Professional Documents
Culture Documents
HYCR Apr-Sept 22 SECL Kusmunda Area
HYCR Apr-Sept 22 SECL Kusmunda Area
HYCR Apr-Sept 22 SECL Kusmunda Area
KUSMUNDA AREA
Half yearly compliance
Of
Environment Clearance
Kusmunda OCP
50.00 MTPA (Normative)/62.5 MTPA (Peak)
KUSMUNDA AREA
CONTENTS
SL CHAPTER PAGE
01 EC COPY 7-21
02 DATA SHEET 23-33
03 Environment compliance 35-109
04 Annexures 111-875
LIST OF ANNEXURES ENCLOSED
PART –I
(General Particulars)
PART-II
1
5. Monitoring cell established Yes/No. if any Environment Management Cell is established at GM
no, give reasons. Office, Kusmunda Area & monitoring work is being done
by CMPDIL (an ISO 14001 certified company)
6. How regularly /Quarterly/Six monthly/ Last Six monthly Compliance report from October to
Progress reports are submitted to the March 2022 was sent vide letter no. 660 dated on
ministry. Details of last report submitted. 31.05.2022.
7. Firefighting system/Emergency plan details Fire extinguishers have been provided at all required
points
PART-III
(Rehabilitation/Reclamation/ Restoration Programme)
2
3. No of displaced persons/families employed Families to be displaced for additional Land of Phase-
kind of jobs. II- 6712
Employment given -2093 till 30.09.2022
1.Quantity of solid waste /OB produced/ 22.890 Million Cu. M. in year 2022-23(up to 30.09.22).
year wise
2. Location and total area to be reclaimed / The back filling of de-coaled area is already being
restored practiced to comply with the conditions and Biological
Reclamation with plantation is being regularly done on
back filled OB dumps by Chhattisgarh Rajya Van Vikas
Nigam (CGRVVN, a State Govt. Organization).
Since beginning of the project till date, Total
24.61 lakh no. of plants have been planted including
50,000 saplings planted under 2022-23 Plantation
Programme in SECL Kusmunda OCP
(As on 30.09.2022)
INTERNAL DUMP/BACK FILLED TOTAL RECLAIMED
EXTERNAL OB DUMPS DETAILS
AREA DETAILS EXTERNAL OB DUMP AREA
RECLAIMED AREAS
RECLAIMED/ BACK
RECLAIMED AREA
TOTAL AREA OF
AREA ALREADY
AREA ALREADY
BIOLOGICALLY
BIOLOGICALLY
BIOLOGICALLY
TECHNICALLY
TECHNICALLY
TECHNICALLY
TOTAL AREA
TOTAL AREA
EXCAVATED
RECLAIMED
RECLAIMED
RECLAIMED
FILLED
TOTAL
TOTAL
815.627 510.610 203.00 196.242 196.242 196.242 706.852 399.242
3
4. Facilities provided to collect industrial waste Presently, an RCC Settling Tank with Sludge Drying
water and sewage. Bed (Capacity: 540m3) has been constructed for
treatment of mine discharge water for industrial waste
water.
2MLD DETP of costing Rs.2.22 Crore is Constructed
For Drinking water
2 MGD Capacity Water Treatment Plant has been
installed
5. Quantity /day discharged industrial waste water/ Average Peak Daily Discharge –
domestic, point of discharge & location map. Industrial – 2779 m3/day
Domestic – 1326 m3/day
6. Monitoring of treated effluent frequency, No. of Frequency - Fortnightly
sampling points. Sampling points – 05 (Effluent)
Sampling points – 03 (Drinking water)
7. Air quality analysis & its Monitoring frequency, Frequency – Twice a week
No. of station Sampling station - 04 in core and 05 in buffer zone.
8. Noise pollution monitoring stations Frequency – Fortnightly
Sampling station - 04 in core and 05 in buffer zone.
Various Mitigative measures being taken at Kusmunda OCP to control dust & other fugitive
emissions are as follows:
Use of surface miners for coal winning & production eliminates the requirement of drilling and
blasting in coal and further need of crushing of coal in crushers.
All Drill machines are provided with a Dust extractor equipped with fabric filter and wet drilling
arrangement.
All Departmental Mobile water sprinklers for haul roads are equipped with Mist Spray Sprinkling
System.
Water guns are installed at coal stock yard & railway sidings to suppress fugitive dust emission.
All surface approach roads to CHP and sidings are being converted from WBM to RCC & 60% of the
work has been completed in FY 2022-23 (Up to Sep’22). A fund of Rs 40 lakhs has been earmarked
for fixed sprinklers along the alignment of this road in Capital Expenditure FY 2023-24. All Haul
roads leading to the quarry face inside the mine area are WBM.
All internal roads of the residential areas and approach roads to the mine and all other roads which are
in regular use are black topped.
A new overhead state-of-the-art 20,000 Te Bunker & Truck Receiving Station (CHP Phase – I) has
been commissioned from 08.02.2020. Annually 7.00 MT coal is transported through a closed
conveyor belt to nearby thermal power station.
Four nos. of new SILO’s with Rapid Loading System (4000 Te capacity each) along with New
Railway Siding (CHP Phase- II) has been commissioned from 24.08.2021. This eliminates the need of
loading of coal by pay loaders into rail wagons. It also enhances the capacity of despatch of coal from
Kusmunda Project (40.00 MTPA) & further eliminates road transport of coal outside the mine to end
consumers.
4
One No. of “Dust Suppression System with mist blower/fog forming long range water sprinkler with
horizontal throw of 40 mtrs (min) mounted on truck chassis of GVW-25T(min)” for Kusmunda Area
at a cost of Rs 47.69 Lakhs has been procured and commissioned from 19.07.2019.
Supply order for one no. of additional Dust Suppression System with mist blower/fog forming long
range water sprinkler has been placed on 04.05.21. Delivery has been delayed by the agency & it is
expected to be procured and commissioned in FY 22-23.
Dust Breaking arrangement & Vertical Greenery System (VGS) is operational at NK-II Railway
Siding.
2 Nos. of 28 KL and 70 KL capacity water tankers with mist spray arrangements have been
additionally commissioned in last three years.
A Field Experiment study for “Erosion Prevention & Soil Dump Stabilization at Overburden dumps
through implementation of Vetiver system technology for development of horticulture on restored
mine sites” has been carried out at Kusmunda OCP by IIT, Kharagpur. One Lakh Vetiver saplings
were planted on a 1.00 ha site earmarked for the study in 2017-18. Growth of the saplings is
satisfactory.
Dust masks are being distributed regularly to workers operating in dusty areas. No of dust masks
provided during Apr-Sep 22:7803 nos.
Plantation in all important areas like sites earmarked for infrastructure such CHP, crushers, coal stock
yards, ETP, workshops and road sides of the mining lease are undertaken to increase the density of
plantation. A total of 24.61 lakhs plants have been planted till date in Kusmunda OCP including
50000 saplings planted during FY 2022-23. A total of 6.62 lakhs of plant species have been planted
around Non-dump areas in Kusmunda OCP till date. Gap Plantation has been undertaken by PP in past
4 years to strengthen the existing green belt.
Safety Zone of 5km length & 10000 nos. of plants have been developed all along the Northern &
Eastern Mine Boundary of Kusmunda OCP.
Work for Vertical Greenery Plantation has been completed for NK-2 railway siding & Kusmunda
Guest House in FY 2022-23.
Mechanical Vacuum Air cleaning machines are used for dust control in workshops.
All Staff are provided with LPG connections, restricting burning of coal for domestic use. Number of
LPG connections provided till date: 5144 nos.
Trucks are optimally loaded to prevent spillage on haul roads. It is strictly ensured that Coal loaded
trucks are covered with Tarpaulin before leaving the mine premises.
In order to reduce the pollution load, high capacity equipment has been planned in phased manner at
Kusmunda OCP:
5
06 Loader (CAT– 10.75 Cum) Nil 05 05
07 Dumper (35Te) Nil Nil Nil
08 Dumper (BH60-60T) 68 86 84
09 Dumper (CAT60 –60T) 54 67 67
10 Dumper (BH100- 100T) 56 56 56
Moreover, other upcoming & other associated developmental activities according to the Kusmunda 50
MTY Project Report (Approved by CIL Board on 03/08/2013) are as follows:-
o CHP Phase-III – In-Pit Belt Conveyors: Work has been awarded for Construction of In-pit belt
conveyor on 18.01.2021. Physical progress: 31%. It is likely to be completed by 31/12/2023.
o Connectivity of New Railway Siding to East-West Rail Corridor Project (Rs. 27 crores):-
Work progress 13% up to 30.09.2022. This will facilitate faster integration & movement of
coal across the country.
o Construction of Integrated Main Workshop Complex:- Work Progress 96% upto 30.09.2022.
This will reduce the movement of HEMM to multiple locations & will provide a single
location for undertaking pollution control measures.
o Procurement of 15 nos. of fixed mist cannon/ fogging machines for coal stock yards & railway
sidings has been approved on 22.09.22 & tender will be floated soon.
o Procurement of two no. of mechanized sweeping machines is under process of approval.
o A fund of Rs 40 lakhs has been earmarked for fixed sprinklers along the alignment of new
CC road in Capital Expenditure FY 2023-24.
6
o Construction of WBM/bypass road at an estimated cost of Rs 1.94 crores (Length: 1.1 kms and
width is 7.0 kms) from Mangaon village to Naraibodh village to avoid road transportation
through Gevra Basti village. NOC has been obtained from Collector, Korba for diversion of
0.936 ha Revenue Forest Land.
o Other WMM roads under construction within premises are:
Various Control measures being taken at Kusmunda OCP to control Water Pollution are as
follows:
i. Domestic Effluent Treatment Plant (DETP) of 2 MLD capacity is constructed for treating the
domestic effluent of residential colonies.
ii. An RCC Settling Tank with Sludge Drying Bed (Capacity: 540m3) has been constructed for
treatment of mine discharge water for industrial use at an estimated cost of Rs 27.65 Lakhs and
commissioned along with newly constructed CHP.
iii. Settling ponds are provided for treating the mine water before discharge of mine water into the
main stream.
iv. Catch drains & garland drains are constructed and maintained around the external dumps and all
around the mine. Check dams are provided in catch drains.
v. Sedimentation ponds, Settling/ Siltation ponds act as a natural source of recharge of groundwater.
vi. Under the Corporate Social Responsibility (CSR) works, many ponds were constructed/
renovated which again complements in recharge of the ground water.
vii. Rain water harvesting system is being practiced to recharge the ground with rain water at
following eight locations at present:
o One structure at Kusmunda House
o One structure at CGM Office
o One structure at DAV School Kusmunda
o Two structures at Central School Kusmunda
o One structure each at Dispensaries of Vikas Nagar and Adarsh Nagar respectively
o One structure at CAAQMS/ Environment Office, AHQ
Moreover, Rain Water Harvesting structures are being proposed on different locations like RRRT
Building, Sr. Recreation Club, SBI/Post Office compound etc.
viii. Kuccha/ garland drain has been constructed and cleaned regularly along the periphery of the
mines and residential areas for channeling of run-off water during rainy season.
7
ix. Drinking Water quality is also being monitored at Chun- Chuni Colony, Gevra Basti & Vikas
Nagar Colony, on monthly basis.
x. The project authority also meets the requirement of the Drinking water in nearby villages by
supplying potable water through mobile tankers.
xi. 10 Nos. of Piezometers have been constructed for measuring the Ground Water level in and
around Kusmunda OCP.
xii. Two Reservoirs of 70000 KL& 30000 KL have been planned & estimate moved for approval for
final settling of mine water before discharge into local water bodies.
xiii. 7 Nos. of Automatic Digital Water Level Recorders have been procured for Automatic & Real
Time monitoring of piezometer readings at these locations. It has been installed in one piezometer
as on date as per NOC condition.
xiv. Old Oil & Grease Trap has been dismantled. A new Effluent Treatment Plant (ETP) (Cost: 40
Lakhs) of enhanced capacity for meeting the requirement of new HEMMs, as per PR of 50 MTY,
is under construction at new integrated workshop of Kusmunda OCP. It is expected to be
commissioned by 31.12.2022.Details are as below:
Requirement: 240Te, 100Te and 60 Te Dumper/HEMM washing
Number of Settling tanks: 03 Nos.
Capacity: 2300m3 each with 1240 m3 recycling capacity (80%).
Dimensions: Length:65 m X Width 12m X Height 4m each.
Various Control measures being taken at Kusmunda OCP to control Noise Pollution are as follows:
Stress on use blasting free technology of Surface Miner mining in coal mines.
Proper maintenance of equipment to minimize vibration;
All HEMMs are provided with noise proof cabins for operators. Extensive plantation done on over
burden dumps, which act as noise barrier between mines area and residential area.
Thick green belts developed around residential areas, along colony roads, coal transportation road and
around the mine infrastructure, also act as noise barrier.
Employees who are exposed to higher level of noise are provided with ear plugs.
Generally blasting operation is carried out between 1 pm to 3 pm with minimum no. of persons within
the mine premises.
Vocational, Special training and On spot training is also carried out to provide information about
safety and health aspects by VTC personnel/Safety Personnel regularly.
Noise Level Monitoring is being regularly done on a fortnightly basis & values are below the standard
limits.
8
Following measures are being taken up at Kusmunda area for reducing energy consumption,
efficiency improvements & use of renewable energy:-
1. Work has been awarded for installation of solar panels/rooftops (65 nos.) vide no. 1566100 on
05.01.22 for a quantity of 65 units at a cost of 26.43 lakhs for Kusmunda Area. Site visit has
been completed and locations have been finalized at GM Office, Kusmunda Bhavan and Rescue
office for installation.
2. Halogen lamps are being replaced by LED Lighting system in the mines.
3. Proper maintenance of Lighting, working of AC cabins, electrical equipment etc. in HEMM
helps in maintaining efficiency of their working & thus reduces energy consumption.
4. Distribution of LPG Cylinders to the employees & workers helps in restriction of burning of coal
for domestic use. Number of LPG connections provided till date:5144 nos.
