Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 58

STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Monday 26-Feb-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concert
Casting RCP 42 - - - 17.00
Production
RCP 48 1,167.00 1,167.00 216.00
1 21+100 No
RCP 36 30.00 - 30.00 27.00
RCP Concert
RCP 42 - - -
Installed on Site
RCP 48 603.00 - 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concert L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concert Casting Production 1,311.00 - 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Monday 26-Feb-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Available
Available Material
S.No Work Description Quantity Man Remark
From To Equipment Consumption
power
loader Cement=10bag 1=Forman
Masonry construction for Retaining
1 42+014 42+019
Wall
8.44m3 Sand=0.9m3 1=Oprator 2C
6=Labor
1=Forman
Masonry construction for Type B Inlet and Type C
2 46+517 8.61m3 1=Oprator
outlet
6=Labor
1=Forman

3 47+082 Pavedwater Way and Stone Pitching 7.3m3 1=Oprator


6=Labor
1=Forman

4 46+791 Pavedwater Way and Stone Pitching 5.3m3 1=Oprator


6=Labor
1=Forman

5 42+014 42+019 installation of Weephole 8.48m 1=Oprator


6=Labor
1=Forman
6 42+014 42+019 installation of Expansion Joint 23.64m2 1=Oprator
6=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Tuesday 27-Feb-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 38.00 19.00


RCP Concert
Casting RCP 42 - - 17.00
Production
RCP 48 1,167.00 1,167.00 216.00
1 21+100 No
RCP 36 30.00 30.00 27.00
RCP Concert
RCP 42 - -
Installed on Site
RCP 48 603.00 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concert L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concert Casting Production 1,311.00 - 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting China Civil Engineering Construction
Ethiopian Roads Administration (ERA)
with HUB Engineering Corporation (CCECC)
Time of Operation : Date:- Tuesday 27-Feb-24
8:00 AM To 11:00 PM Weather:- sunny
Temperature at 8:00 AM:- Min 24 °C Max 31
Available
Station Available Material
S.No Work Description Quantity Man Remark
From To Equipment Consumption
power
1=Forman
Masonry construction for Type B Inlet and Type C
1 46+517 8.61m3 1=Oprator comp
outlet
6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
2 42+014 42+019
Wall
8.44m3 Sand=0.9m3 1=Oprator 2C
6=Labor
1=Forman
Checkdam and Pavedwater way
3 47+082 6.3m3 1=Oprator
Construction 6=Labor
1=Forman

4 46+791 Pavedwater way Construction 2.1m3 1=Oprator


6=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Wednesday 28-Feb-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 38.00 19.00


RCP Concert
Casting RCP 42 - - 17.00
Production
RCP 48 1,167.00 5.00 1,172.00 211.00
1 21+100 No
RCP 36 30.00 30.00 27.00
RCP Concert
RCP 42 - -
Installed on Site
RCP 48 603.00 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concert L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concert Casting Production 1,311.00 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Wednesday 28-Feb-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Cement=10bag 1=Forman
Masonry construction for Retaining
1 42+014 42+019
Wall
8.44m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=4bag 1=Forman
pointing for Retaining wall and
3 47+082 Sand=0.9m3 1=Oprator
Checkdam (inlet and outlet) 6=Labor

Cement=4bag 1=Forman
pointing for Retaining wall and
4 46+791 Sand=0.9m3 1=Oprator
Checkdam (inlet and outlet) 6=Labor

Cement=2bag 1=Forman

5 46+517 Pointing for inlet and outlet masonry Sand=0.9m3 1=Oprator


6=Labor
Small Loader =1 Concrete=5.1m3 1=Forman
Concrete Casting for 48" PC(Pipe
6 21+100 5 by No. mixer=1 1=Oprator
Production)
Vibrator=1 3=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Thursday 29-Feb-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concert
Casting RCP 42 - - - 17.00
Production
RCP 48 1,172.00 5.00 1,177.00 206.00
1 21+100 No
RCP 36 30.00 - 30.00 27.00
RCP Concert
RCP 42 - - -
Installed on Site
RCP 48 603.00 - 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concert L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concert Casting Production 1,311.00 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Thursday 29-Feb-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Cement=10bag 1=Forman
Masonry construction for Retaining
1 42+014 42+019
Wall
8.44m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=4bag 1=Forman
pointing for Retaining wall and
3 47+082 Sand=0.9m3 1=Oprator
Checkdam (inlet and outlet) 6=Labor

