Manutenção Elétrica Guindaste Subsea
Manutenção Elétrica Guindaste Subsea
Manutenção Elétrica Guindaste Subsea
Revision 0
Page 47
The electric system includes the electric motor with starter cabinet, slipring unit, control
panel and electric cables in general.
Hardware is all electric equipment of which the control system consists. The
maintenance consists of:
- Checking that all connections are properly tightened.
- Checking that all relays are properly mounted in their sockets.
- Checking that all relays aÍe functioning as provided.
NOTE Earth faults or short circuit can lead to total stoppage of the crane
Software are all programs loaded. The crane is dependent of the programs being
constantly running, and that transmission of signals is not intruded. A fault in a program
will either lead to a stop in program routines or wrong logical function. Fault could also
be indicated by "ERROR" - indication at PLC CPU/Power module.
wrvw.nov,com
c ATIO AL OIIJÚELI YANGO
Document number T5395-Z-MA-005
Revision 0
Page 48
NOV's serviceman should check crane control system (CCS) every second year. This
also includes re-calibration of load cells, pressure transmitters, temperature
transmitters, angle transmitters and flow transmitters.
The motor has greased bearing. The lubrication points are located in each end of the
motor. Follow the periodic maintenance schedule.
Ensure that motor has sufficient cooling and still stand heating is functioning. Ensure
that motor is not subject to oil or water leaks.