5. Technological upgradation like High Capacity HEMM, New Bunker with State of Art
technology, upcoming of Silos & in-pit conveyor belt, Washery, Integrated Workshop etc. will
help in efficiency improvements & energy savings on a large scale in the cradle to gate cycle of
Kusmunda OCP.
6. Expenditure towards energy conservation for the FY 21-22 is 2.18 crores. Target for the FY 22-
23 energy expenditure is estimated to be 7.5 crores.
7. Timers have been provided in all colonies and mines for auto start and stop to save energy &
energy savings on a large scale in the cradle to gate cycle of Kusmunda OCP.
8. Solar roof tops have been installed at 5 different locations namely at Substation 1, Rest shelter,
Time office, Administrative offices (E&M, Excv. each) inside New Integrated workshop campus
with a capacity of 200 kW.
The Capital budget for Env. Protection measures as per EMP/PR is Rs. 575.33 Crores. Expenditure
incurred in Environment related works during past three years is as follows:
YEAR
PARTICULARS 2022-23
2020-21 2021-22
(Apr-Sep)
CSR EXPENSES 2851777.00 2500000.00 175000.00
TREE PLANTATION 74488140.20 37304587.00 41361658.72
ENVIRONMENTAL MONITORING 2679749.00 11175002.00 13735783.00
REHABILITATION AND 199794000.00 202494000.00 102486000.00
RESETTLEMENT
MINE CLOSURE ACTIVITY 79027200.00 64938200.00 31818950.00
OTHER ENV EXPENSES 70740.00 300888.60 428985.00
TOTAL 358911606.20 318712677.00 190006376.72
9
PART – V
(Green Belt & Afforestation, etc.)
*Remark- Kusmunda Area had carried out Plantation of 62000 no. of saplings alongside 21 km as a
part of roadside plantation in FY 2008-09.
**Note: SECL Kusmunda Area has also paid Rs 31,94,386/- in FY 2022-23 to Chhattisgarh Forest
Department for development of “Krishna Kunj” plantation site at Ward No. 14, Khasra No. 17/1,
Area – 0.810 Ha in Katghora District, Chhattisgarh. A total of 900 plants have been planted by
Forest Department for development of urban eco-park in Katghora town.
10
Part VI
11
COMPLIANCE OF
ENVIRONMENT
CLEARANCE
EC CONDITIONS FOR KUSMUNDA OPENCAST PROJECT
50 MTPA (Normative)/62.50 (Peak) CAPACITY
(i) Condition: - No mining activity shall be conducted in 43.942 ha of forest land till Project
proponents obtain Forest Clearance.
No mining operation is being undertaken in any forest land. The said 43.942 ha of forest
land falls under Phase-II of Kusmunda Expansion Project & application for its diversion is under
process with MoEF&CC vide proposal no. FP/CG/MIN/41604/2019 dated 18.10.2019. No mining
will be conducted in the said revenue forest land till the grant of FC (Undertaking enclosed as
Annexure-01).
(ii) Condition: - Compliance of recommendation of EAC sub-committee dated 10-11th Sept 2019.
Compliance: -Being Complied by PP.
Action taken report regarding Recommendations of EAC sub-committee has been enclosed
as Annexure-02.
(iii) Condition: - Mitigation measures to be proposed by IIT Kharagpur after air quality monitoring
shall be strictly complied.
Action taken report regarding Recommendations of IIT Kharagpur has been enclosed as
Annexure-03.
(iv) Condition: - Project proponent to plant 100,000 nos. of native trees with broad leaves along the
villages and transportation route to prevent the effect of air pollution. After completion of tree
plantation, number of trees shall be duly endorsed from District Forest Officer.
1
DFO, Katghora in this regard & will be submitted to Integrated Regional Office (IRO),
MoEF&CC, Raipur. (Details are enclosed as Annexure-04)
(v) Condition: - The project proponent shall obtain Consent to establish from the State Pollution
Control Boards for the proposed peak capacity of 50 MTPA (Normative) / 62.5 MTPA (Peak) prior
to commencement of the increased production.
Compliance:-Complied by PP.
M/s Kusmunda Opencast Project has obtained Renewal of Consent to Operate for Air &
Water for a peak capacity of 50 MTPA (Normative)/62.5 MTPA (Peak) from CECB, Atal
Nagar, Raipur vide letter no. 6568 dated 14.12.2021 with a validity up to 31.12.2022.
Compliance of the conditions is under progress. (Copy of Valid Consent to Operate is attached
as Annexure-05)
(vi) Condition: - The company shall obtain approval of CGWA for use of groundwater for mining
operations at its enhanced capacity of 50 MTPA (Normative) / 62.5 MTPA (Peak).
Kusmunda area had applied for Groundwater NOC vide application no. 21-4/329/CT/MIN/2016
& had obtained:
1. Original NOC vide NOC No. CGWA/NOC/MIN/ORIG/2017/2416 dated 16.02.2017 with
a validity upto 19.01.2019 (Copy attached as Annexure-06)
2. First Renewal vide NOC No. CGWA/NOC/MIN/REN/1/2020/5628 dated 27.01.2020 with
a validity upto 18.01.2022. (Copy attached as Annexure-06)
3. Kusmunda Area had applied for 2nd Renewal on 15.01.2022 along with an interim report
of Impact Assessment with GW modelling in respect of Kusmunda OCP. (Application
Copy attached as Annexure-06)
Final Impact Assessment report has been submitted to CGWB, Raipur in the month of July,
2022 vide no. SECL/GM(M)/KOCP/22-23/926 dated 24.06.2022 in compliance with GW
guidelines, 2020 (Copy attached as Annexure-07). The application is under process at CGWA,
New Delhi since 22.08.2022.
(vii) Condition: - Thick green belt of adequate width at the final boundary in the down wind direction of
the project site shall be developed to mitigate/check the dust pollution. No shrubs shall be planted
and only trees of native species shall be planted.
(viii) Condition: - The activities and fund provisions for CER shall be made as per the guidelines issued
by the ministry regarding CER on 1st May, 2018.
As per revised guidelines issued by MoEF&CC, New Delhi dated 30.09.2020, allocation
of funds for CER has been dropped. However, for keeping commitments made to public during
Public hearing proceedings, Kusmunda OCP has carried out an expenditure of Rs 2.82 Cr in FY
2022-23 upto 30.09.2022. (Copy of guidelines & expenditure statement is enclosed as Annexure-
09).
(ix) Condition: - Compliance of all the non-compliance and partially complied conditions by Regional
Office of MoEF&CC, Nagpur for the project of EC dated 2nd January, 2019. The PP shall take all
the mitigation measures and the Action taken report shall be submitted the Regional Office of the
MoEF&CC.
(x) Condition: - The Project Proponent shall comply with the statutory requirements and judgment of
Hon‟ble Supreme Court dated the 2nd August 2017 in Writ Petition (Civil) No. 114 of 2014 in the
matter of Common Cause versus Union of India and Ors. State Government shall ensure that the
entire compensation levied, if any, for illegal mining paid by the Project Proponent through their
respective Department in strict compliance of judgment of Hon‟ble Supreme Court dated the 2nd
August 2017 in Writ Petition (Civil) No. 114 of 2014 in the matter of Common Cause versus
Union of India and Ors.
(xi) Condition: - Project Proponent shall obtain the necessary prior permission from the Central
Ground Water Authority (CGWA) in case of intersecting the Ground water table. The Intersecting
ground water table can only be commenced after conducting detailed hydro-geological study and
necessary permission from the CGWA. The Report on six monthly basis on changes in Ground
3
water level and quality shall be submitted to the Regional Office of the Ministry, CGWA and
State Pollution Control Board.
(xii) Condition: - Proponent shall appoint an Occupational Health Specialist for Regular and
Periodical medical examination of the workers engages in the Project and maintain records
accordingly, also, Occupational health check-ups for workers having some aliments like BP,
diabetes, habitual smoking, etc. shall be undertaken once in six months and necessary
remedial/preventive measures taken accordingly. The Recommendations of National Institute for
ensuring good occupational environment for mine workers shall be implemented, the prevention
measure for burns, malaria and provision of anti-snake venom including all other paramedical
safeguards may be ensured before initiating the mining activities.
4
Target and achievement of periodical medical examination for last 5 years are as follows:
(xiii) Condition: - Project Proponent shall follow the mitigation measures provided in Office
Memorandum No. Z-11013/57/2014-IA.II (M), dated 29th October, 2014, titled “Impact of mining
activities on Habitations-issues related to the mining Projects wherein Habitations and villages are
the part of mine lease areas or Habitations and villages are surrounded by the mine lease area”.
(xiv) Condition: - The illumination and sound at night at project sites disturb the villages in respect of
both human and animal population. Consequent sleeping disorders and stress may affect the health
in the villages located close to mining operations. Habitations have a right for darkness and minimal
noise levels at night. PPs must ensure that the biological clock of the villages is not disturbed, by
noise levels well within the prescribed limits for day light/night hours.
Illumination survey is carried out on a monthly basis, reviewed daily and made sure that lightning
required for mining activities is restricted within the premises so as not to disturb the human and
animal population around mine. Copies of Latest Illumination Survey Report is enclosed as
Annexure-14.
To control the Noise Pollution at Kusmunda Open Cast Mine the following measures are adopted:
Stress on use blasting free technology of Surface Miner mining in coal mines.
Proper maintenance of equipment to minimize vibration;
All HEMMs are provided with noise proof cabins for operators. Extensive plantation done
on over burden dumps, which act as noise barrier between mines area and residential area.
Thick green belts developed around residential areas, along colony roads, coal
transportation road and around the mine infrastructure, also act as noise barrier.
Employees who are exposed to higher level of noise are provided with ear plugs.
5
Generally blasting operation is carried out between 1 pm to 3 pm with minimum no. of
persons within the mine premises.
Vocational, Special training and On spot training is also carried out to provide information
about safety and health aspects by VTC personnel/Safety Personnel regularly.
Noise Level Monitoring is being regularly done on a fortnightly basis & values are below
the standard limits. Copy of Latest Noise Monitoring Report is enclosed as Annexure – 15.
(xv) Condition: - The project proponent shall take all precautionary measures during mining operation
for conservation and protection of endangered fauna, if any, spotted in the study area. Action plan
for consultation of flora and fauna shall be prepared and implemented in consultation with the State
Forest and Wildlife Department. A copy of action plan shall be submitted to the Ministry of
Environment, Forest and Climate Change and its Regional Office.
(xvi) Condition: - Hon‟ble Supreme Court in an Writ Petition (s) Civil No. 114/2014, Common Cause vs
Union of India &Ors vide its judgment dated 8th January, 2020 has directed the Union of India to
impose a condition in the mining lease and a similar condition in the environmental clearance and
the mining plan to the effect that the mining lease holders shall, after ceasing mining operations,
undertake regressing the mining area and any other area which may have been disturbed due to their
mining activities and restore the land to a condition which is fit for growth of fodder, flora, fauna
etc. Compliance of this condition after the mining activity is over at the cost of the mining lease
holders/Project Proponent”. The implementation report of the above said condition shall be sent to
the Ministry‟s Regional Office for site inspection/verification.
Compliance: -Agreed by PP
6
COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR
40.00 MTY OF KUSMUNDA OPENCAST PROJECT
i. Condition:- The sub-committee of the EAC shall make site visit to assess adequacy and
efficacy of pollution control measures and its impact on ambient air quality.
Compliance:- Being Complied by PP.
EAC sub-committee has visited Kusmunda OCP to assess adequacy and efficacy of
pollution control measures and its impact on ambient air quality and other environmental
parameters on 10 -11 September, 2019 & its recommendations have been covered in
condition no. 02 of EC of 50 MTPA (Normative) / 62.50 MTPA (Peak) dated 10-01-2020.
Action taken report regarding Recommendations of EAC sub-committee has been enclosed
as Annexure-02.
ii. Condition:- Third party monitoring (by NEERI/CIMFR/IIT) for air quality shall be carried
out at identified locations, both ambient and the process area to arrive at the impact of the
proposed expansions in phases (26-36 MTPA) and then up to 40 MTPA). The monitoring
results along with the recommendations shall be presented before the EAC to assess the
efficacy and adequacy of pollution control measures.
An undertaking duly endorsed by IIT Kharagpur has been submitted regarding the
mitigating measures and the infrastructure available for the proposed coal production
capacity of 40 MTPA along with recommendations in the final report on “Third party
7
monitoring for air quality at identified locations of Kusmunda OCP of Kusmunda Area” at
that time to Regional Office, MoEF&CC, Nagpur vide ref no.1756 dated: 26.07.2020.
iv. Condition:-Coal production shall be consistent with that given in the approved mine plan
Mining at Kusmunda OCP is being carried out as per the approved mining plan(PR
approved by CIL Board on 03/08/2013 including Mine Closure Plan) & all mining laws
related to coal mining and the relevant circulars issued by Directorate General Mines Safety
(DGMS) are being abided by the project proponent. Total Coal Reserves 01.04.2022 are
713.236 Million Te & Life of Mine is 15 Years from FY 2022-23.
8
COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR
36.00 MTY OF KUSMUNDA OPENCAST PROJECT
(i) Condition:-The project proponent shall collect and analyse one season base line data for
environmental parameters, preferably during April-June, 2018, and submit for consideration of the
EAC before 31st December, 2018.
(ii) Condition:-The project proponent shall also submit the details regarding action taken on different
observations of the Regional Office before 31st December, 2018, for the Committee to examine
adequacy and efficacy of the pollution control measures and its impact on ambient air quality and to
make recommendations for continuance of the project thereafter.
(iii)Condition:-To control the production of dust at source, the crusher and in-pit belt conveyors shall be
provided with mist type sprinklers.
Both CHP Phase-I (20,000 Te Bunker & Truck Receiving Station -1) & CHP Phase-II (Four no. of
Silos & TRS-II) and coal crushing units installed at coal stock yards have been equipped with Mist
and nozzle spray arrangement at unloading & transfer points to arrest fugitive emission. The nozzles
are checked daily and repaired/cleaned on daily basis if necessary.