Cement=4bag 1=Forman
pointing for Retaining wall and
4 46+791 Sand=0.9m3 1=Oprator
Checkdam (inlet and outlet) 6=Labor

Cement=2bag 1=Forman

5 46+517 Pointing for inlet and outlet masonry Sand=0.9m3 1=Oprator


6=Labor
Small Loader =1 Concrete=5.1m3 1=Forman
Concrete Casting for 48" PC(Pipe
6 21+100 5 by No. mixer=1 1=Oprator
Production)
Vibrator=1 3=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Friday 1-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 38.00 19.00


RCP Concert
Casting RCP 42 - - 17.00
Production
RCP 48 1,177.00 1,177.00 206.00
1 21+100 No
RCP 36 30.00 30.00 27.00
RCP Concert
RCP 42 - -
Installed on Site
RCP 48 603.00 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concert L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concert Casting Production 1,311.00 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Friday 1-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Cement=10bag 1=Forman
Masonry construction for Retaining
1 42+014 42+019
Wall
8.44m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=4bag 1=Forman
pointing for Retaining wall and
2 40+838 Sand=0.9m3 1=Oprator
Checkdam (inlet and outlet) 6=Labor

Cement=4bag 1=Forman
pointing for Retaining wall and
3 41+341 Sand=0.9m3 1=Oprator
Checkdam (inlet and outlet) 6=Labor

Cement=2bag 1=Forman

4 42+004 Pointing for inlet and outlet masonry Sand=0.9m3 1=Oprator


6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
6 42+019 42+024
Wall
8.75m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Saturday 2-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

S.No Station of production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concert
Casting RCP 42 - - - 17.00
Production
RCP 48 1,177.00 1,177.00 206.00
1 21+100 No
RCP 36 30.00 - 30.00 27.00
RCP Concert
RCP 42 - - -
Installed on Site
RCP 48 603.00 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concert L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concert Casting Production 1,311.00 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Saturday 2-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
loader Cement=10bag 1=Forman
Masonry construction for Retaining
1 42+014 42+019
Wall
8.44m3 Sand=0.9m3 1=Oprator Comp
6=Labor

Cement=4bag 1=Forman
Checkdam construction (inlet and
2 40+838 5.2m3 Sand=0.9m3 1=Oprator
outlet) 6=Labor

Cement=4bag 1=Forman
pointing for Retaining wall and
3 42+545 Sand=0.9m3 1=Oprator
Checkdam (inlet and outlet) 6=Labor

Cement=2bag 1=Forman

4 40+619 Pointing for inlet and outlet masonry Sand=0.9m3 1=Oprator


6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
5 42+019 42+024
Wall
8.75m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Sunday 3-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,177.00 1,177.00 206.00
1 21+100 No
RCP 36 30.00 - 30.00 27.00
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Sunday 3-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Cement=10bag 1=Forman
Masonry construction for Retaining
1 42+019 42+024
Wall
8.75m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=4bag 1=Forman

