND IF
SDB- 83 SECURITY ROOM - VIEW 3 THERE ANY DISCREPANCY SHOULD
BE REPORTED TO PLANNER.
SDB- 84 SECURITY ROOM - VIEW 4
BEFORE WORK EXECUTED, THE
CONTRACTOR LIABLE TO MAKE A
FORM OF COORDINATION
DRAWING EXAMPLE AND
SUBMITTING MATERIAL PLANNER
AND REQUESTING APPROVAL.

MISMATCHES EVERY FIELD IN MUST


IMMEDIATELY CONSULT AND SEEK
APPROVAL OF PLANNER.

The Pound Cake


S. Parman
APPROVAL

Name :

Date :

(sign here)

ADDITIONAL INFORMATION

DRAWING NAME

3D RENDER EXTERIOR

PAGE CODE SCALE

DAFTAR ISI 2N.T.S.