Professional Documents
Culture Documents
10 1109@icpere 2018 8739735
10 1109@icpere 2018 8739735
ICPERE 2018
Abstract— The airport powersystem has the same elements as the such as transformers or capacitors [4]. Relay is a protection
Indonesia Electricity Company (PLN) system, which is consists of component that works by monitoring the current and voltage
generation, transmission and distribution. The main power level of system to detect any interference. The two types of
source not only supplied by PLN, but also can be obtained from relays used in this final project, Over Current Relay (OCR) and
the generator set. High reliability of power systems is needed to Ground Fault Relay (GFR), were sensitive to over current, and
supply vital equipment and essential facilities, such as runway will work if the current flowing (If) exceeds the current value
lights, telecommunication system in control tower, data of the setting (Iset) [5].
processing computer, radar navigation system and other
facilities. To be able to provide reliable service, the power system II. PROTECTION SYSTEM
must remain intact and able to overcome various kinds of faults
that may occur. Therefore, the coordination of the protection A. Disturbance Source In Electric Power System
system has important role in maintaining the continuity and In a three phase electrical power system, there is
reliability of the power system. In this study, overcurrent relay interference that may cause overcurrent, such as overload, short
and ground fault relay were used. The result was revealed by circuit, and overvoltage disturbances [2].
graphical images in the form of a current-time curve. This study
suggested the coordination arrangement of over current relay at B. Adjustment of Phase Disturbance Excess Current Relay
Samarinda Airport to estabalish more reliable current relay Current adjustment for excess currents has current
coordination.
magnitudes limits. The overcurrent setting limit define as the
Keywords- Ground Fault, Phase Fault, Relay coordination relay should avoid to work at maximum load. The current
specified setting must be greater than the maximum load
I. INTRODUCTION current.
At the airport electrical system, a high reliability is required
to supply vital equipment, such as telecommunications systems
in control towers, on-run lights and data processing computers.
In order to obtain continuity of good power distribution, a
power system must be designed in such a way as to have a high
degree of reliability. One way is to design good coordination of
protection. The protection system is designed to detect
interference and minimize the affected area [1].
Interference is defined as a physical condition caused by a
device, component or an element failure to work in accordance
with its function [2]. The term interference is identical with
short circuit. Short circuit failure may cause damage to the
equipment and interrupt the continuity of power services [3].
Based on the impact, the disturbance may consist of temporary
and permanent disruption. Temporary disturbance can occur Figure 1. Limit of current setting accuracy based on BS 142-1983
due to flashover lightning. Most temporary disturbances can be
secured with circuit breakers or other safeguards, and the Based on Figure 1, the adjustment limit should consider
system can still run after interruption has been disconnected. about error pick up, according to the British BS
While permanent disturbance is a disturbance that can cause
permanent damage to the system. Such as the failure of the 142-1983 standby limit between 1.05 - 1.3 Iset. According
insulator, damage to the carrier as well as damage to equipment to it, this final project used constant of 1.05 Iset. It can be seen
as follows :
2A31-2 The 4th IEEE Conference on Power Engineering and Renewable Energy
ICPERE 2018
Iset≥ 1.05 x Inominal (1) regions namely the low-voltage side (LV) and high-voltage
side (HV) [8]. Figure 3 shows the illustration of two bus
I set divide by transformator.
Is = (2)
rasio_ct
Where : Waktu (detik) Time (second)
Is = current setting
Selection of tap used = Is / In
Actual current setting Iset = tap x In x CT
Search for the nearest value below the result.
In excess relay settings, the limit maximum setting is need
to be considered for security reasons and back up to the t = 80 milidetik T = 80 milisecond
I set ≤ 0.8 I sc 2, min (3) Figure 2. Characteristic of instant excess current relay
Bus B (LV)
C. Adjustment of Phase Disturbance Excess Current Relay
Figure 3. Safety of Transformator for excess current relay
Release time is determined by dial time setting.
Determining of dial time of excess current relay in each curve The terms of instant pickup setting on the coordination type
inverse can be used the follow equation : must fulfill the following conditions [7]:
td = (5) Isc max bus B ≤ Iset ≤ 0.8 Isc min bus, A (7)
ground. In the ground fault relay, the range used is 20% - 80% 1. Typical 1
of the current ratting or even lower, 10% - 40% [7], other
references use 10% - 50% [3]. This beam release will be Coordination of phase excess current protection using 3
activated if the remaining current Ires = Ia+Ib+Ic that flows up relays i.e CB1, CB7 and LVCB 8. Starting from Grid PLN_1,
exceeds the treshold setting [5] [7]. main panel bus to PTR 1 bus.