2 43+900 Pointing for inlet and outlet masonry Sand=0.9m3 1=Oprator


6=Labor

Cement=4bag 1=Forman

3 45+745 Pointing for inlet and outlet masonry Sand=0.9m3 1=Oprator


6=Labor

Cement=2bag 1=Forman

4 46+072 Pointing for inlet and outlet masonry Sand=0.9m3 1=Oprator


6=Labor

Cement=4bag 1=Forman

5 46+333 Pointing for inlet and outlet masonry Sand=0.9m3 1=Oprator


6=Labor
1=Forman

6 42+019 42+024 installation of Weephole 8.48m 1=Oprator


6=Labor
1=Forman
7 42+019 42+024 installation of Expansion Joint 11.82m2 1=Oprator
6=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Monday 4-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 12 °C Max 24
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,177.00 1,177.00 206.00
1 21+100 No
RCP 36 30.00 - 30.00 27.00
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Monday 4-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 12 °C Max 24
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Cement=10bag1=Forman
Masonry construction for Retaining
1 42+019 42+024
Wall
8.75m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=10bag1=Forman
Masonry construction for Retaining
2 42+024 42+029
Wall
8.68m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=10bag1=Forman
Masonry construction for Retaining
3 42+029 42+034
Wall
7.92m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=10bag1=Forman
Masonry construction for Retaining
4 42+034 42+040
Wall
7.17m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Tuesday 5-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 12 °C Max 24
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,177.00 1,177.00 206.00
1 21+100 No
RCP 36 30.00 - 30.00 27.00
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Tuesday 5-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 12 °C Max 24
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Cement=10bag 1=Forman
Masonry construction for Retaining
1 42+019 42+024
Wall
8.75m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
2 42+024 42+029
Wall
8.68m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
3 42+029 42+034
Wall
7.92m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
4 42+034 42+040
Wall
7.17m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Wednesday 6-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 12 °C Max 24
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,177.00 1,177.00 206.00
1 21+100 No
RCP 36 30.00 - 30.00 27.00
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 - 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Wednesday 6-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 12 °C Max 24
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Cement=10bag 1=Forman
Masonry construction for Retaining
1 42+019 42+024
Wall
8.75m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
2 42+024 42+029
Wall
8.68m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
3 42+029 42+034
Wall
7.92m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
4 42+034 42+040
Wall
7.17m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Thursday 7-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 12 °C Max 24
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,177.00 1,177.00 206.00
1 21+100 No
RCP 36 30.00 - 30.00 27.00
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Thursday 7-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 12 °C Max 24
Station
Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power

Cement=10bag 1=Forman
Masonry construction for Retaining
1 42+019 42+024 8.75m3 Sand=0.9m3 1=Oprator Completed
Wall 6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
2 42+024 42+029
Wall
8.68m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
3 42+029 42+034
Wall
7.92m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
4 42+034 42+040
Wall
7.17m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Friday 8-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 12 °C Max 24
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,177.00 1,177.00 206.00
1 21+100 No
RCP 36 30.00 - 30.00 27.00
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Friday 8-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 12 °C Max 24
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Cement=10bag 1=Forman
Masonry construction for Retaining
1 42+024 42+029
Wall
8.68m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
2 42+029 42+034
Wall
7.92m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
3 42+034 42+040
Wall
7.17m3 Sand=0.9m3 1=Oprator 2C
6=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction
Niche Infrastructure Consulting with HUB Engineering
(ERA) Corporation (CCECC)

Time of Operation : Date:- Saturday 9-Mar-24


Weather:- Rainy
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,177.00 1,177.00 206.00
1 21+100 No
RCP 36 30.00 - 30.00 27.00
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 - 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction
Ethiopian Roads Administration (ERA)
Engineering Corporation (CCECC)

Time of Operation : Date:- Saturday 9-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station
Available Material Available Man
S.No Work Description Quantity Remark
From To Equipment Consumption power

No Structural Activity on this day!

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Sunday 10-Mar-24


Weather:- sunny, Rainy
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,177.00 1,177.00 206.00
1 21+100 No
RCP 36 30.00 - 30.00 27.00
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 - 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 - 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Sunday 10-Mar-24


Weather:- sunny, Rainy
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Available Material Available Man
S.No Work Description Quantity Remark
From To Equipment Consumption power

No Structural Activity on this day!

