Installation Qualification – Site Preparation Specification

Instrument Details Model Serial Number


Ref: IQ - 4

Yes/No Comment
Ventilation: Position of Extraction Fan
Ref: IQ - 5 Air Flow of Extraction Fan

Allocated Bench: Both Sides of Instruments


Ref: IQ - 6 Rear of Instrument
Horizontal
Sufficient Strength

Instrument Appearance: Atomizer Clean


Ref: IQ - Instrument Appearance Clean

Preparation Checklist: PC Date & Time Configured Correctly


Ref: IQ - 8 AAWin® Software Installed Successfully
Instrument Successfully Initialised Through AAWin®

Specification Result Pass/Fail Comment


Environmental Conditions: Ambient Temperature 15 to 30˚C
Ref: IQ - 9 Relative Humidity 10 to 70%

Gas Source Requirements: Air Supply Line Pressure


Ref: IQ - 10 Purity
Acetylene Gas Source Regulator Pressure
Safety Leak Test
Purity
Argon Gas Source Regulator Pressure
Safety Leak Test
Purity
Oxide Gas Source Nitrous Regulator Pressure
Safety Leak Test
Propane Gas Source Regulator Pressure
Safety Leak Test
Installation Qualification – Site Preparation Specification
(500G/FG only) Specification Result Pass/Fail Comment
Water Source Requirements: Water Source Cooling Water Circulator
Ref: IQ - 11 Water Pressure/Flow

Stable Voltage
AC220V/AC120V(10%)5A
Power Supply Conditions: Base Unit Power Supply
Ref: IQ - 12 Grounding

Stable Voltage
AC220V(10%)40A
Graphite Furnace Power
Grounding

The following signatures confirm that this section of the Installation Qualification has been performed with strict adherence to the instructions in the Qualification Workbook.

Additional Comments:

Executed by: Name: Signature: Date:

Reviewed by: Name: Signature: Date: