Professional Documents
Culture Documents
Chapter 1 QSE
Chapter 1 QSE
Chapter 1 QSE
Estimating
➔ Before taking up any work, the owner should know the total volume of work and its
probable cost required to carry out the proposed project.
➔ Estimating for any construction work may be defined as the process of calculating
quantities and costs of various items required in connection with the work.
➔ An estimate is worked out from the dimensions on the drawings.
➔ An estimate is prepared by calculating the quantities of items from the drawings and then
multiplying them with the unit cost of concerned item.
➔ The accuracy of an estimate depends on careful study of various dimensions on drawings,
the method of estimating, consideration of rates, probable unforeseen expenses and also
quantity of tolerance for wastages.
➔ Estimating = quantity surveying
Costing
➔ Costing is defined as the process of finding out the probable cost of work before starting
that work.
➔ It is prepared considering the standard rates at the time of making an estimate.
PURPOSE:
1. To determine the necessary amount of money required by the owner to complete the
proposed work. For public works, an estimate is required to obtain administrative,
technical sanction and budget provision.
2. To find out quantities of materials required for their timely procurement.
3. To calculate the number of different categories of workers to be employed for timely
completion of work.
4. To check the requirement of tools, plants and equipment required.
5. To fix the completion period from the volume of work.
6. To prepare a construction schedule and arrange for funds accordingly.
7. To justify the investment from the Benefit-Cost ratio. (Ideally > 1)
8. To invite tenders.
9. To prepare bills for payment.
10.An estimate of an existing property is required for its valuation.
11.Alterations in specifications, drawings and estimates can be done if the costing of the
project is above the budget available.
1. PROCEDURE OF EXECUTION OF WORK BY PWD (Public WorksDepartment)
Government
↓
Secretary to Government
↓
↓
↓
↓
↓
↓
Supervisor
↓
Workers
CHIEF ENGINEER:
1. To submit proposals to the government regarding new works and maintenance works in his
area (zone / circle / region).
2. To give approval for projects.
3. To accept tenders for works by contract method.
4. To give ‘Technical Sanction’ for works.
5. To coordinate with the Accountant General of State regarding expenditure in his area.
SUPERINTENDING ENGINEER:
1 . To keep administrative and technical control of his circle.
2. To do inspection of works in his circle.
3. To arrange for procurement of stores.
4. To do inspection of divisions in his circle and report to the Chief Engineer.
5. To keep financial control on execution of works.
EXECUTIVE ENGINEER:
1 . To check whether proper approval, technical and financial sanction is given for the work.
2. To do effective supervision on the works in his division.
3. To see that the contractor's accounts are properly maintained and regularly submitted to the
competent authority.
4. To collect money from the project fund and give it to the payment of the contractor.
5. To inspect offices of AE / SDO once in a year.
6. To ensure that all tools and equipment are properly maintained.
ASSISTANT ENGINEER:
1 . To check muster roll.
2. To maintain all buildings and roads.
3. To physically verify dead stock in a year.
4. To maintain construction accounts.
5. To check the works in progress.
JUNIOR ENGINEER:
1 . To take measurements of all works and note it down in ‘Measurement Book’.
2. To check whether works are done according to ‘Specifications’.
3. To prepare an estimate of work.
4. To prepare ‘Running Bill’ and ‘Final Bill’.
5. To supervise the works in his charge.
C.PWD PROCEDURE OF INITIATING WORK:
➔ For any new work, the concerned department prepares a proposal report regarding the
cost of work and its necessity.
➔ After studying the proposal, the department will then proceed for ‘Administrative
Approval’.
➔ The Engineering Department will then prepare detailed drawings, designs, estimates and
submit the same to higher authorities for ‘Technical Sanction’.
➔ The competent authority studies the detailed drawings, designs, estimates carefully and
verifies it according to the rules stated and then provides ‘Technical Sanction’.
➔ Then the ‘Budget Provision’ is made for the project as per the government plan.
➔ The execution of work is then started by that contractor whose tender is selected.