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Monday 11-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,177.00 1,177.00 206.00
1 21+100 No
RCP 36 30.00 - 30.00 27.00
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 - 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 - 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Monday 11-Mar-24


Weather:- sunny, Rainy
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Cement=10bag 1=Forman
Masonry construction for Retaining
1 42+024 42+029 26.04m3 Sand=0.9m3 1=Oprator 2C
Wall 6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
2 42+029 42+034 23.76m3 Sand=0.9m3 1=Oprator 2C
Wall 6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
3 42+034 42+040 21.51m3 Sand=0.9m3 1=Oprator 2C
Wall 6=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Tuesday 12-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,177.00 1,177.00 206.00
1 21+100 No
RCP 36 30.00 - 30.00 27.00
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 - 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Tuesday 12-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Cement=10bag 1=Forman
Masonry construction for Retaining
1 42+024 42+029 8.68m3 Sand=0.9m3 1=Oprator Completed
Wall 6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
2 42+029 42+034 7.92m3 Sand=0.9m3 1=Oprator 2C
Wall 6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
3 42+034 42+040 7.17m3 Sand=0.9m3 1=Oprator 2C
Wall 6=Labor

Excavator 1=Forman
Structural Excavation for Irrigation
4 21+653 79.39m3 1=Oprator completed
Cannel (Slab Culvert) 1=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Wednesday 13-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 12 °C Max 24
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,177.00 5.00 1,182.00 201.00
1 21+100 No
RCP 36 30.00 - 30.00 27.00
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 - 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Wednesday 13-Mar-24


Weather:- Rainy
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 12 °C Max 24
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Cement=10bag 1=Forman
Masonry construction for Retaining
1 42+029 42+034 7.92m3 Sand=0.9m3 1=Oprator Completed
Wall 6=Labor

Cement=10bag 1=Forman
Masonry construction for Retaining
2 42+034 42+040 7.17m3 Sand=0.9m3 1=Oprator Completed
Wall 6=Labor
Excavator 1=Forman
Structural Excavation for Irrigation
3 21+653 34.09m3 1=Oprator Completed
Cannel (Slab Culvert) 1=Labor
Small Loader =1 Concrete=5.1m3 1=Forman
Concrete Casting for 48" PC(Pipe
4 21+100 5 by No. mixer=1 1=Oprator
Production) Vibrator=1 3=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Thursday 14-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,182.00 5.00 1,187.00 196.00
1 21+100 No
RCP 36 30.00 30.00 27.00
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Thursday 14-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Small Loader =1 Concrete=5.1m3 1=Forman
Concrete Casting for 48" PC(Pipe
1 21+100 5 by No. mixer=1 1=Oprator
Production) Vibrator=1 3=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Friday 15-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 12 °C Max 24
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,187.00 5.00 1,192.00 191.00
1 21+100 No
RCP 36 30.00 - 30.00 27.00
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 - 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 - 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Friday 15-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 12 °C Max 24
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Small Loader =1 Concrete=5.1m3 1=Forman
Concrete Casting for 48" PC(Pipe
1 21+100 5 by No. mixer=1 1=Oprator
Production) Vibrator=1 3=Labor
Excavator 1=Forman
Lean Concrete Casting for Irrigation
2 21+653 30.51m2 1=Oprator Completed
Cannel (Slab Culvert) 1=Labor
Excavator 1=Forman
Lean Concrete Casting for Irrigation
3 18+630 33.38m2 1=Oprator Completed
Cannel (Slab Culvert) 1=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Saturday 16-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,192.00 1,192.00 191.00
1 21+100 No
RCP 36 30.00 - 30.00 27
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 - 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 - 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Saturday 16-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
15cm Foundation Pad Concrete Excavator Rein=0.17tone 1=Forman

1 21+653 Casting for Irrigation Cannel (Slab 4.33m3 1=Oprator Completed


Culvert) 1=Labor

15cm Foundation Pad Concrete Excavator Rein=0.19tone 1=Forman

2 18+630 Casting for Irrigation Cannel (Slab 4.74m3 1=Oprator Completed


Culvert) 1=Labor
Excavator 1=Forman
Check dam and Paved Water way
3 42+004 5.36m3 1=Oprator Completed
Construction for PC with RW 1=Labor
Excavator 1=Forman