Work has been awarded for Construction of CHP Phase-III - In-pit belt conveyors at a cost
of Rs. 544.59 Crores on 18.01.2021. Progress of work up to September‟22 is 31%. It is likely to be
completed by 31/12/2023. It will also be fully covered to arrest air-borne dust during coal
transportation with built-in mist spray & jet sprayers at unloading & transfer points. Work Order
copy attached as Annexure- 17.
9
(iv) Condition:-Mitigative measures shall be undertaken to control dust and other fugitive emissions all
along the roads by providing sufficient numbers of water sprinklers. Adequate corrective measures
shall be undertaken to control dust emissions as presented before the Committee, which would
include mechanized sweeping, water sprinkling/mist spraying on haul roads and loading sites, long
range misting/fogging arrangement, wind barrier wall and vertical greenery system, green belt, dust
suppression arrangement at railway siding, etc.
Compliance:- Being Complied by PP
Mitigative measures being taken at Kusmunda OCP to control dust & other fugitive emissions are as
follows:
Use of surface miners for coal winning & production eliminates the requirement of drilling and
blasting in coal and further need of crushing of coal in crushers.
All Drill machines are provided with a Dust extractor equipped with fabric filter and wet
drilling arrangement.
All Departmental Mobile water sprinklers for haul roads are equipped with Mist Spray
Sprinkling System.
Water guns are installed at coal stock yard & railway sidings to suppress fugitive dust emission.
All surface approach roads to CHP and sidings are being converted from WBM to RCC & 60%
of the work has been completed in FY 2022-23 (Up to Sep‟22). A fund of Rs 40 lakhs has been
earmarked for fixed sprinklers along the alignment of this road in Capital Expenditure FY 2023-
24. All Haul roads leading to the quarry face inside the mine area are WBM.
All internal roads of the residential areas and approach roads to the mine and all other roads
which are in regular use are black topped.
A new overhead state-of-the-art 20,000 Te Bunker & Truck Receiving Station (CHP Phase – I)
has been commissioned from 08.02.2020. Annually 7.00 MT coal is transported through a
closed conveyor belt to nearby thermal power station.
Four nos. of new SILO‟s with Rapid Loading System (4000 Te capacity each) along with New
Railway Siding (CHP Phase- II) has been commissioned from 24.08.2021. This eliminates the
need of loading of coal by pay loaders into rail wagons. It also enhances the capacity of
despatch of coal from Kusmunda Project (40.00 MTPA) & further eliminates road transport of
coal outside the mine to end consumers.
One No. of “Dust Suppression System with mist blower/fog forming long range water sprinkler
with horizontal throw of 40 mtrs (min) mounted on truck chassis of GVW-25T(min)” for
Kusmunda Area at a cost of Rs 47.69 Lakhs has been procured and commissioned from
19.07.2019.
Supply order for one no. of additional Dust Suppression System with mist blower/fog forming
long range water sprinkler has been placed on 04.05.21. Delivery has been delayed by the
agency & it is expected to be procured and commissioned in FY 22-23.
Dust Breaking arrangement & Vertical Greenery System (VGS) is operational at NK-II Railway
Siding.
2 Nos. of 28 KL and 70 KL capacity water tankers with mist spray arrangements have been
additionally commissioned in last three years.
10
A Field Experiment study for “Erosion Prevention & Soil Dump Stabilization at Overburden
dumps through implementation of Vetiver system technology for development of horticulture
on restored mine sites” has been carried out at Kusmunda OCP by IIT, Kharagpur. One Lakh
Vetiver saplings were planted on a 1.00 ha site earmarked for the study in 2017-18. Growth of
the saplings is satisfactory.
Dust masks are being distributed regularly to workers operating in dusty areas. No of dust
masks provided during Apr-Sep 22:7803 nos.
Plantation in all important areas like sites earmarked for infrastructure such CHP, crushers, coal
stock yards, ETP, workshops and road sides of the mining lease are undertaken to increase the
density of plantation. A total of 24.61 lakhs plants have been planted till date in Kusmunda OCP
including 50000 saplings planted during FY 2022-23. A total of 6.62 lakhs of plant species have
been planted around Non-dump areas in Kusmunda OCP till date. Gap Plantation has been
undertaken by PP in past 4 years to strengthen the existing green belt.
Safety Zone of 5km length & 10000 nos. of plants have been developed all along the Northern
& Eastern Mine Boundary of Kusmunda OCP.
Work for Vertical Greenery Plantation has been completed for NK-2 railway siding &
Kusmunda Guest House in FY 2022-23.
Mechanical Vacuum Air cleaning machines are used for dust control in workshops.
All Staff are provided with LPG connections, restricting burning of coal for domestic use.
Number of LPG connections provided till date: 5144 nos.
Trucks are optimally loaded to prevent spillage on haul roads. It is strictly ensured that Coal
loaded trucks are covered with Tarpaulin before leaving the mine premises.
In order to reduce the pollution load, high capacity equipment has been planned in phased
manner at Kusmunda OCP:
S. HEMM Population
HEMM Equipment & Capacity
No 01.04.2021 01.04.2022 Up to 30.09.22
01 Surface Miner (5 MT) 05 10 10
02 Shovel (P&H - 10 Cum) 03 03 03
03 Shovel (EKG - 5 Cum) 01 Nil Nil
04 Shovel (BE1800E – 10 Cum) 03 03 03
05 Loader (WA800E-10 Cum) 10 15 13
06 Loader (CAT– 10.75 Cum) Nil 05 05
07 Dumper (35Te) Nil Nil Nil
08 Dumper (BH60-60T) 68 86 84
09 Dumper (CAT60 –60T) 54 67 67
10 Dumper (BH100- 100T) 56 56 56
Moreover, other upcoming & other associated developmental activities according to the
Kusmunda 50 MTY Project Report (Approved by CIL Board on 03/08/2013) are as follows:-
o CHP Phase-III – In-Pit Belt Conveyors: Work has been awarded for Construction of In-
pit belt conveyor on 18.01.2021. Physical progress: 31%. It is likely to be completed by
31/12/2023.
11
o Connectivity of New Railway Siding to East-West Rail Corridor Project (Rs. 27
crores):- Work progress 13% up to 30.09.2022. This will facilitate faster integration &
movement of coal across the country.
o Construction of Integrated Main Workshop Complex:- Work Progress 96% upto
30.09.2022. This will reduce the movement of HEMM to multiple locations & will
provide a single location for undertaking pollution control measures.
o Procurement of 15 nos. of fixed mist cannon/ fogging machines for coal stock yards &
railway sidings has been approved on 22.09.2022 & tender will soon be floated.
o Procurement of two no. of mechanized sweeping machines is under process of approval.
o A fund of Rs 40 lakhs has been earmarked for fixed sprinklers along the alignment of
new CC road in Capital Expenditure FY 2023-24.
12
S. Location Measurement Physical Progress
No
WMM Haul Road for 60 Te Dumper 950 M X 15 M
01 from Samanvay Chowk to SW Mine 60%
Entry (Cost : 1.50 Cr)
WMM Road for 60 Te Dumper & 2500 M X 20 M
02 Coal Tippers from Satarkta Chowk 60%
to Eastern Coal Face (Cost : 5.10 Cr)
WMM road from centre of mine 990 M X 12 M Work to be started after
03 (Cost : 1.20 Cr) completion of above
roads.
13
42 CUM SHOVEL KUSMUNDA OCP
14
CONSTRUCTION OF NEW RAILWAY SIDING, KUSMUNDA OCP
15
CONSTRUCTION OF IN-PIT BELT CONVEYOR (CHP PHASE-III)
KUSMUNDA OCP
16
240 TE DUMPER AT KUSMUNDA OCP LONG RANGE FOGGING MACHINE
17
(v) Condition:-Persons of nearby villages shall be given training on livelihood and skill
development to make them employable.
(vi) Condition:-To ensure health and welfare of nearby villages, regular medical camps shall be
organized at least once in six months.
Compliance:- Complied.
Such camps are being organized on a regular basis for ensuring the health & welfare of
nearby villagers. No. of Health Check-up camps organized by Kusmunda Area in past 5 years are:
2016 2017 2018 2019 2020 2021
56 52 38 51 NIL* NIL*
*Note – Due to COVID-19, only testing & vaccination camps were organised by Kusmunda Area
Vaccination camps have been organised by SECL Vikasnagar and Adarshnagar dispensaries
in various villages like Naraibodh, Vaishalinagar, Mangaon, Vikasnagar and contractual employees
inside mine premises against COVID-19 from 12.09.22 to 16.9.2022 with a vaccination count:174
nos.. Photographs and details are as below:
18
COVID-19 MEGA VACCINATION DRIVE AT MANGAON, KUSMUNDA AREA
(vii) Condition:-Thick green belt of 75 m width at the final boundary in the down wind direction of the
projectsite shall be developed to mitigate/check the dust pollution.
Compliance:- Compliance in progress.
Safety Zone of 75m thickness has been developed in Northern & Eastern Boundary of
the Kusmunda Project in FY 2020-21. Kusmunda Mine is currently proceeding in Southern &
Western direction. Land has already been acquired by Kusmunda Project for an area of 752.456 ha
after Section 9(i) dated 28.03.2010 & for an area of 1050.593 ha after Section 9 (i) dated
18.07.2018 in Southern & Western Directions under Coal Bearing Areas (land & Acquisition) Act,
1957. (Copy of relevant Section 9(i) & 11(i) records are enclosed as Annexure –18)
19
PHOTOGRAPHS OF SAFETY ZONE AROUND KUSMUNDA AREA
Moreover, after undertaking an active consultation exercise with the villagers, a Govt.
Land of 2.75 Ha was identified & a total of 6,855 Nos. of saplings were planted in the Monsoon
Year 2017-18 at Bata village (a village selected outside the final mine lease boundary of
Kusmunda Project in the downwind direction for mitigating the effects of dust pollution in the
surrounding villages). A total of 9000 cum (approx.) of top soil was also used for this purpose.
These trees will take a mature shape when the mine reaches that boundary in future. Action
Programme for green belt development in final mine boundary direction is enclosed as
Annexure-08.
(viii) Condition:-A third party assessment of EC compliance shall be undertaken once in three years
through agency like ICFRI /NEERI/IIT or any other expert agency identified by the Ministry.
Compliance:- Being Complied with.
Moreover, proposal for carrying out third party assessment of EC Compliance of Kusmunda
OCP through ICFRE, Dehradun on nomination basis in FY 2022-23 under MoU of ICFRE with Coal
India Limited has been approved from competent Authority. Work has been awarded to ICFRE,
Dehradun for the above said same vide no. SECL/GM/KSM/ENV/22-23/146 dated 01.10.2022 (copy
of letter enclosed as Annexure-19).
20
COMPLIANCE STATUS OF GENERIC CONDITIONS
AS GIVEN IN EC OF 36.00 MTY OF KUSMUNDA OPENCAST PROJECT
A) MINING
(i) Condition:-Mining shall be carried out under strict adherence to provisions of the Mines Act
1952 and subordinate legislations made there-under as applicable
Mining is being carried out under strict adherence to provisions of the Mines Act
1952 and subordinate legislations made there-under as applicable.
(ii) Condition:-No change in mining method i.e., OC to UG, calendar programme and scope of
work shall be made without obtaining prior approval of the Ministry of Environment, Forest
and Climate Change (MoEF&CC).
(iii) Condition:-Mining shall be carried out as per the approved mining plan (including Mine
Closure Plan) abiding by mining laws related to coal mining and the relevant circulars issued
by Directorate General Mines Safety (DGMS).
Mining at Kusmunda OCP is being carried out as per the approved mining plan(PR
approved by CIL Board on 03/08/2013 including Mine Closure Plan) & all mining laws
related to coal mining and the relevant circulars issued by Directorate General Mines Safety
(DGMS) are being abided by the project proponent. Total Coal Reserves as on 1.04.2022 is
713.236 Million Te & Life of Mine is 15 Years from 2022-23.
21
Copy of DGMS Permission & Annual returns submitted to DGMS office for the Year
ending 21-22 are enclosed as Annexure- 20 & 21.
(iv) Condition:-No mining shall be carried out in forest land without obtaining Forestry
Clearance as per Forest (Conservation) Act, 1980 and also adhering to The Scheduled Tribes
and Other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 read with
provisions of Indian Forest Act, 1927.
22
SATELLITE IMAGERY, KUSMUNDA OCP
23
TECHNICAL RECLAMATION IN KUSMUNDA OPENCAST PROJECT
(ii) Condition:-The surface drainage plan including surface water conservation plan for the area of
influence affected by the said mining operations, considering the presence of river/rivulet/pond/lake
etc, shall be prepared and implemented by the project proponent. The surface drainage plan and/or
any diversion of natural water courses shall be as per the approved mining plan/EIA/EMP report and
with due approval of the concerned state/GOI Authority. The construction of embankment to prevent
any danger against inrush of surface water into the mine should be as per the approved Mining Plan
and as per the permission of DGMS.
No major drainage is being altered or impacted by mining at Kusmunda OCP. Mining is being
carried at a considerable distance from the Hasdeo/Ahiran rivers & Laxman nallah which are major
channels around the mine. External dumps around the river periphery have been completely
stabilized with dense plantation & have been provided with check dams, retaining walls etc. to avoid
the flow of silt into the rivers.
24
Chhattisgarh Council of Science & Technology (CCOST), Raipur has carried out a work on
“Comprehensive Catchment Treatment Plan in the area to arrest flow of silt in the Hasdeo River & to
improve water regime in respect of Kusmunda Expansion OC Project”. Its report is enclosed as
Annexure- 25.
(iii) Condition:-The final mine void depth should preferably be as per the approved Mine Closure Plan,
and in case it exceeds 40 m, adequate engineering interventions shall be provided for sustenance of
aquatic life therein. The remaining area shall be backfilled and covered with thick and alive top soil.
Post–mining land be rendered usable for agriculture/ forestry purposes and shall be handed over to
the respective state government as specified in the guidelines for preparation of Mine Closure Plan
issued by the Ministry of Coal dated 27th August, 2009 and subsequent amendments.
Final Mine Closure Plan is a part of approved Project Report for Kusmunda Expansion OCP
(15-50MTPA). Final mine void of depth not more than 40 m will be left for conversion into a water
body which will act as a source of irrigation/ water recharge & remaining area will be back filled and
covered with top soil for agricultural use in future. Post Mining Land use has been covered in detail
in Chapter-IV of EIA/EMP Report of Kusmunda OCP Expansion (15-50 MTY) (Copy enclosed as
Annexure-26)
Yearly report of Mine Closure Plan of Kusmunda open cast mine is submitted to The Coal
Controller, Kolkata. Last Yearly Report for of Mine Closure Plan of Kusmunda open cast mine for
FY 2021-22 has been submitted vide letter no. 1159 dated 18.06.2022 (Copy enclosed as Annexure-
27)
(iv) Condition:-The entire excavated area, backfilling, external OB dumping (including Top soil) and
afforestation plan shall be in conformity with the “during mining”/”post mining” land-use pattern,
which is an integral part of the approved Mining Plan and the EIA/EMP submitted to this Ministry.
Progressive compliance status vis-à-vis the post mining land use pattern shall be submitted to the
Ministry of Environment, Forest and Climate Change/ Regional Office on six monthly basis.
Final Mine Closure Plan is a part of approved Project Report for Kusmunda Expansion OCP (15-
50MTPA). The entire excavated area, backfilling, external OB dumping (including Top soil) and
afforestation plan forms a part of our Final Mine Closure Plan as well as the EIA/EMP of the project.
There are total 13 external dumps & one internal dump / backfilled dump at Kusmunda
OCP. No more external dumps will be created in future & all the overburden is planned for
backfilling in the internal dump only. As on 30.09.2022, out of the 13 external dumps, 2 have been
completely rehandled & 5 more external dumps have been partially re-handled into the mine for
infrastructure expansion as per the approved mining plan.
25
Restoration and reclamation plan is done as per Progressive Mine Closure Plan of
Kusmunda OCP 50.00 MTPA which is given below (year-wise programme):
OB Dump plan Dump area (Ha) Dump area No. of No. of
Year Removal (M cum) available for Plantation Plantation
reclamation (Ha) Planned Actual
(M External Internal External Internal External Internal
Cum)
1 20.73 10 10.73 162.50 10.10 130 8.08 120282 55000
(2013-14)
2 20.73 10 10.73 162.50 10.10 130 8.08 137529 125000
3 20.73 0.00 20.73 0.00 19.52 32.50 15.61 345203 140000
4 29.89 0.00 29.89 0.00 28.14 32.50 22.51 345203 140000
5 40.56 0.00 40.56 0.00 38.18 0.00 30.55 76369 106855
6 40.46 0.00 40.46 0.00 38.09 0.00 30.47 76181 126000
7 50.24 0.00 50.24 0.00 47.30 0.00 37.84 94595 70000
8 66.71 0.00 66.71 0.00 62.80 0.00 50.24 125606 50000
9 66.88 0.00 66.88 0.00 62.90 0.00 50.37 125926 53000
10 66.97 0.00 66.97 0.00 63.05 0.00 50.44 126096 50000
(2022-23)
11 67.03 0.00 67.03 0.00 63.10 0.00 50.48 126209
12 67.23 0.00 67.23 0.00 63.29 0.00 50.63 126585
13 67.23 0.00 67.23 0.00 63.29 0.00 50.63 126585
14 67.27 0.00 67.27 0.00 63.33 0.00 50.66 126661
15 67.30 0.00 67.30 0.00 63.36 0.00 50.69 126717
16 67.30 0.00 67.30 0.00 63.36 0.00 50.69 126717
17 67.64 0.00 67.64 0.00 63.68 0.00 50.94 127357
18 68.27 0.00 68.27 0.00 64.27 0.00 51.42 128543
19 68.27 0.00 68.27 0.00 64.27 0.00 51.42 128543
20 68.32 0.00 68.32 0.00 64.32 0.00 51.46 128638
21 68.33 0.00 68.33 0.00 64.33 0.00 51.46 128656
22 68.15 0.00 68.15 0.00 64.16 0.00 51.33 128318
23 67.90 0.00 67.90 0.00 63.92 0.00 51.14 127847
24 38.31 0.00 38.31 0.00 36.07 0.00 28.85 72133
MC 1 0.00 0.00 0.00 0.00 0.00 0.00 83.00 207500
MC 2 0.00 0.00 0.00 0.00 0.00 0.00 83.00 207500
MC 3 0.00 0.00 0.00 0.00 0.00 0.00 83.00 207500
915855
TOTAL 1342.45 20.00 1322.45 325.00 1245.00 325.00 1245.00 3925000
(Till 2022-23)
26
Reclamation of OB dumps is being practiced and as on 30.09.2022, the total area of
External dumps is 196.242 ha which has been fully reclaimed technically as well as biologically
(through plantation). Presently, Internal OB dumping is being practiced and as on 30.09.2022,
total 510.610 Ha area has been backfilled and out of which 203.00 Ha area has been biologically
reclaimed through plantation. Compliance status is regularly submitted to MOEF&CC as a part
of our half yearly compliance & to The Coal Controller, Kolkata as a part of our Yearly report of
the Mine Closure Plan.
(As on 30.09.2022)
INTERNAL DUMP/BACK FILLED TOTAL RECLAIMED
EXTERNAL OB DUMPS DETAILS
AREA DETAILS AREA
EXTERNAL OB DUMP
RECLAIMED AREAS
RECLAIMED/ BACK
RECLAIMED AREA
TOTAL AREA OF
AREA ALREADY
AREA ALREADY
BIOLOGICALLY
BIOLOGICALLY
BIOLOGICALLY
TECHNICALLY
TECHNICALLY
TECHNICALLY
TOTAL AREA
TOTAL AREA
EXCAVATED
RECLAIMED
RECLAIMED
RECLAIMED
FILLED
TOTAL
TOTAL
815.627 510.610 203.00 196.242 196.242 196.242 706.852 399.242
Present bifurcation of land in operation at Kusmunda OCP 50 MTPA (Normative)/ 62.50 MTPA
(Peak) is as follows:
27
Others 62.54 ha Includes vacant area for future colony,
R&R, public road, HFL area of
Hasdeo & Ahiran river, nallahs etc.
Total Area in ha 1655.825 Ha
(v) Condition:-The Top soil shall be stored at earmarked site(s) only and shall not be kept unutilized for
long. The top soil shall be used for land reclamation and plantation purposes. Active OB dumps shall
be stabilized with native grass species to prevent erosion and surface run-off. The other overburden
dumps shall be vegetated with native flora species. The excavated area shall be backfilled and
afforested in line with the approved Mine Closure Plan. Monitoring and management of rehabilitated
areas shall continue until the vegetation becomes self-sustaining. Compliance status shall be
submitted to the Ministry of Environment, Forest and Climate Change/ Regional Office on six
monthly basis.
Compliance:- Complied.
Top Soil Storage & removal is a part of Chapter –IV (Pg-IV-51) of EIA/EMP of 15-50
MTY Kusmunda Expansion OCP. The top soil is removed before drilling, blasting, mining or any
kind of surface disturbance & is stored at an earmarked site of 3 Ha area on the internal dump such
that it is placed on a completely reclaimed dump, undisturbed & protected from wind & water
erosion, & protected from unnecessary compaction due to dense forest around. Suitable water
coursing channels & a separate approach road has been constructed to protect &recover top soil.This
Top soil is used for spreading over the levelled graded backfilled soil for reclamation of the quarried
out land & for yearly plantation programmes.
As per EIA/EMP, the year wise programme for Top Soil Management at Kusmunda OCP is given
below in Table 4.31.
28
TABLE 4.31 TOP SOIL MANAGEMENT OF KUSMUNDA OC
AREA
QUARRY TOP TOP SOIL SPREAD
TOP SOIL EXTERN TOP SOIL REQUIRED
AREA OF SOIL INTERNAL
REMOVED AL STACKED FOR
YEAR EXCAVA REMOV DUMP
CUMULATI DUMP EXT. INT. CUMM. SPREADING
TION ED MCUM TOTAL
VE MCUM MCUM DUMP DUMP MCUM TOP SOIL
(HA) MCUM
(HA)
1 10.40 10.31 0.00 0.00
(2013-14)
2 10.40 10.31 0.00 0.00
3 20.71 0.00 0.00
4 28.00 0.11 0.11 31.86 0.11 0.11 0.00
5 28.00 0.11 0.22 42.49 0.11 0.11 0.00
6 61.00 0.24 0.46 42.59 0.10 0.14 0.24 0.00
7 61.00 0.25 0.71 52.29 0.25 0.25 0.00
8 61.00 0.25 0.96 67.65 0.25 0.25 0.00
9 61.00 0.24 1.20 67.80 0.24 0.24 0.00
10
61.00 0.24 1.44 67.91 0.24 0.24 0.00
(22-23)
11 66.00 0.27 1.71 67.92 0.27 0.27 0.00
12 66.00 0.26 1.97 68.13 0.26 0.26 0.00
13 66.00 0.27 2.24 68.13 0.16 0.16 0.11
14 66.00 0.26 2.50 68.14 0.11 0.11 0.27
15 64.00 0.26 2.76 68.25 0.11 0.11 0.41
16 41.00 0.16 2.92 68.25 0.15 0.15 0.43
17 41.00 0.16 3.08 68.35 0.15 0.15 0.44
18 41.00 0.17 3.25 69.24 0.15 0.15 0.46
19 41.00 0.16 3.41 69.24 0.15 0.15 0.47
20 41.00 0.17 3.58 69.25 0.15 0.15 0.49
21 33.00 0.13 3.71 69.24 0.27 0.27 0.35
22 33.00 0.13 3.84 69.09 0.27 0.27 0.20
23 33.00 0.13 3.97 53.68 0.27 0.27 0.06
24 18.00 0.07 4.04 30.83 0.13 0.13 0.00 16.28
TOTAL 1011 4.04 20.80 1321.66 0.32 3.72 4.04
Presently, Only Internal OB dumping is being practiced and as on 30.09.2022, total 510.610
Ha area has been backfilled and out of which 203.00 Ha area has been biologically reclaimed
through plantation. The slopes of OB dumps are made stable by plantation of grass beds and
saplings. Further no external dump would be created. 13 Nos. of External dumps around the river
periphery have been completely stabilized with dense plantation with native floral species & have
been provided with check dams, retaining walls etc. to avoid the flow of silt into the rivers.
Thick plantation has been done in & around the quarry, over backfilled OB dump, infrastructure
sites, service building areas, township, pond, avenue, and plantation on both sides of the Coal
29
transportation road. A total of 24.61 lakhs plants have been planted till date in Kusmunda OCP
including 50000 saplings planted during FY 2022-23. A total of 6.62 lakhs of plant species have
been planted around Non-dump areas in Kusmunda OCP till date. Plantation in all important areas
like sites earmarked for infrastructure such CHP, crushers, coal stock yards, ETP, workshops and
road sides of the mining lease are undertaken to increase the density of plantation.
Compliance status is regularly submitted to Integrated Regional Office (IRO),
MOEF&CC, Raipur on a six monthly basis. Last Six monthly Compliance report from Oct to Mar
2022 was sent vide letter no. 660 dated 30.05.2022.
31
GAP PLANTATION ON DUMP NO. 02 (2020-21)
32
C) EMISSIONS, EFFLUENTS AND WASTE DISPOSAL
(i) Condition:-Transportation of coal, to the extent permitted by road, shall be carried out by covered
trucks/conveyors. Effective control measures such as regular water/mist sprinkling/rain gun etc shall
be carried out in critical areas prone to air pollution (with higher values of PM 10/PM2.5) such as haul
road, loading/unloading and transfer points. Fugitive dust emissions from all sources shall be
controlled regularly. It shall be ensured that the Ambient Air Quality parameters conform to the
norms prescribed by the Central/State Pollution Control Board.
Compliance:- Complied.
At present, coal is being transported through a newly constructed 20000 Te Bunker with
approximately 7.00 MT per annum of coal to CSPGCL, Korba through a covered conveyor belt in an
environment friendly manner. After commissioning of SILO‟s from 18.03.2021, maximum despatch
is through rail mode. This will only increase with commissioning of In-pit belt conveyor & road
despatch will be minimal. The break-up of mode of coal dispatch to different consumers from KOCP
is as follows:
Road transportation is being practiced only to meet the needs of local consumers & industries
through fully covered transportation trucks. Control measures adopted by Kusmunda OCP area as
follows:
All transportation roads are well paved and maintained in good condition. The roads inside the
mine pit are WBM, cleaned regularly and well maintained by using high capacity graders.
Haul roads and service roads are separated to avoid traffic congestion with proper signs to
protect workers from dust and accidental damages.
All surface approach roads to CHP and sidings are being converted from WBM to RCC &
60% of the work has been completed in FY 2022-23 (Apr-Sep). A fund of Rs 40 lakhs has
been earmarked for fixed sprinklers along the alignment of this road in Capital Expenditure
FY 2023-24.
All internal roads of the residential areas and approach roads to the mine and all other roads
which are in regular use are black topped.
Mitigative measures to control dust and fugitive emission such as mist sprayers, perforated
pipe systems, water guns & long range fogging machine are regularly monitored, and changes
are made as per requirements.
Mobile water sprinklers (Departmental: 28 KL capacity: 04 nos. with mist spray
arrangements; 70 KL capacity: 10 nos. with mist spray arrangements and Contractual water
33
tankers 9 KL capacity: 06 nos.) have exclusively been deployed in the mine and at area level
to control fugitive emissions.
Fixed sprinklers, Long Range Fogging Machine and mobile sprinkling arrangements are
thoroughly checked, cleaned, well lubricated and kept in check to avoid choking and
decreased efficiency.
Water guns are installed at coal stock yard & railway sidings to suppress fugitive dust emission.
Trucks are optimally loaded to prevent spillage on haul roads. It is strictly ensured that Coal
loaded trucks are covered with Tarpaulin before leaving the mine premises.
All Heavy and light commercial Vehicles plying in the mine premises are allowed only after
verifying the pollution under control certificate issued by the State Government authorized test
centre.
One No. of “Dust Suppression System with mist blower/fog forming long range water sprinkler
with horizontal throw of 40 mtrs (min) mounted on truck chassis of GVW-25T(min)” for
Kusmunda Area at a cost of Rs 47.69 Lakhs has been procured and commissioned from
19.07.2019. Supply order for one no. of additional Dust Suppression System with mist
blower/fog forming long range water sprinkler has been placed on 04.05.21. Delivery has been
delayed by the agency & it is expected to be procured and commissioned in FY 22-23.
Three tier plantations are also being along the roads & transportation routes.
Alternative roads or bypass roads are being constructed in a phased manner like new entry into
the mine through ROB to avoid residential areas, four lining of roads to avoid decongestion on
roads, new bypass road to avoid densely populated villages etc with the finalisation of mine
layout & infrastructure creation in Kusmunda OCP.
Trial run for using Mechanically covered truck for coal transportation by road has been
successfully completed at Kusmunda OCP. Possibilities are being explored for availability of
such vehicles commercially for bulk deployment.
Procurement of 15 nos. of fixed mist cannon/ fogging machines for coal stock yards & railway
sidings has been approved & tender will soon be floated.
Procurement of two no. of mechanized sweeping machines is under process of approval.
CAAQMS machine installed at Kusmunda Area to monitor Ambient Air quality data is
maintained on a daily basis by the firm. The service provider/contractor provides service for the
machine for every 3 months as part of routine maintenance and round the clock working. Avg.
readings for the year 2022-23(Jan-Sep) are enclosed as Annexure-28.
CMPDIL, having a NABL certified Lab & an ISO 14001 certified company, carries out the 104
readings per annum of Air Quality in Kusmunda OCP as per NAAQS guidelines. Total 09 nos.
of locations have been selected in consultation with State Pollution Control Board for Ambient
Air quality monitoring out of which 04 nos. in core zone and 05 nos. in buffer zone. The report
of the same is being regularly submitted to State Pollution Control Board, Chhattisgarh. Air
Quality Monitoring Report of Sep 2022 is enclosed as Annexure-15. It shows that the Ambient
Air Quality parameters conform to the norms prescribed by the Central Pollution Control Board.
Fugitive emissions standards have been set by the Central Pollution Control Board for Coal
Washeries. They are not applicable for Coal Mines. Standards for coal mines were inserted
by Rule 2(1) of the Environment (Protection) Amendment Rules, 2000 notified vide notification
34
G.S.R. 742(E), dated 25.9.2000 stipulated by the Ministry of Environment, Forests & Climate
Change (MoEF&CC), New Delhi which are followed for Kusmunda Mines of SECL in Korba
Coalfields. Air Quality Monitoring in Core Zone area carried out by CMPDIL on a bi-weekly
basis is enclosed in its report of Sep 2022 is enclosed as Annexure-15. It shows that the Air
Quality parameters in the core zone area conform to the norms prescribed by the Coal Mine
Standards under EPA Rules 2000.
35
HAUL ROAD ALONG SATARKATHA CHOWK TO BARKUTA
KUSMUNDA OCP
(ii) Condition:-Greenbelt consisting of 3-tier plantation of width not less than 7.5 m shall be developed
all along the mine lease area in a phased manner. The green belt comprising a mix of native species
shall be developed all along the major approach/ coal transportation roads.
Compliance:- Being Complied by PP.
Greenbelt consisting of 3-tier plantation of width not less than 7.5 m is being developed all
along the mine lease area in a phased manner. At present, the Mine is proceeding in Southern &
Western Directions as per the approved Project Report. Thus, a Safety Zone of 7.5m width with 3-
tier plantation has been developed within the existing mining leasehold in Northern & Eastern
Directions for a length of 5.0 kms in FY 2020-21.
36
SAFETY ZONE DEVELOPED IN PRESENT MINE BOUNDARY AT KOCP
A thick green belt has been developed in & around the quarry, over backfield OB dump,
infrastructure sites, service building areas, township, pond, avenue, and plantation on both sides of
the Coal transportation road since inception. A total of 24.61 lakhs plants have been planted till date
in Kusmunda OCP including 50000 saplings planted during FY 2022-23. A total of 6.62 lakhs of
plant species have been planted around Non-dump areas in Kusmunda OCP till date. Gap Plantation
has been undertaken by PP in past 4 years to strengthen the existing green belt.
Green belt development along the final boundary in the down wind direction of the mine will be
done in phased manner as per land acquisition programmes. For compliance of the EC Condition,
after undertaking an active consultation exercise with the villagers, a Govt. Land of 2.75 Ha was
identified & a total of 6,855 Nos. of saplings were planted in the Monsoon Year 2017-18 at Bata
village (a village selected outside the final mine lease boundary of Kusmunda Project in the
downwind direction for mitigating the effects of dust pollution in the surrounding villages). A total
of 9000 cum (approx.) of top soil was also used for this purpose. These trees will take a mature
shape when the mine reaches that boundary in future. Action Programme for green belt
development in final mine boundary direction is enclosed as Annexure-08.
37
PLANTATION AT BATA VILLAGE (2017-18)
(iii) Condition:-The transportation of coal shall be carried out as per the provisions and route proposed in
the approved Mining Plan. Transportation of the coal through the existing road passing through any
village shall be avoided. In case, it is proposed to construct a „bypass‟ road, it should be so
constructed so that the impact of sound, dust and accidents could be appropriately mitigated.
Compliance:- Being Complied by PP.
The transportation of coal is being carried out as per the provisions and route proposed in the
approved Mining Plan. As the Mine is in an expansion stage, Final layout of the mine according to
the Project Report has not been achieved yet & existing road network is being utilized by Kusmunda
as well as its nearby mines.
Transportation of coal through village roads is mostly avoided & trucks are being plied on roads /
routes approved in consultation with the State Government.
Meanwhile, measures such as widening of existing roads, cementation of some roads, regular water
sprinkling on the public roads, dense plantation on road sides, sign hoardings etc. is being practiced
in consultation with the State govt. to minimize the impact of sound, dust & accidents. A provision of
Rs 63.55 Crores has been provided in the Project Report for Cement Concretization of Colony,
Service, Approach & other roads in & around the mine premises.
Trucks are optimally loaded to prevent spillage on haul roads. It is strictly ensured that Coal
loaded trucks are covered with Tarpaulin before leaving the mine premises. All Heavy and light
commercial Vehicles plying in the mine premises are allowed only after verifying the pollution under
control certificate issued by the State Government authorized test centres (Copies of some certificate
are enclosed as Annexure-30). Transit pass certificates have been enclosed as Annexure-31.
(v) Condition:-Coal stock pile/crusher/feeder and breaker material transfer points shall invariably
be provided with dust suppression system. Belt-conveyors shall be fully covered to avoid air borne
dust. Side cladding all along the conveyor gantry should be made to avoid air borne dust. Drills shall
be wet operated or fitted with dust extractors.
Compliance:- Complied by PP.
Measures taken by Kusmunda OCP for provision of dust suppression systems in CHPs, Coal stock
yards, crushers/feeder and breaker material transfer points etc are as follows:
Use of surface miners for coal winning & production eliminates the requirement of drilling and
blasting in coal and further need of crushing of coal in crushers. However, few Crushers have
been deployed at coal stock yards for breaking of some ROM coal into -100 mm size for coal
transportation. These crushers are well equipped with mist spray arrangement & control dust at
source.
CHP Phase-I (20,000 Te Bunker & Truck Receiving Station -1) is state of art fully covered
conveyor belt system equipped with Mist and nozzle spray arrangement at unloading & transfer
points to arrest fugitive emission.
CHP Phase-II (4 no. of Silos & Truck Receiving Station -2) also feeds coal from TRS-II into 4
no. of silos through fully covered conveyor belt system equipped with Mist and nozzle spray
arrangement at unloading & transfer points to arrest fugitive emission. TRS-II is covered from
three sides & is equipped with mist spray sprinklers system for effective dust suppression. The
nozzles are checked daily and repaired/cleaned on daily basis.
CHP Phase-III – In-Pit Belt Conveyor & two 40,000 Te O.H. Bunkers are under construction. It
will also be fully covered to arrest air-borne dust during coal transportation with built-in mist
spray & jet sprayers at unloading & transfer points. Work Order copy attached as Annexure-
17.
All Fixed & Mobile Crushers are well equipped with Mist and nozzle spray arrangement at
unloading & transfer points to arrest fugitive emissions.
All Drill machines are provided with a Dust extractor equipped with fabric filter and wet
drilling arrangement.
Side Cladding has been provided at all incline parts of the conveyors gantry to avoid air borne
dust.
39
FULLY COVERED CONVEYOR BELT SYSTEM WITH SIDE CLADDING
FEEDING COAL INTO SILOS OF KUSMUNDA OCP
40
MIST SPRAY ARRANGEMENT AT LOADING POINTS CRUSHERS & SILOS
AT KUSMUNDA OCP
41
DRILL MACHINE FITTED WITH WET DRILLING ARRANGEMENT
KUSMUNDA OCP
(vi) Condition:-Crushers shall be operated with effective control measures viz. bag filters/water or mist
sprinkling system etc to check fugitive emissions from crushing operations, conveyor system,
transfer points. etc.
Compliance:- Being Complied by PP.
CHP Phase-I (20,000 Te Bunker & Truck Receiving Station -1) is state of art fully covered
conveyor belt system equipped with Mist and nozzle spray arrangement at unloading & transfer
points to arrest fugitive emission.
CHP Phase-II (4 no. of Silos & Truck Receiving Station -2) also feeds coal from TRS-II into 4
no. of silos through fully covered conveyor belt system equipped with Mist and nozzle spray
arrangement at unloading & transfer points to arrest fugitive emission. The nozzles are checked
daily and repaired/cleaned on daily basis.
All Fixed & Mobile Crushers are well equipped with Mist and nozzle spray arrangement at
unloading & transfer points to arrest fugitive emissions.
Side Cladding has been provided at all incline parts of the conveyors gantry to avoid air borne
dust.
As per the Coal Mining Standards 2000 published in Gazette Notification of Ministry Of
Environment & Forests, G.S.R. 742 (E) dated 25.09.2000, values of PM100, PM10, NOx &
SO2 concentration at OITDS/Workshop No. 3 (near CHP P-II) & Workshop No 1 (near CHP P-
I) within 500 metres of the above dust generating sources are well within the permissible limits.
Air Quality Monitoring Report of September 2022 is enclosed as Annexure-15. Fugitive
emission standards, stipulated by CPCB for coal washeries, are not applicable for coal mines
like Kusmunda OCP.
(vii) Condition:-Ground water, excluding mine water, shall not be used for mining operations. Rainwater
harvesting shall be implemented for conservation and augmentation of ground water resources.
Compliance:- Complied by PP.
Only Mine water is used and re-used for mining activities like dust suppression of haul
roads, Washing of HEMMs, CHP, quenching and plantation activities. Groundwater to the tune of
42
277 KLD through 2 Bore wells is being used for meeting the needs of domestic uses within the
mining area for which NOC from CGWA, New Delhi is obtained from time to time. Canal water is
being used for meeting the needs of domestic uses within the colonies & R&R sites through overhead
water tank storage structures.
(viii) Condition:-Catch/garland drains and siltation ponds of appropriate size shall be constructed around
the mine working, coal heaps & OB dumps to prevent run off of water and flow of sediments directly
into the river and water bodies. Further, dump material shall be properly consolidated/ compacted
and accumulation of water over dumps shall be avoided by providing adequate channels for flow of
silt into the drains. The drains/ ponds so constructed shall be regularly de-silted particularly before
onset of monsoon and maintained properly. Sump capacity should provide adequate retention period
to allow proper settling of silt material. The water so collected in the sump shall be utilized for dust
suppression measures and green belt development. Dimension of the retaining wall constructed, if
any, at the toe of the OB dumps within the mine to check run-off and siltation should be based on the
rainfall data. The plantation of native species to be made between toe of the dump.
Compliance:- Being Complied by PP.
Kuchha/ garland drain of average dimension 3500m x 4.0m x 2.5m has been constructed all
along the periphery of the quarry for channelling of run- off water during rainy season. The drains are
periodically de-silted before Monsoon every year. Copy of some work orders are attached as
Annexure-32.
43
KUCCHA/ GARLAND DRAIN CONSTRUCTED ALONG
COAL STOCK YARD NO. 28 KUSMUNDA OCP
Catch drain of various sizes (width up to 4.2 m. and depth up to 3.0 mtr.) and at different
locations are regularly prepared and cleaned before monsoon. 2 nos. of Silting/ Sedimentation pond
also has been constructed of size 122mx35mx2m (8540 m3) & 40M x 60Mx 3M (7200 m3). Work
has been awarded for construction of gabion walls at various locations of mine on 07.09.2022
44
SEDIMENTATION / SILTATION PONDS
KUSMUNDA AREA
External dumps around the river periphery have been completely stabilized with dense
plantation & have been provided with check dams, retaining walls etc. to avoid the flow of silt into
the rivers. Sump capacity and pumping capacity for dewatering of quarry area are planned properly
for monsoon as well as lean period so as to provide adequate retention period to allow proper settling
of silt material. Copy of Monsoon Action Plan for FY 2022-23 is enclosed as Annexure-33. Mine
water is stored in the mine sumps and the settled water after sedimentation is used for industrial
demand like dust suppression, HEMM washing, plantation and in CHP. The excess treated water
available after mine usage is discharged into the main water stream/nallah.
SUMPS INSTALLED WITH PUMPS FOR DEWATERING FROM THE MINE PIT
KUSMUNDA OCP
45
RETAINING WALL AT THE TOE OF OLD OB DUMP, KOCP
(ix) Condition:-Industrial waste water generated from CHP, workshop and other waste water, shall
be properly collected and treated so as to conform to the standards prescribed under the Environment
(Protection) Act, 1986 and the Rules made there under, and as amended from time to time. Oil and
grease trap shall be installed and maintained fully functional with effluents discharge adhering to the
norms. Sewage treatment plant of adequate capacity shall be installed for treatment of domestic
waste
46
Compliance:- Being Complied by PP.
One Domestic Effluent Treatment Plant (DETP) of capacity 2 MLD for treating waste water
from the township was commissioned in 2001 at a cost of 222 Lakhs and it is functioning efficiently
and satisfactorily. Photographs of working DETP are pasted below:
Presently, an RCC Settling Tank with Sludge Drying Bed (Capacity: 540m 3) has been
constructed for treatment of mine discharge water for industrial use at an estimated cost of Rs 27.65
Lakhs and commissioned along with newly constructed CHP.
47
RCC SETTLING TANK WITH SLUDGE DRYING BED AT CHP PHASE-I, KUSMUNDA OCP
Old Oil & Grease Trap has been dismantled. A new Effluent Treatment Plant (ETP) (Cost:
40 Lakhs) of enhanced capacity for meeting the requirement of new HEMMs, as per PR of 50 MTY,
is under construction at new integrated workshop of Kusmunda OCP. It is expected to be
commissioned by 31.12.2022 (Work Order copy is enclosed as Annexure-34).Details are as below:
Requirement: 240Te, 100Te and 60 Te Dumper/HEMM washing
Number of Settling tanks: 03 Nos.
Capacity: 2300m3 each with 1240 m3 recycling capacity (80%).
Dimensions: Length:65 m X Width 12m X Height 4m each.
48
Two Reservoirs of 70000 KL& 30000 KL have been planned & estimate moved for
approval for final settling of mine water before discharge into local water bodies. Effluent water
quality is being regularly monitored and action taken as per the requirement. A copy of the Effluent
Quality report for the month of September, 2022 is enclosed as Annexure- 15.
(x) Condition:-Adequate groundwater recharge measures shall be taken up for augmentation of ground
water. The project authorities shall meet water requirement of nearby village(s) in case the village
wells go dry due to dewatering of mine.
Compliance:- Being Complied by PP
Following Artificial Water recharge measures have been implemented in Kusmunda OC for
augmenting natural groundwater resources:
1. Rain water harvesting system is being practiced to recharge the ground with rain water at
following eight locations at present:
49
RAIN WATER HARVESTING STRUCTURE AT CAAQMS BUIDLING,
KUSMUNDA AREA
50
RAIN WATER HARVESTING STRUCTURE AT KUSMUNDA HOUSE, KUSMUNDA
AREA
2. Sedimentation pond of capacity 122mx35mx2m (8540 m3) & One Siltation Pond of capacity
40M x 60Mx 3M (7200 m3) near siding are acting as a source for recharging the ground water.
3. Deepening of the Sarvamangla Nagar pond which will act as a recharge structure for the
Groundwater in the up dip side of the mine has been completed.
4. Old water logged quarry (310mx160mx20m) near Dump No.14 (Jatraj Village) of Kusmunda
OCP also acts as a water recharge structure.
5. Under the Corporate Social Responsibility (CSR) works, many ponds have been constructed/
deepened to recharge the ground water with rain water.
6. Plantation of over 24 lakh saplings since 1992 over an area of 619 Ha acts as natural recharge
area for rainwater harvesting.
7. Various Check Dams/ Stop Dams have been constructed to arrest the flow of Rain Water in
nearby Nallahs/ surface water bodies like Laxman Nallah etc.
51
STOP DAM AT LAXMAN NALLAH, KUSMUNDA AREA
8. A report regarding “Comprehensive Catchment Treatment Plan in the area to arrest flow of silt
in the Hasdeo River & to improve water regime in respect of Kusmunda Expansion OC Project”
has been prepared and submitted by Chhattisgarh Council of Science and Technology, Raipur
vide no. 1804 dated 22.02.2020. Check dams/ appropriate embankments like vegetative bunds,
check dams, nallah bunds etc. are being taken up along major water bodies as per the
recommendations of the above study.
9. A suitable plan for de-siltation & deepening of about 33 no. of village tanks & other water
bodies (along with their GPS Coordinates) located within 5 kms from the Mine Lease Boundary
of Kusmunda OC Project has been prepared for a four year period (i.e. from, FY 2022-23 to FY
2025-26) by Kusmunda Area & duly verified by DFO, Katghora.
10. Two Reservoirs of 70000 KL& 30000 KL have been planned & estimate moved for approval
for final settling of mine water before discharge into local water bodies
52
The project authority meets the requirement of the Drinking water in nearby villages by following
measures:
1. By supplying potable water through mobile tanker in nearby villages (Work order copy attached
as Annexure- 36)
2. Under Corporate Social Responsibility (CSR) works, many works like hand pumps, installation
of submersible pumps along with PVC Water tanks, construction of nirmal ghats/ stop dams,
construction of Overhead Water tanks etc have been undertaken in nearby villages.
3. Measures adopted under Catchment Area Treatment Plan & “Narwa garwa ghurwa badi”
Yojana of Chhattisgarh by State Forest Department will further add to the capacity of
groundwater availability in the nearby areas.
Some Photographs of different works carried out for drinking water & clean sanitation in nearby
villages & R&R sites are provided below:
53
DRINKING WATER SUPPLY AT CONSTRUCTION OF NIRMAL GHAT
NARAIBODH VILLAGE AT KANHAIYABHATA VILLAGE
54
BOREHOLE FACLITIES PROVIDED AT SHANTINAGAR AND
MONGRABATA VILLAGE UNDER CSR HEAD, KUSMUNDA AREA
Adequate illumination is ensured in all mine locations (as per DGMS standards) and monitored on a
daily basis. Moreover, from time to time, arrangements are made for portable DG set Lighting
System in the mines wherever required. Illumination survey is carried out on a monthly basis,
reviewed daily and made sure that lightning required for mining activities is restricted within the
premises so as not to disturb the human and animal population around mine. Copies of Latest
Illumination Survey Report is enclosed as Annexure-14.
55
(ii) Condition:-Adequate measures shall be taken for control of noise levels below 85 dB(A) in the
work environment. Workers engaged in blasting and drilling operations, operation of HEMM, etc
shall be provided with personal protective equipment (PPE) like ear plugs/muffs in conformity with
the prescribed norms and guidelines in this regard. Adequate awareness programme for users to be
conducted. Progress in usage of such accessories to be monitored.
Compliance:- Complied by PP.
To control the Noise Pollution at Kusmunda Open Cast Mine the following measures are adopted:
Stress on use blasting free technology of Surface Miner mining in coal mines.
Proper maintenance of equipment to minimize vibration;
All HEMMs are provided with noise proof cabins for operators. Extensive plantation done
on over burden dumps, which act as noise barrier between mines area and residential area.
Thick green belts developed around residential areas, along colony roads, coal
transportation road and around the mine infrastructure, also act as noise barrier.
Employees who are exposed to higher level of noise are provided with ear plugs.
Generally blasting operation is carried out between 1 pm to 3 pm with minimum no. of
persons within the mine premises.
Vocational, Special training and On spot training is also carried out to provide information
about safety and health aspects by VTC personnel/Safety Personnel regularly.
Noise Level Monitoring is being regularly done on a fortnightly basis & values are below
the standard limits. Copy of Sep 2022 Noise Monitoring Report is enclosed as Annex – 15.
7803 nos. 423 pairs 1298 pairs 921pairs 494 nos. 952 nos.
Photograph of worker wearing dust mask and photographs of personnel protective equipment are
given below:
Majority coal production of Kusmunda Open Cast Project is done by surface miner which
eliminates blasting in coal. However, at OB benches, blasting is done by controlled blasting
technique with delay detonators and blasting is carried out only during day time. Controlled
blasting is practiced as per rules and regulations stipulated by the DGMS and monitoring of the
ground vibration during blasting is done regularly. Copy of some Vibration cum Blasting reports
are enclosed as Annexure-37.
(iv) Condition:-The noise level survey shall be carried out as per the prescribed guidelines to assess
noise exposure of the workmen at vulnerable points in the mine premises, and report in this regard
shall be submitted to the Ministry/RO on six-monthly basis.
Compliance:- Complied by PP.
Noise Level Monitoring is being regularly done on a fortnightly basis & report is being
submitted to Regional office of MoEF&CC & to Member Secretary, State Pollution Control Board
on a monthly basis. Noise Monitoring report for the month of September, 2022 is enclosed in
Annexure-15, which clearly shows that the noise levels at Kusmunda area are well below 85
dB(A).
As per The Mines Act, 1952, Periodical Occupational health check-up for one-third of the
employees of the project is carried out every year in which workers is being subjected to full health
check-up like ECG for Cardiac function, X-Ray for occupational diseases and audiometry test for
hearing impairment, and a composite annual, disease wise, medical examination report is sent to
Chief of Medical Services, SECL and a detailed report is sent to DGMS.
A copy of PME done at Kusmunda Area is enclosed as Annexure-38. Target and achievement
of periodical medical examination in past five years is as follows:
57
TOTAL TOTAL PME TOTAL PME ACHIEVEMENT
YEAR
MANPOWER TARGET ACHIEVED %
(ii) Condition:-Personnel (including outsourcing employees) working in dusty areas shall wear
protective respiratory devices and shall also be provided with adequate training and information on
safety and health aspects.
Compliance:- Complied by PP.
Persons working in dusty areas are provided with dust mask. The workers are adequately
trained and informed regularly by experienced Doctors about the safety and health aspect during
vocational training / special training at group VTC Kusmunda Area and On spot training is also
carried out at the working site itself to provide information about safety and health aspects by VTC
58
personnel/Safety Personnel regularly (Annexure-39). Details of PPE Equipment distributed in the
period for the FY 22-23 (Apr-Sep) are as below:
Dust Masks Leather Boots Gum Boots Canvas Shoes Helmets Fluorescent jackets
7803 nos. 423 pairs 1298 pairs 921pairs 494 nos. 952 nos.
(iii) Condition:-Skill training as per safety norms specified by DGMS shall be provided to all workmen
including the outsourcing employees to ensure high safety standards in mines.
Compliance:- Complied by PP.
Experienced doctors are called at group VTC for giving training to the departmental as well
as the contractual workers during their vocational training and special training courses at VTC,
Kusmunda project. The outsourced manpower is briefed regularly regarding safety and health
issues at their working site / camps by the VTC personnel/Safety Personnel as well as Medical
experts as a part of On Spot training programme / health camps. Skill development and livelihood
training was provided to 16 PAPs from Central Institute of Plastics Engineering and Technology
(CIPET), Raipur on 18th Feb, 2019. (On Spot Training details are enclosed as Annexure-39)
Regular measures/tasks as per the action plan submitted during public hearing are regularly
reviewed and changes are made as when necessary. R&R is being done as per CIL R&R policy
60
2012 & Chhattisgarh Rajya Adarsh Punarvas Niti-2007 and employment is provided to project
affected persons as per approved policy. Action taken report of Public Hearing Proceedings held on
11.02.2015 is enclosed as Annexure-40. For keeping commitments made to public during Public
hearing proceedings, Kusmunda OCP has carried out an expenditure of Rs 2.82 Cr in FY 22-23
upto 30.09.22. (Copy of expenditure statement is enclosed as Annexure- 09).
(ii) Condition:-The project proponent shall ensure the expenditure towards socio-economic
development in and around the mine, in every financial year in pursuance of the Corporate Social
Responsibility Policy as per the provisions under Section 135 of the Companies Act, 2013.
Compliance:- Being Complied by PP.
CIL has one of the best & well-defined CSR Policy which has been framed after
incorporating the features of the Companies Act 2013 and as per notification issued by Ministry of
Corporate Affairs, Govt. of India on 27.02.2014 as well as DPEs guidelines.
CSR Work Action Plan is being prepared in consultation with local villagers every year &
finalized with the approval of District Collector under Deposit Scheme.
Various CSR work for basic amenities are being done like Community Hall, School, Market
place, Stop Dam, Roads, hand pumps, bore wells, overhead water tanks, etc. In Addition to above,
free medical facility is being provided to the BPL Card holders & the project affected persons in
SECL Hospitals. Medical Camps are also being organized in affected villages for regular health
check & monitoring. CSR Expenditure for FY 2022-23 (Apr-Sep) is Rs 1.75 Lakhs.
61
Few Major Expenditures done towards socio-economic development under CSR head at
Kusmunda Area:
1. Construction of Cement Concrete Road in Km 50/6 to 55/4 = 5 Km of Seepat-Baloda-Urga Road
including reconstruction of damaged hume pipe culverts in Korba Distt. – Rs 1003.00 Lakhs
2. Construction of toilets under Swachh Bharat Abhiyan-Rs 987.80 Lakhs.
3. Various other initiatives are taken by the firm to implement recharge measures along with provision
of safe drinking water and sanitation under CSR head and ODF schemes are as follows:
Drinking water is being supplied to different villages like Pali, Padania, Khodri, Birda, Amgaon
(Approximate cost Rs. 20 Lakhs) under Kusmunda Area throughout the year.
One bore hole including submersible pump was provided in school at ward No.57 at
Mongrabhata and one bore hole including submersible pump has been provided in school at
ward 56 has been constructed under CSR head of Kusmunda Area.
Financial Assistance (Rs. 171.86 Lakhs) has been provided to Distt. Collector, Korba for
construction of 1299 no. of toilets for Open defecation free (ODF) on saturation basis at 9 no. of
gram panchayats of Korba district under CSR head of SECL Kusmunda Area.
62
CONSTRUCTION OF CC ROAD INSIDE THE KHAIRBHAWANA VILLAGE,
KUSMUNDA AREA
63
DRINKING WATER TANKS PROVIDED AT VILLAGE CHURAIL, KUSMUNDA AREA
(iii)Condition:-The project proponent shall follow the mitigation measures provided in this Ministry's
OM No.Z-11013/5712014-IA.11 (M) dated 29th October, 2014, titled 'Impact of mining activities
on habitations-issues related to the mining projects wherein habitations and villages are the part of
mine lease areas or habitations and villages are surrounded by the mine lease area‟.
Compliance:- Being Complied by PP.
Action Taken Report of the Ministry‟s OM dated 29th October 2014 is enclosed as
Annexure- 13.
(iv) Condition:-The project proponent shall make necessary alternative arrangements, if grazing land is
involved in core zone, in consultation with the State government to provide alternate areas for
livestock grazing, if any. In this context, the project proponent shall implement the directions of
Hon'ble Supreme Court with regard to acquiring grazing land.
Compliance:- Agreed by PP
Suitable Grazing Land will be provided for livestock grazing beyond the safety zone of the mine
leasehold area after necessary possession of the acquired land of Kusmunda Opencast Expansion
Project 50 MTY & development of safety zone area.
64
A well laid down Environmental policy as per ISO 14001 & approved by the Board of
Directors already exists & reads as “Coal India Limited(CIL) is committed to promote sustainable
development by protecting the environment through integrated project planning & design,
prevention/ mitigation of pollution, conservation of natural resources, restoration of ecology &
biodiversity, recycling/ proper disposal of wastes, addressing climate change and inclusive growth.
It also aims to bringing awareness amongst its stakeholders for continual improvement in
environmental performances following best practices”. Copy enclosed as Annexure –42.1.
(ii) Condition:-The hierarchical system or Administrative Order of the company to deal with
environmental issues and for ensuring compliance with the environmental clearance conditions
should be displayed on website of the Company.
65
(iii)Condition:-A separate environmental management cell both at the project and company
headquarter level, with suitable qualified personnel shall be set-up under the control of a Senior
Executive, who will report directly to the Head of the Organization.
Compliance:- Complied by PP.
Under the direct control of Director (Opr) of SECL, a separate Environment Management
Cell is already functional with sufficient no. of executives & staff headed by GM (Env) at
Headquarters, Bilaspur.
At Area level, an Environment Management cell functions under the direct control of Area
GM, headed by Nodal Officer (Env/Forest) with sufficient nos. of Executives & staff members
along with a Nodal Officer (Env/Forest) at project level to oversee day to day monitoring.
(iv) Condition:-Action plan for implementing EMP and environmental conditions shall be prepared and
shall be duly approved by competent authority. The year wise funds earmarked for environmental
protection measures shall be kept in separate account and not to be diverted for any other purpose.
Year wise progress of implementation of action plan shall be reported to the Ministry/Regional
Office along with the Six Monthly Compliance Report.
Compliance:- Complied by PP.
As per approved Project report for expansion of Kusmunda OCP 15.00 MTPA to 50.00
MTPA funds have been earmarked in separate account for environmental programmes in Capital as
well as Revenue heads. In Capital head funds earmarked are 575.33 Crores, in Revenue head funds
earmarked is 86.03 lacs per annum which includes land reclamation cost as 83.33 lacs.
Year wise expenditure is being incurred for the above funds earmarked in the approved PR.
An amount of Rs 19 Crores has been incurred on environment management during financial year of
2022-23 (Apr-Sep).
(v) Condition:-Self Environmental Audit shall be conducted annually. Every three years third party
environmental audit shall be carried out.
Compliance:- Complied by PP.
A Revenue cost of Rs 20,000 per annum has been reserved for Environmental Audit
purposes in the Project Report of 50 MTY of Kusmunda Expansion Project. Internal Audit of the
EC Conditions of all mines is being regularly carried out by GM(Envt) at CIL Level & Director
(Tech) at SECL Level. Review meetings are being held at SECL HQ on a regular basis to resolve
issues of all mines for compliance of Environmental Conditions.
66
its Mitigation in Coal India Limited and its Subsidiaries”. A follow-up audit of its report is
presently underway by CAG audit team in SECL in 2022.
Moreover, proposal for carrying out third party assessment of EC Compliance of Kusmunda
OCP through ICFRE, Dehradun on nomination basis in FY 2022-23 under MoU of ICFRE with Coal
India Limited has been approved from competent Authority. Work has been awarded to ICFRE,
Dehradun for the above said same vide no. SECL/GM/KSM/ENV/22-23/146 dated 01.10.2022 (copy
of letter enclosed as Annexure-19).
Self-Audit of Environmental clearance compliance is regularly carried out by the
Environment team of SECL Kusmunda Area & shortcomings are pointed out & submitted in
writing to General Manager (Mining) / Project Head of Kusmunda OCP (Enclosed as Annexure-
19.1). Shortcomings are thus rectified on a regular basis by the mine management.
(iii)Condition:-The project proponent shall obtain Consent to Establish/Operate under the Air Act,
1981 and the Water Act, 1974 from the concerned State Pollution Control Board.
Compliance:- Complied by PP.
M/s Kusmunda Opencast Project has obtained Renewal of Consent to Operate for Air &
Water for a peak capacity of 50 MTPA (Normative)/62.5 MTPA (Peak) from CECB, Atal Nagar,
Raipur vide letter no. 6568 dated 14.12.2021 with a validity up to 31.12.2022. Compliance of the
conditions is under progress. (Copy of Valid Consent to Operate is attached as Annexure-05)
(iv) Condition:- The project proponent shall obtain the necessary permission from the Central
Ground Water Authority (CGWA).
Compliance:- Being Complied by PP.
Kusmunda area had applied for Groundwater NOC vide application no. 21-4/329/CT/MIN/2016
& had obtained:
1. Original NOC vide NOC No. CGWA/NOC/MIN/ORIG/2017/2416 dated 16.02.2017 with
a validity upto 19.01.2019 (Copy attached as Annexure-06)
67
2. First Renewal vide NOC No. CGWA/NOC/MIN/REN/1/2020/5628 dated 27.01.2020 with
a validity upto 18.01.2022. (Copy attached as Annexure-06)
3. Kusmunda Area had applied for 2nd Renewal on 15.01.2022 along with an interim report
of Impact Assessment with GW modelling in respect of Kusmunda OCP. (Application
Copy attached as Annexure-06)
Final Impact Assessment report has been submitted to CGWB, Raipur in the month of July,
2022 vide no. SECL/GM(M)/KOCP/22-23/926 dated 24.06.2022 in compliance with GW
guidelines, 2020 (Copy attached as Annexure-07). The application is under process at CGWA,
New Delhi since 22.08.2022.
(J) MONITORING OF PROJECT
(i) Condition:-Adequate ambient air quality monitoring stations shall be established in the core zone
as well as in the buffer zone for monitoring of pollutants, namely PM10, PM2.5, S02 and NOx.
Location of the stations shall be decided based on the meteorological data, topographical features
and environmentally and ecologically sensitive targets in consultation with the State Pollution
Control Board. Online ambient air quality monitoring stations may also be installed in addition to
the regular monitoring stations as per the requirement and/or in consultation with the SPCB.
Monitoring of heavy metals such as Hg, As, Ni, Cd, Cr, etc to be carried out at least once in six
months.
Compliance:- Complied by PP.
Total 09 nos. of ambient Air quality monitoring stations has been installed, out of which
04nos. are in core zone and 05 nos. are in buffer zone, in consultation with State Pollution Control
Board. The ambient Air quality monitoring is done by CMPDIL. The report of the same is being
regularly submitted to State Pollution Control Board on a monthly basis. The Monitoring Report for
Air, Water & Noise Quality of Kusmunda Area for the month of September, 2022 is enclosed as
Annexure-15 respectively.
In addition to above, Continuous Ambient Air Quality Monitoring Station has been installed
in front of Kusmunda Project Office for monitoring of ambient air quality round the clock in
consultation with SPCB as a part of Korba Action Plan. A copy of the Continuous Ambient Air
Monitoring report is enclosed as Annexure-28.
Heavy Metals Analysis is also being carried out by CMPDIL on a six monthly basis. A copy
of the Heavy Metals Monitoring report for the period of Jan-June 2022 is enclosed as Annexure-
43. Annual effluent report for the FY 2022-23 is enclosed as Annexure-44.
68
(ii) Condition:-The Ambient Air Quality monitoring in the core zone shall be carried out to ensure the
Coal Industry Standards notified vide GSR 742 (E) dated 25.9.2000 and as amended from time to
time by the Central Pollution Control Board. Data on ambient air quality and heavy metals such as
Hg, As, Ni, Cd, Cr and other monitoring data shall be regularly reported to the Ministry/Regional
Office and to the CPCB/SPCB.
Compliance:- Complied by PP.
Monthly reports of Ambient Air Quality as well as Six Monthly Reports of Heavy Metals
Monitoring are being regularly submitted to CECB, Naya Raipur as per the guidelines of CPCB &
to Integrated Regional Office, MOEF&CC Raipur on a regular basis. The Ambient Air Quality
monitoring in the core zone is being carried out by CMPDIL to ensure the Coal Industry Standards
notified vide GSR 742 (E) dated 25.9.2000 and as amended from time to time by the Central
Pollution Control Board. The Monitoring Report for Ambient Air Quality of Kusmunda Area for
the month of Sep, 2022 is enclosed as Annexure-15.
Heavy Metals monitoring report are submitted to CECB, Naya Raipur & Integrated
Regional Office, MoEF&CC, Raipur on a six monthly basis. Heavy Metals Monitoring report for
the period of Jan-June 2022 is enclosed as Annexure-43.
(iii)Condition:-The effluent discharge (mine waste water, workshop effluent) shall be monitored in
terms of the parameters notified under the Coal Industry Standards vide GSR 742 (E) dated
25.9.2000 and as amended from time to time by the Central Pollution Control Board.
Compliance:- Complied by PP.
Monthly reports of Effluent Quality are being regularly submitted to CECB, Raipur & to
Integrated Regional Office, MOEF&CC Raipur on a monthly basis. The effluent discharge (mine
waste water, workshop effluent) are being monitored in terms of the parameters notified under the
Coal Industry Standards vide GSR 742 (E) dated 25.9.2000 and as amended from time to time by
the Central Pollution Control Board. A copy of the Effluent Quality report for the month of Sep,
2022 is enclosed as Annexure- 15. Annual effluent report for the FY 2022-23 is enclosed as
Annexure-44.
(iv) Condition:-The monitoring data shall be uploaded on the company‟s website and displayed at the
project site. The circular No.J-20012/1/2006-IA.11 (M) dated 27thMay, 2009 issued by Ministry of
Environment, Forest and Climate Change shall also be referred in this regard for its compliance.
Compliance:- Complied by PP.
The Continuous monitoring data of Ambient Air Quality Parameters of Kusmunda Area are
being continuously displayed at the entrance of Project office/CAAQMS Building. Half Yearly
Compliance Reports & Satellite Imagery Reports of Kusmunda Area are being uploaded on the
company‟s website for public scrutiny.
69
Monitoring details of Air/Water/Noise/Heavy Metals, Drinking Water Parameters,
Plantation details, Area covered under plantation, Latest Vibration Cum Blasting Reports,
Vehicular Emission Reports, Data on PPE provided, Training, etc. all form a part of the Half Yearly
Compliance Reports which have been uploaded on the website of SECL/CIL.
(v) Condition:-Regular monitoring of ground water level and quality shall be carried out in and around
the mine lease area by establishing a network of existing wells and constructing new piezometers
during the mining operations. The monitoring of ground water levels shall be carried out four times
a year i.e. pre-monsoon, monsoon, post-monsoon and winter. The ground water quality shall be
monitored once a year, and the data thus collected shall be sent regularly to MoEF&CC.
Compliance:- Complied by PP.
Regular ground water level is being monitored through existing wells in nearby villages and
4 sets/ 10 Nos. of Piezometers located at GM Office (02), Sarvamangla Nagar (03), Padania (02)&
Amgaon (04). 7 Nos. of Automatic Digital Water Level Recorders have been procured for
Automatic & Real Time monitoring of piezometer readings at these locations. It has been installed
in one piezometer as on date as per NOC Condition. Piezometer readings is enclosed as Annexure
45.
Ground water quality (bore wells) is regularly being monitored at nearby locations on a
quarterly basis by CMPDIL. Groundwater Quality for July-Spet 2022 period is enclosed as
Annexure- 46.1.
Drinking Water Quality is being monitored at 3 locations: Chun- Chuni Colony, Gevra Basti
& Vikas Nagar Colony, on a monthly basis. Drinking Water quality report for the month of Sep‟22
is enclosed as Annexure-46.2.
Open Dug Well Monitoring is being done at 28 locations on a quarterly basis & the report
for is enclosed as a part of Half Yearly Compliance and submitted to Regional Office of the
Ministry and State Pollution Control Board. A Report on six monthly basis on changes in Ground
water level and quality is submitted to the Regional Office of the Ministry, CGWA & Member
Secretary, CECB, Raipur on a half yearly basis. Dug well monitoring readings for FY 22-23 is
enclosed as Annexure- 47.
70
(vi). Condition:-Monitoring of water quality upstream and downstream of water bodies shall be
carried out once in six months and record of monitoring data shall be maintained and submitted to
the Ministry of Environment, Forest and Climate Change/Regional Office.
Compliance:- Complied by PP.
Water Quality is being done monitored fortnightly at two locations – upstream &
downstream of the point where the outlet from Kusmunda Mine meets Hasdeo River to assess the
changes in water quality of the River. The results are being regularly submitted to CECB, Naya
Raipur as per the guidelines of CPCB & to Integrated Regional Office, MoEF&CC, Raipur on a
monthly basis. Effluent Quality Monitoring Report of Sep 2022 is enclosed as Annexure-15.
(vi) Condition:-The project proponent shall submit six monthly reports on the status of the
implementation of the stipulated environmental conditions to the Ministry of Environment, Forest
and Climate Change/Regional Office. For half yearly monitoring reports, the data should be
monitored for the period of April to September and October to March of the financial years.
Compliance:- Complied by PP.
(vii) Condition:-The Regional Office of this Ministry shall monitor compliance of the stipulated
conditions. The project authorities should extend full cooperation to the officer(s) of the Regional
Office by furnishing the requisite data /information/monitoring reports.
Compliance:- Agreed by PP.
(K) MISCELLANEOUS
(i) Condition:-Efforts should be made to reduce energy consumption by conservation, efficiency
improvements and use of renewable energy.
Compliance:- Complied by PP.