Tap selected = 1.95 In (Pickup Range 0.3 In– 2.4 In, with Step
0.05In )
Dial Time :
Operation time selected (t) = 0.125 s
t= x
Td =
Td =
Td = 0.289
Td ≥ 0.289, Td selected = 0.5 (Range Td 0.05-3.2, with
step 0.01)
Instantaneous Pickup :
A≤ ≤ In
A≤ ≤ In
13.4 A≤ ≤ 279 In
selected = 15.9 A (Pickup Range 0.5 A – 175 A, with Figure 6. Curve of setting time coordination in typical 2a
Step 0.01A)
Actual value of =15.9 x 65/1 = 1034 A Based on Figure 6 can be concluded that:
1. CB12 relay secured T6 transformers, it worked
instantaneously, depending on the minimum short-circuit value
Delay Time :
of the middle voltage main panel and also the maximum short
Selected delay time was 0.125 s
circuit in the CHILLER 1_2 load bus. Delay time of CB12 was
0.125 so it was not affected the inrush transformer located at
The calculation result was plotted in the current curve 0.1 s.
of the current time condition setting in simulation software, it is
2. CB9 was a back-up relay when the underneath relays were
presented on Figure 6. The other relay calculation for noise of
not capable of securing a short-circuit noise in the main panel.
excess current relay phase also used the same method.
It worked based on the current contribution of the underload
2A31-2 The 4th IEEE Conference on Power Engineering and Renewable Energy
ICPERE 2018
buses, if there was a minimum short circuit in SST 2 CHILLER The current time curve of setting conditions was plotted in
ROOM. simulation software using the calculation results, the result is
D. Coordination of Ground Fault Relay Excess Current presented on Figure 7. The other relation of calculation for
Typical 2a excess current relay ground fault setting was used the same
method.
The ground fault relay was simulated using the similiar
type. An analysis of short circuit one-phase to ground fault
was done to determined the ground fault relay. In simulation V. CONCLUSION
of short circuit, one-phase fault to the ground was done on the Based on the result of study and analysis of security relay
buses in the typical that have been selected. coordination at Samarinda Airport which had been done,
hence taken some conclusion as follows:
1. Result of relay setting in accordance with the standard
time grading IEEE-242 was 0.2 seconds. It needs to be
considered because if delay time setting is not
appropriate and there is a relay fault, the backup will be
tripped because it does not provide enough time for the
main safety relay to disconnected the fault. Coordinate
errors are very common when setting time delay
occured.
2. Setting ground fault relay using definite curve due to
short circuit of ground fault.
3. The safety relay settings that was obtained and the
result of current curve plot can be used as consideration
and reference.
4. For further study can be done the development with arc
flash consideration in coordination of Samarinda
Airport protection in order to improve safety standards
on workers and operators who work in the panel.
REFERENCES
[1] I. o. E. a. E. Engineers, "IEEE Standard 242," in Protection and
Coordination of Industrial and Comercial Power System, ed, 2001.
[2] Lazar Irwin “Electrical System Analysis and Design for Industrial
Plant”, McGraw-Hill Inc., USA, Ch, 1, 1980.
Figure 7. Curve of setting time coordination in typical 4.b
[3] P. M. Anderson, Power System Protection. Pistacaway, NJ: IEEE Press,
1999.
CB11 Relay :
[4] Gurevich, Vladimir, "Electric Relays, Principle and Application ",
Manufacturer : Merlin Gerin CRCPress, USA, 2006.
Mode : SEPAM 1000 [5] IEEE std 242-2001, "IEEE Recommended Practice for Protection and
Curve Type : Definite Time Cordination of Industrial and Commercial Power System ", The Institute
CT Ratio : 65/1 of Electrical and Electronic Engineering, Inc, New York, 2001.
[6] Wadhwa, C.L., “Electrical Power Systems”, New Age Science, Ltd.,
Instantaneous Pickup : England, 2009.
[7] Préve, Christope, “Protection for Electrical Network”, ISTE Ltd.,
(5-15 %) Ingr < < 50 % Ingr London, 2006
[8] Phadke, Arun G, and Thorp, James S, “Computer Relaying for Power
(5-15%) 575< < 50% 575 System”, John Wiley and Sons, Ltd., England, 2009.
[9] Service Manual,“Overcurrent Relays for Phase and Earth Fault”, Merlin
Gerin, Schneider.
(28.75-86.73) < < 287.5 [10] Gers, Juan M., and Holmes, Edward J., “Protection of Electrical
Selected of = 30 A Distribution Network 2nd Edition”, The Institution of Electrical
Engineers, London, 2004.