4 42+000 42+040 Pointing for RW 1.8m3 1=Oprator Completed


1=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Sunday 17-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,192.00 5.00 1,197.00 186.00
1 21+100 No
RCP 36 30.00 - 30.00 27
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 - 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Sunday 17-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Small Loader =1 Concrete=5.1m3 1=Forman
Concrete Casting for 48" PC(Pipe
1 21+100 5 by No. mixer=1 1=Oprator
Production) Vibrator=1 3=Labor
Excavator 1=Forman
Masonry Construction for Irrigation
2 18+630 33.51m3 1=Oprator on progress
Cannel (Slab Culvert) 1=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Monday 18-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,197.00 5.00 1,202.00 181.00
1 21+100 No
RCP 36 30.00 - 30.00 27
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 - 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 - 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Monday 18-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity M3 Available Equipment Remark
From To Consumption power
Small Loader =1 Concrete=5.1m3 1=Forman
Concrete Casting for 48" PC(Pipe
1 21+100 5 by No. mixer=1 1=Oprator
Production) Vibrator=1 3=Labor
Excavator 1=Forman
Masonry Construction for Irrigation
2 18+630 33.51m3 1=Oprator Completed
Cannel (Slab Culvert) 1=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Tuesday 19-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,202.00 1,202.00 216.00
1 21+100 No
RCP 36 30.00 - 30.00 27
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 - 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Tuesday 19-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity M3 Available Equipment Remark
From To Consumption power
Excavator 1=Forman
Masonry Construction for Irrigation
1 21+651 30.8m3 1=Oprator on progress
Cannel (Slab Culvert) 1=Labor
Excavator 1=Forman

2 18+630 Paved Water Way and Plastering 3.2m3 1=Oprator Completed


1=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Wednesday 20-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,202.00 1,202.00 216.00
1 21+100 No
RCP 36 30.00 - 30.00 27
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 - 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Wednesday 20-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Excavator 1=Forman
Masonry Construction for Irrigation
1 21+651 30.8m3 1=Oprator completed
Cannel (Slab Culvert) 1=Labor
Excavator 1=Forman

2 22+130 Structural Excavation for Slab Culvert 74.3m3 1=Oprator Completed


1=Labor
Excavator No.of Pipe=8 1=Forman
Demolish Existing Structure Type C
3 22+130 8.17m3 1=Oprator Completed
inlet and outlet with 48" PC 1=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Thursday 21-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,202.00 1,202.00 216.00
1 21+100 No
RCP 36 30.00 - 30.00 27
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 - 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 - 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Thursday 21-Mar-24


Weather:- sunny and Rainy
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Excavator 1=Forman

1 21+651 Paved Water Way and Plastering 3.2m3 1=Oprator Completed


1=Labor
Excavator 1=Forman

2 23+904 Structural Excavation for Slab Culvert 96.4m3 1=Oprator Completed


1=Labor
Excavator 1=Forman
1st layer Structural Backfill and FDT
3 18+630 2.75m3 1=Oprator Completed
(BHS) 1=Labor
Excavator 1=Forman
2nd layer Structural Backfill and FDT
4 18+630 2.75m3 1=Oprator Completed
(BHS) 1=Labor
Excavator 1=Forman
Masonry Construction for Type A
5 22+130 drop inlet and Type C Outlet-Town 7.72m3 1=Oprator on Progress
Section drop Gutter 1=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Friday 22-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,202.00 1,202.00 216.00
1 21+100 No
RCP 36 30.00 - 30.00 27
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 603.00 780.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 - 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Friday 22-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power
Excavator 1=Forman
3rd layer Structural Backfill and FDT
1 18+630 2.75m3 1=Oprator Completed
(BHS) 1=Labor

Masonry Construction for Type A Excavator 1=Forman

2 22+130 drop inlet and Type C Outlet-Town 7.72m3 1=Oprator on Progress


Section drop Gutter 1=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction
Niche Infrastructure Consulting with HUB Engineering
(ERA) Corporation (CCECC)

