QUALITY DEFECT DATA
Improvement plans are typically prioritized by:
• External Customers – Reacting to escapes
• Complexity
• Executive priority
3
This document does not contain any technical data ECCN: EAR99
DEFECT REDUCTION - DCERI
Defect category escape reduction initiative
0 0%
Dimensional Damage Part Marking Failed Casting / Raw Misassembly Leakage Contamination Testing Design /
Component Mat'l Producibility
0 0%
Diagnose the processes with poor yield and prescribe robust process controls 5
This document does not contain any technical data ECCN: EAR99
ELECTRONICS SUPPLIER EXAMPLE
Prioritize by Defect Categories vs. Part #s
Defects by Defect Categories
40 100%
35
30 80%
25 60%
20
15 40%
10 20%
5
0 0%
7
Defects by Part Numbers 100%
6
80%
5
4 60%
3 40%
2
20%
1
0 0%
Op 30
Op 90
Op 100
Op 190
Op 215
Op 240
Op 270
Op 280
Risk QMS
Containment Containment
Diagnose
Use your Q-Clinic to perform triage daily. Analyze defect data using MS
Excel. Include external escapes by customers (HS), internal MRB data, and
assign a defect category to each line item. Flow map and identify the key
processes within your value streams that generate the majority of defects.
Prescribe
Assign a team to each defect category with a 50% reduction goal within 6
months. Select the appropriate continuous improvement tool, predict
expected % reduction for each action item, executive Q reviews, ask for
8
help.
This document does not contain any technical data ECCN: EAR99
DEFECT CATEGORY ANALYSIS
Value Stream #1 Jan through Dec defects
Root Cause Defect Category Breakdown
160 100
90
140
80
120
70
100 60
80 50
40
60
30
40
20
20 10
0 Business
0
Failed Design/Produci Special Process Wrong
Dimensional Misassembly Part Marking Weight Damage Casting Contamination
Component bility Processes Documentatio Material
n
Shop 0 1 10 0 1 0 0 0 0 0 0 0
ENG 24 47 22 30 7 1 11 1 7 3 3 6
SCM 125 6 10 8 28 29 18 19 12 15 10 1
Cumulative % 33 45 54 62 70 77 83 87 92 96 98 100
9
This document does not contain any technical data ECCN: EAR99
DEFECT REDUCTION PLAN - SAMPLE
Correlate actions to results 2011 SCM Performance
2010 Performance – All Defects Root Cause Defect Category Breakdown
50% Reduction Goal
35 100 60
14
90
4E 30 5X
12 80 50
5X 25 5V
70
10 5V 40
60 5S
5S 20
8 50 5Q
5Q 15
30
6 40 5D
5E 10 30 20 5B
4 5D 20
5 Goal Line
2 5C 10 10
Cumulative
5B 0 0
0 Dimensional Damage Casting Contamination
Failed
Misassembly
Special
Wrong Material 0
Component Processes
November
December
January
May
June
August
September
April
October
March
July
May
August
September
April
March
July
2010
November
December
January
February
June
October
February
Shop 0 0 0 0 0 1 0 0
ENG 5 3 0 0 4 3 1 0
SCM 26 5 7 6 1 0 2 1
Cumulative % 48 60 71 80 88 94 98 100
No. Pareto of Input Drivers No. Pareto of Input Drivers Process Goal
Description
1 Dimensional Defects 4 Dimensional - Setup Pieces
Manufacture of Complex Eliminate Supplier #1’s
2 Casting CADs 5
Machine Parts Value Stream Interruptions
3 Contamination 6
2 Eliminate submittal of casting CADs to recoup machining costs 1/15/11 Jim 10% Reduction, Complete 2/10/11 2/10/11
3 Add bore scope inspection after milling operations 2/15/11 Peter 1% Reduction 5/2011 4/2011
3 Machine milled surfaces prior to anodize versus after anodize 2/15/11 Mary 1% Reduction 5/2011 6/2011
3 Green belt project using HS provided consultants 2/22/11 HS - Brian Initial walk the process complete 7/2011 7/2011
4 Create policy for setup pieces to be submitted on CAD 2/22/11 Jim 2% Reduction 3/15/11 3/12/11
This document does not contain any technical data ECCN: EAR99 10
STANDARD WORK
Process Control and Certification
Prioritization Define CTQ Baseline Process Process
Approval Characteristics Performance Control Certification
M0 M1 M2 M3 M4
Define program lead Define CTQ parts Determine key Data collection and Certify the process
Waterline CTQ parts process inputs analysis Cpk=1.33 +
Evaluate for safety Perform gage
Allocate funding Implement control Control plan in
capability study charts place
Determine key product
Establish milestone Prepare control plan
characteristics Evaluate process Self audit schedule
plan
Conduct key capability Cpk=1.0
Apply characteristics to characteristic review Action items closed
drawing –engineering Conduct process
change control review
11
This document does not contain any technical data ECCN: EAR99
Desired Quality Improvement System
ACCELERATING DEFECT REDUCTION
D D M A I C S
Customer
Satisfaction
M
Level Supplier
is Poor
Improvement
All Escapes by Category - 2005 & 2006
50
at HS 40
Fault
Dimensional
Marking
A
Contamination
Misassembly
Damage
Wrong Material
Packaging
30
Missing Features
20
10
Percent
Damage
60
Count
Wrong Material
25
Packaging 6
Missing Features 40
20 4
2 20
15
0 0
Defect Type Y
NG RE
10
ULT DIM AM BL
FA NT RKI M ATU
I
A
5 CO M A S SE FE
IS G
M S IN
0 IS
M
Honeywell-RM
Honeywell-Tempe
Honeywell-Int.
Honeywell-Eng.Sys.
Count 5 3 1 1 1 1
Percent 41.7 25.0 8.3 8.3 8.3 8.3
Cum % 41.7 66.7 75.0 83.3 91.7 100.0
Percent
10 60
Count
10 Packaging
Missing Features
8
8
40
6
6
4
20
4
2
2 0 0
C13 Honeywell-RM Honeywell-Tempe
0 Count 12 5
Honeywell-RM
Honeywell-Int.
Honeywell-Eng.Sys.
Honeywell-Tempe
CAB
Structure
S
Physical
Location
Layout
Performance People &
Review
Flow
Gauging
Metrics &
Equipment
Visual
Management
This document does not contain any technical data ECCN: EAR99
HS SUPPLIER QUALITY ENGINEERING
AMS success story 2011
AMS All Supplier's - Defect Reduction Performance
1600
1400
1200
1000
800
600
400
44% reduction in
200 Supplier Defects
0
2010 2011
Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
Total Goal
Actual 1377 37 38 65 72 66 84 44 89 45 67 78 83 964
Goal 80 161 241 321 402 482 562 643 723 803 884 964
YTD 37 75 140 212 278 362 406 495 540 607 685 768
13
This document does not contain any technical data ECCN: EAR99
HS SUPPLIER QUALITY ENGINEERING
AMS success story 2011
AMS Top 10 Supplier's - Defect Reduction Performance
500
450
400
350
300
250
200
150
100
66% reduction in
50 supplier defects
0
2010 2011
Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
Total Goal
Actual 467 8 4 14 16 8 34 4 11 20 14 16 18 327
Goal 27 54 82 109 136 163 191 218 245 272 300 327
YTD 8 12 26 42 50 84 88 99 119 133 149 167
14
This document does not contain any technical data ECCN: EAR99
QUESTIONS?
15
This document does not contain any technical data ECCN: EAR99
HS SUPPLIER QUALITY ENGINEERING
Support
For more information on using the DCERI methodology in your
Quality Clinic System to accelerate defect reduction contact:
Hamilton Sundstrand
Windsor Locks, CT
M/S 2-M-GG15
Phone: (860) 654-3381
Cell: (860) 904-3056
Fax: (860) 660-2599
e-mail:john.gaughan@hs.utc.com
16
This document does not contain any technical data ECCN: EAR99