S.No IR.No Zone & level Description of Inspection Discipline ATNM subject to site
Type
condition
Sheikha/Amjad
1 CVL-4968 Main Entrance Road 200mm thick subgrade level, compaction CVL W Santhosh 10.00AM
Sheikha/Amjad
2 CVL-4970 LV manholes Pcc for LV manholes(5NOS) CVL W Santhosh 10.00AM
Sheikha/Amjad
3 CVL-4972 Canopy 08 Level, compaction & setting out to proceed pcc concrete CVL W Santhosh 10.00AM
Sheikha/Amjad
4 CVL-4973 LV manholes 2coat of bitumen paint to proceed backfilling CVL W Santhosh 10.00AM
Sheikha/Amjad
5 CVL-4974 Swale 04 Stone pitching to proceed grouting CVL W Santhosh 10.00AM
9 HVAC-93 Zone-8,Level-01 Installation/insulation of GI duct of Extract air duct HVAC W Sami/sheik 10.00AM
10 PLB-518 Zone-7,Level-02(HL) Installation of High level (Horizontal piping) drainage piping PLB W Praveen/sheik 10.00AM
11 ELC-58 External LV Installation og UPVC duct pipe for external LV ELC W Bashir/Jithin 10.00AM