Time of Operation : Date:- Saturday 23-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of Produced
S.No production Summery of this day produced Unit
previously
Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,202.00 1,202.00 181.00
1 21+100 No
RCP 36 30.00 - 30.00 27
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 603.00 25.00 628.00 755.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 - 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting China Civil Engineering Construction
Ethiopian Roads Administration (ERA)
with HUB Engineering Corporation (CCECC)

Time of Operation : Date:- Saturday 23-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Available Material Available Man
S.No Work Description Quantity Remark
From To Equipment Consumption power
Masonry Construction for Excavator 1=Forman
Type A drop inlet and Type C
1 22+130 7.72m3 1=Oprator on Progress
Outlet-Town Section drop 1=Labor
Gutter
Excavator 1=Forman

2 22+130 Pipe installation 25 1=Oprator on Progress


1=Labor
Excavator 1=Forman
Pipe Ring Pointing and
3 22+130 1.2m3 1=Oprator on Progress
Plastering inside and outside 1=Labor

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Sunday 24-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,202.00 1,202.00 181.00
1 21+100 No
RCP 36 30.00 - 30.00 27
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 628.00 - 628.00 755.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 - 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Sunday 24-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-
STRUCTURE DAILY SITE WORK INSPECTION REPORT

PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Ethiopian Roads Administration China Civil Engineering Construction Corporation
Niche Infrastructure Consulting with HUB Engineering
(ERA) (CCECC)

Time of Operation : Date:- Monday 25-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Pre cast units produced

Station of
S.No production Summery of this day produced Unit Produced previously Today Produced To date produced Remaining

Pipe (RCP) Production

RCP 36 38.00 - 38.00 19.00


RCP Concrete
Casting RCP 42 - - - 17.00
Production
RCP 48 1,202.00 1,202.00 181.00
1 21+100 No
RCP 36 30.00 - 30.00 27.00
RCP Concerte
RCP 42 - - -
Installed on Site
RCP 48 628.00 - 628.00 755.00

Ditch cover
A. PEDESTRIAN CROSSING
W= 1370
9.00 - 9.00
Ditch Cover Concerte L=500 H=120
Casting Production W= 1570
- - -
L=500 H=120
2 21+100 W= 1370
No
- - -
Ditch Cover Installed L=500 H=120
on Site
W= 1570
- - -
L=500 H=120
B. VEHICLE CROSSING
W= 1370
- - -
Ditch Cover Concert L=500 H=200
Casting Production
W= 1570
- - -
L=500 H=200
3 21+100 No
W= 1370
- - -
Ditch Cover Installed on L=500 H=200
Site
W= 1570
- - -
L=500 H=200
Guide post and KM post
Guide post/ROW Demarcation Concerte Casting Production 1,311.00 - 1,311.00 823.00
4
Guide post/ROW Demarcation Installed on Site - - -
21+100 No
KM post Concert Casting Production - - - 118.00
5
KM post Installed on Site - - -
FootWay
Concrete Tiles Produaction ( 300 mm * 300mm * 50 mm thick ) - - - 34100m2
6 21+100 M2
Concrete Tiles Placing on site ( 300 mm * 300mm * 50 mm thick ) - - -

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE

Signature:- Signature:- Signature:-


STRUCTURE DAILY SITE WORK INSPECTION REPORT
PROJECT NAME: KESSA GIMJABET AZENA AMBELLA Road Project

EMPLOYER CONSULTANT CONTRACTOR


Niche Infrastructure Consulting with HUB China Civil Engineering Construction Corporation
Ethiopian Roads Administration (ERA)
Engineering (CCECC)

Time of Operation : Date:- Monday 25-Mar-24


Weather:- sunny
8:00 AM To 11:00 PM
Temperature at 8:00 AM:- Min 24 °C Max 31
Station Material Available Man
S.No Work Description Quantity Available Equipment Remark
From To Consumption power

Challenges Encountered:-

Prepared by:- Zerihun Mulugeta Checked by ;- Contractor Verified by:- RE/ARE


Signature:- Signature:- Signature:-

You might also like