PRINCIPLE OF UNITS:
1 . Mass, voluminous and thick works are measured inm3 (cubic meter)
2. Shallow, thin and surface works are measured inm2(square meter)
3. Long and thin works are measured inm (meters orrunning meters / RMT)
4. Piece works are measured innumbers
MODES OF MEASUREMENT:
ARTHWORK
E
Earthwork in excavation 3
m
Earth filling, cutting m3
Surface dressing m2
Cutting of trees numbers
Puddling m3
Quarrying of stones m3
Blasting of rock m3
For excavation Lead = 30m and Lift = 1.5m
CONCRETE
Lime concrete 3
m
Plain cement concrete m3
Reinforced cement concrete m3
Cement concrete grill work m2
DAMP PROOF COURSE (DPC)
DPC m2
BRICKWORK
Brickwork masonry 3
m
Half brick thick brickwork m2
Thin partition wall m2
Jack arch roofing including top finishing m2
Coping, Cornice, Porgetting, Bridge edging m
Honey comb brickwork m2
STONEWORK
Stone masonry 3
m
Cut stone work in lintel, beam m3
Stone slab in roof, shelve, sill, stone chajja (thickness specified) m2
Stone work in wall facing or lining (thickness given) m2
WOOD WORK
Wood work in door and window frame, rafter, truss 3
m
Door and window shutters (thickness specified) m2
Door and window fittings numbers
Timbering (thickness specified) m2
Sawing of timber m2
Wood work in partition, Plywood m2
Panel work m
STEEL WORK
Rolled steel Joists, Channel, Tee, Angle, Flat uintal
q
Steel reinforcement bars quintal
Bending, binding quintal
Fabrication and hoisting quintal
Fabric reinforcement, wire netting m2
usset plate
G uintal
q
Cutting of Joists, Channels cm
Cutting of Angles, Tees, Plate cm2
Threading cm
Welding, soldering cm
Boring holes numbers
Cast iron (CI) pipe (diameter specified) m
Rivets, bolts, nuts quintal
Barbed wire fencing m
Railing m
Iron grill, collapsible gate m2
Rolling shutter m2
Steel doors and windows m2
ROOFING
Tiled roof (any tile) 2
m
Timber roofing m2
Thatch roofing m2
Eaves board (thickness specified) m2
RCC slab roof m3
Mud roof or Lime concrete roof over brick (thickness specified) m2
Ridges, valleys, gutters m
Tar felting, Bituminous painting m2
Insulating layer in roof of sand and clay, asphalt etc. m2
Expansion or contraction construction joint m
Ceiling – Timber, AC sheet, Paste board, False m2
Centring and shuttering, formwork m2
PLASTERING, POINTING AND FINISHING
Plastering (any type) (thickness and proportion specified) 2
m
Pointing m2
Dado (thickness specified) m2
Skirting (thickness and height specified) m
Cement or lime mortar rubbing m2
White washing, Colour washing m2
Distempering m2
Painting, Varnishing m2
Polishing of wood work m2
Painting letters and figures numbers
Oiling and clearing of doors and windows m2
Coal tarring m2
Removal of paint or varnish m2
FLOORING
Flooring (any tile, any thickness and over any layer) 2
m
Apron or Plinth protection m2
Door and window sill slab work m2
ISCELLANEOUS WORKS
M
Plumbing fixtures and fittings umbers
n
Site clearance Lumpsum
1. Measurement shall be item wise for the finished item of work and its description shall
include materials, transport, labour, fabrication, hoisting, tools and plants, overheads,
shape, size, design and specifications.
2. While recording measurements, the order shall be in the sequence of length, breadth and
height or depth or thickness.
3. All works shall be measured net subject to following tolerances unless otherwise stated:-
a) Dimensions shall be measured to the nearest0.01 m.
b) Areas shall be measured to the nearest0.01m2.
c) Cubic contents shall be measured to the nearest0.01 m3.
d) Weights shall be measured to the nearest0.01Kg.
4. Same type of work under different conditions and nature shall be measured separately
under separate items.
5. The bill of quantities shall fully describe materials, proportions and workmanship.
6. In case of structural concrete, brickwork, stone masonry, the following categories shall be
considered for measuring separately with height:-
a) Foundation to Plinth level.
b) Plinth level to First floor level.
c) First floor level to Second floor level and so on.
d) Parapet is measured with corresponding lower floor.
MEASUREMENT SHEET:
Wi Hei
It Len
d g
e N gt
t h
m
o h Quant
Description h t
n s ( ity
( (
o . m
m m
. )
) )
ABSTRACT SHEET:
It
Per
e
u
m Quan Rate Cost
Description n
n tity (̀ ) (̀ )
i
o
t
.
FACE SHEET:
Sr.
N Particulars Amount
o
Rs
_____________________
__
+
Rs
_____________________
__
Rs
_____________________
__