1. Introduction......................................................................................................................................................4
2. Scope................................................................................................................................................................4
3. Equipment & Materials....................................................................................................................................4
4. Grouting Material and Equipment....................................................................................................................4
5. Construction of Consolidation Grouting...........................................................................................................5
6. Eliminating Measures of Waste, Residue,Slurry and Water.............................................................................7
7. Safety Measures...............................................................................................................................................8
1. Introduction
2. Scope
This method statement is applicable for consolidation grouting of rock masses using cement grout mix.
The drill-hole operation of the consolidation grouting construction is drilled with the hydraulic drill,and
the inspection hole uses the geological drilling rig for construction. 3SNS high pressure grout inject
pump. Machine in the slurry station is the NJ-400 type high speed mixer wiith small size and strong
production capacity.
a) Drilling holes
b) Cleaning and washing holes
c) Testing holes - water pressure testing,
d) Grouting holes, and
e) Testing the grouted zone for efficacy of grouting
Drilling will be done by hydraulic drilling method. The grout hole of 50mm diameter and the depth
should be between 0.75 D and D where D is the finished diameter of the tunnel, except in special
reaches where it could be more. The maximum depth is 15m as per IS 5878-PARTVII-1972.
After completion of drilling up to required depth and while retrieval of drill rod from the bore hole
flushing of bore hole shall be done.
For consolidation grounting, the drilling and grouting are recommended to be done from invert
upwards doing the crown holes last. However, where the invert hole is exactly at the bottom and it
cannot be drilled and grouted without interfering with other operations in the tunnels this should be
done last.
Pattern of grout holes can be hexagonal pattern or set of holes in one vertical plane.
7. Safety Measures
The following safety measures shall be followed during the entire construction work:
1) Experienced Crews of Drillers and assistants shall be engaged in works. All the rotating parts will
be guarded.
2) House-keeping to be done on daily basis. ,
3) Hard hats, reflecting jackets, steel toe-capped footwear and necessary PPE will be worn by all
workers at all time during their presence at site.
4) No loose clothing shall be worn by workmen while working at site. Safety induction and tool
box talk shall be conducted periodically.
5) All workers shall be trained for awareness and sequence of operation. Fire extinguishers shall
be in place.
6) First aid kit and first aider must be available for entire duration of work