ELECTRICAL CIRCUITING VOLTAGE DROP CLACULATIONS

CABLE ROUTE LOAD CABLES


SN. Supply No of CKT No of Voltage
FROM TO Connected Load Power Demand Load Demand Voltage Phases Breaker Luminaires Cable size Type R X Grounding Installation Length to 1st Total Length drop (%)
(W) Factor (VA) Load (A) (Sq.mm) (Sq.mm) Luminaire (m) (m)
1 ALP-1 ALP-1/1 1,500 0.85 1,765 2.55 400 3 25 6 10 Cu.XLPE.Multi 2.33 0.1111 10 Direct burried 50 300 0.51%
2 ALP-1 ALP-1/2 2,400 0.85 2,824 4.08 400 3 25 24 10 Cu.XLPE.Multi 2.33 0.1111 10 Direct burried 50 1,200 2.43%
3 ALP-1 ALP-1/3 2,400 0.85 2,824 4.08 400 3 25 24 10 Cu.XLPE.Multi 2.33 0.1111 10 Direct burried 100 1,250 2.61%
4 ALP-1 ALP-1/4 2,400 0.85 2,824 4.08 400 3 25 24 10 Cu.XLPE.Multi 2.33 0.1111 10 Direct burried 20 1,170 2.32%
5 ALP-1 ALP-1/5 2,400 0.85 2,824 12.28 230 1 25 24 10 Cu.XLPE.Single 2.33 0.137 10 Direct burried 50 1,200 26.29%
6 ALP-1 ALP-1/6 2,400 0.9 2,667 3.85 400 3 25 24 10 Cu.XLPE.Multi 2.33 0.1111 10 Direct burried 50 1,200 2.41%
7 ALP-1 ALP-1/7 2,400 0.9 2,667 3.85 400 3 25 24 10 Cu.XLPE.Multi 2.33 0.1111 10 Direct burried 100 1,250 2.59%
8 ALP-1 ALP-1/8 2,400 0.9 2,667 3.85 400 3 25 24 10 Cu.XLPE.Multi 2.33 0.1111 10 Direct burried 20 1,170 2.31%
9 ALP-1 ALP-1/9 2,400 0.9 2,667 11.59 230 1 25 24 10 Cu.XLPE.Single 2.33 0.137 10 Direct burried 50 1,200 26.09%