Sustainable Development Cells (SDC) have been created in MoC, CIL and its subsidiary
companies for focusing on environment mitigation measures in a systematic manner and for
providing better environment to people working and residing in the vicinity of the mine. This will
also help in improving the overall image of coal sector in the country. The main role of this
dedicated cell is for generating new ideas, preparing guidelines, monitoring and evaluating different
environmental mitigation measures. Annual Sustainability Report, 2020-21 & ESG Report of FY
2020-21 of Coal India Limited (CIL) are available at the following link:
https://www.coalindia.in/departments/environment/reports-env/
71
Role of Kusmunda Area: CIL is creating an inventory of land available with its different projects
& in this regard, Kusmunda Area has given an availability of 49.376 Ha of land for solar power
project.
In addition to this following measures are being taken up at Kusmunda area for reducing energy
consumption, efficiency improvements & use of renewable energy:-
1. Work has been awarded for installation of solar panels/rooftops (65 nos.) vide no. 1566100 on
5.01.22 for a quantity of 65 units at a cost of 26.43 lakhs for Kusmunda Area. Site visit has
been completed and locations have finalized at GM Office, Kusmunda Bhavan and Rescue
office for installation. (Copy of Work Order is enclosed as Annexure-48).
2. Halogen lamps are being replaced by LED Lighting system in the mines.
3. Proper maintenance of Lighting, working of AC cabins, electrical equipment etc. in HEMM
helps in maintaining efficiency of their working & thus reduces energy consumption.
4. Distribution of LPG Cylinders to the employees & workers helps in restriction of burning of
coal for domestic use. Number of LPG connections provided till date: 5144 nos.
5. Technological upgradation like High Capacity HEMM, New Bunker with State of Art
technology, upcoming of Silos & in-pit conveyor belt, Washery, Integrated Workshop etc. will
help in efficiency improvements & energy savings on a large scale in the cradle to gate cycle of
Kusmunda OCP.
6. Expenditure towards energy conservation for the FY 21-22 is 2.18 crores & Target for FY
2022-23 is 7.5 Crores (Copy of Expenditure statement is enclosed as Annexure-49).
7. Timers have been provided in all colonies and mines for auto start and stop to save energy &
energy savings on a large scale in the cradle to gate cycle of Kusmunda OCP.
8. Solar roof tops have been installed at 5 different locations namely at Substation 1, Rest shelter,
Time office, Administrative offices (E&M, Excv. each )inside New Integrated workshop
campus with a capacity of 200 kW. Photographs are as shown below:
72
INSTALLATION OF SOLAR ROOF TOPS AT NEW INTEGRATED WORKSHOP, KOCP
(ii) Condition:-The project authorities shall inform to the Regional Office regarding commencement of
mining operations.
Compliance:-Complied by PP.
Regional Office, MoEF&CC, Nagpur has been intimated about the commencement of the
mining operations for enhancement in capacity from 40.00 MTY to 50.00 MTY (Normative)/62.5
(Peak) vide letter No 5422 dated 21/01/2020. Copy of the same has been enclosed as Annexure-50.
A copy of the environmental clearance from 40.00 MTY to 50.00 MTY (Normative)/62.5
(Peak) has been marked to concerned Panchayat, State Pollution Control Board, Regional Office,
District Industry Sector and Collector's Office/Tehsildar Office for information in public domain
vide Ref no. 617 & 620 dated 11.01.2020 respectively. Copies of the same are enclosed as
Annexure-51.
(iv) Condition:-The EC shall be uploaded on the company's website. The compliance status of the
stipulated EC conditions shall also be uploaded by the project authorities on their website and
updated at least once every six months so as to bring the same in public domain.
Compliance:- Complied.
Copies of the EC letter and Half Yearly Compliance Reports are uploaded regularly on the
company‟s website & can be downloaded from the public domain. The copy of latest EC letter can
be downloaded from SECL website url: http://www.secl-cil.in/envt_clearance.php & latest Half
Yearly from url: http://www.secl-cil.in/envt_clearance_compliance_report.php.
73
(v) Condition:-The project authorities shall advertise at least in two local newspapers widely
circulated, one of which shall be in the vernacular language of the locality concerned, within 7 days
of the issue of this clearance, informing that the project has been accorded environmental clearance
and a copy of the same is available with the State Pollution Control Board and also at website of the
Ministry.
Compliance:- Complied by PP.
Advertisements of the EC letter accorded to Kusmunda Project for 50.00 MTY capacity
(Normative)and 62.5 (Peak) have been published in two local daily newspapers Tarun Chhattisgarh
and Dainik Bhaskar –dated 17/01/2020 respectively. Copy of the same is enclosed as Annexure-52.
(vi) Condition:-The environmental statement for each financial year ending 31 March in Form-V is
mandated to be submitted by the project proponent for the concerned State Pollution Control Board
as prescribed under the Environment (Protection) Rules, 1986, as amended subsequently, shall also
be uploaded on the Company's website along with the status of compliance of EC conditions and
shall be sent to the respective Regional Offices of the MoEF&CC by e-mail.
Compliance:- Complied by PP.
Environmental audit statement for the financial year 2021-22 has been submitted to Member
Secretary, CECB, Raipur vide letter no. 173 dated 21/09/22 and to Integrated Regional Office
(IRO), MoEF&CC, Raipur vide letter no. 175 dated 27/09/22 respectively. Copy of the same has
been enclosed as Annexure-53.
(vii) Condition:-The above conditions will be enforced inter-alia, under the provisions of the Water
(Prevention & Control of Pollution) Act, 1974, the Air (Prevention & Control of Pollution) Act,
1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act, 1991 along
with their amendments and Rules and any other orders passed by the Hon'ble Supreme Court of
India/High Courts and any other Court of Law relating to the subject matter.
Compliance:- Agreed.
x---x---x---x---x
74
ANNEXURES
ANNEXURE- 02
SL.
Compliance Conditions of EAC Sub-committee Action Taken Report (As on 30.09.2022)
No Report
1 It is observed from the progressive measures taken a) Final Report on “Air quality monitoring at identified locations of
that: Kusmunda OCP of Kusmunda Area of South Eastern Coalfields
Limited” has been obtained from IIT Kharagpur in the month of July,
a) Order has been placed on IIT Kharagpur 2020. Copy of the same has been submitted to Regional Office,
for monitoring of air Quality on 14/06/2019, the MoEF&CC, Nagpur vide ref no.1756 dated: 26.07.2020. Action taken
final report to be submitted by 15 January 2020. report regarding Recommendations of IIT Kharagpur has been enclosed
as Annexure-03.
b) Work has been awarded for preparation of wild b) SFRTI had withdrawn its consent for the awarded work vide its letter
life conservation plan on 14/06/2018 to State no. 791 dated 17/03/2020 due to shortage of manpower. Work for
Forest Research and Training Institute. “Preparation of Wildlife Conservation Plan including alternative habitat
c) An interim report has been received from development plan for the affected avifauna of core mining area of
Kusmunda Expansion Opencast Project of SECL Kusmunda Area”
Chhattisgarh Council of Science and Technology,
under Katghora Forest Division was then awarded to Shri K.K.Bisen,
Raipur for the work on Comprehensive Retd. CCF, Raipur vide W.O. no. 356 dated 14.08.2021 after due
Catchment Treatment Plan in the area to arrest process. Work has been completed & final copy of the same has been
flow of silt in the Hasdeo River and to improve submitted by Shri K.K.Bisen vide letter no. 17 dated 26.07.2022 (Copy
water regime in respect of Kusmunda OC project. attached as Annexure- 16).
08 Dumper (BH60-60T) 68 86 84
Dumper (CAT60 –
09 54 67 67
60T)
Dumper (BH100-
10 56 56 56
100T)
e) Additional two numbers of 70 KL capacity and e) Details of Water tankers with mist spray arrangement at Kusmunda
2 nos. 28 KL capacity mist spray arrangement Area are as follows:
has been commissioned after 30/11/2018 for
Population as on
effective dust control along coal and OB S. Water Tanker
transportation roads. No Capacity 01.04.2020 01.04.2021 01.04.2022
01 28 KL 04 04 05
02 70 KL 10 10 10
Total 14 14 15
f) A long range water sprinkler with horizontal f) Supply order for one no. of additional Dust Suppression System with
throw of 40 m (min) mounted truck chassis has mist blower/fog forming long range water sprinkler has also been placed
been installed which is working satisfactorily. in FY 21-22 (Work Order copy attached as Annexure-2.1). Delivery has
been delayed by the agency & it is expected to be procured and
commissioned in FY 22-23.
2 Air quality assessment for a period Dec.2018-March Air Quality Assessment has been carried out by Third Party, IIT Kharagpur
2019 has been collected along with a location of in the months of Sept to December 2019 & all readings were found to be
monitoring station and in enclosed as Annexure II. well within permissible limits. Suitable measures are being complied as per
Further, monthly monitoring of Air quality done by the recommendations of the IIT Kharagpur study.
CMPDI has also been collected along with
monitoring station locations for the month of May Also, air quality reports obtained on a monthly basis from CMPDIL along
2019, June 2019, July 2019 and Aug. 2019. with monitoring locations also show the parameters to be within the
a) It is observed that some of the readings of PM10 prescribed standard limits. Environmental Monitoring report for the month
and PM2.5 have marginally exceeded the limited in of September has been enclosed as Annexure-15.
the months of May and June while they are within
limits during July and Aug. 2019 There is a
decreasing trend in PM values from May to Aug.
2019.
ANNEXURE-03
Sir,
Produce the following documents within 15 days as per new guideline notified on 24.09.2020.
While scrutiny of your application the following additional information or attachment for further
process.
1) Self-inspection report on compliance condition on the NOC. The self-inspection carried out
and may be uploaded in the self-inspection module in NOCAP.
-------------------------------------------------
Regional Director
Central Ground Water Board
North Central Chhattisgarh Region
2nd Floor, LK Corporates Tower
Dhamtari Road, Dumartarai
Raipur - 492 015
Email: rdnccr-cgwb@nic.in
Sir,
The self-inspection was carried out and was uploaded in the self-inspection module in NOCAP on
22.01.2022 along with geotagged photographs. Kindly do needful for the issuance of NOC for
groundwater withdrawal in respect of M/S KUSMUNDA OPENCAST MINING PROJECT SECL A
SUBSIDIARY OF CIL.
Regards,
Respected Sir,
With respect to ground water NOC renewal vide Application no: 21-4/329/CT/MIN/2016 dated 15.01.2022 for
Kusmunda OCP, please find enclosed herewith the final Comprehensive report on “Impact assessment report
along with ground water modeling study in respect of Kusmunda OCP” which is being submitted to your kind
office.
Regards,
2 attachments
Submission of Impact assessment report to CGWA from KSM.pdf
607K
Final HG report of SECL Kusmunda_Updated_18_06_2022.pdf
14792K
Dear Sir,
With respect to our previous mail dated 25.06.2022 regarding submission of final impact assessment report along
with groundwater modeling study carried out by Geoclimate Risk Solutions Pvt Ltd. (GCRS), Visakhapatnam in
respect of Groundwater NOC renewal vide Application no: 21-4/329/CT/MIN/2016 dated 15.01.2022 in respect of
Kusmunda OCP of SECL Kusmunda Area, please find enclosed a missing attachment of final groundwater
modeling report prepared by GCRS, Visakhapatnam in June 2022 for consideration of renewal of GW NOC for
SECL Kusmunda Area.
Thanking You,
Yours Sincerely,
https://mail.google.com/mail/u/0/?ik=f8cf182294&view=pt&sear…-a%3Ar7986913024320163985&simpl=msg-a%3Ar4570052706641024863 Page 1 of 2
Gmail - Submission of Final Impact Assessment report along with G…cast Coal Mining Project of M/s South Eastern Coalfields Limited. 15/12/22, 12:14 PM
https://mail.google.com/mail/u/0/?ik=f8cf182294&view=pt&sear…-a%3Ar7986913024320163985&simpl=msg-a%3Ar4570052706641024863 Page 2 of 2
Gmail - Regarding submission of Affidavit for IAR/CHR/ Modelling Report 15/12/22, 12:15 PM
Sir,
With reference to the aforesaid subject, you are requested to submit the Affidavit (attached
with the mail) in the prescribed format within 3 days for further processing of NOC
Application.
Regards
Office of Member CGWA, New Delhi
Central Ground Water Authority, 18/11, Jamnagar House, Mansingh Road, New Delhi-110011
Ph- (011) 23383561, 23383824; Fax- (011) 23382051; e-mail: cgwa@nic.in, rdcgwa-cgwb@nic.in
Subject:Submission of Affidavit With respect to ground water NOC renewal of Kusmunda OCP of Kusmunda Area.
Respected Sir,
With respect to ground water NOC renewal vide Application no: 21-4/329/CT/MIN/2016 dated 15.01.2022 for
Kusmunda OCP, please find the enclosed documents which are being submitted to your kind office. Final
Comprehensive report on “Impact assessment report along with ground water modeling study in respect of
Kusmunda OCP" has been submitted to your kind office vide no.926 on 25.05.2022.
https://mail.google.com/mail/u/0/?ik=f8cf182294&view=pt&searc…g-f%3A1735880619185338131&simpl=msg-a%3Ar2506994284936190041 Page 1 of 2
Gmail - Regarding submission of Affidavit for IAR/CHR/ Modelling Report 15/12/22, 12:15 PM
2 attachments
Joining and Charge assumption report of Sub Area Manager KOCP.pdf
838K
Affidavit w.r.t ground water renwal NOC KOCP.pdf
1092K
https://mail.google.com/mail/u/0/?ik=f8cf182294&view=pt&searc…g-f%3A1735880619185338131&simpl=msg-a%3Ar2506994284936190041 Page 2 of 2
Environment Department SECL Kusmunda <envtksm@gmail.com>
Sir,
Produce the following documents within 2 days as per the new guideline notified on 24.09.2020.
While scrutiny of your application the following additional information or attachment for further process.
1.) Youare herewith being advised to submit the checklist and salient feature(duly signed) of the
submitted IAR
2) You are advised to submit an affidavit on the undertaking as per the format attached (Annexure B-
on 100 Rs.- stamp)
-------------------------------------------------
Regional Director
Central Ground Water Board
North Central Chhattisgarh Region
2nd Floor, LK Corporates Tower
Dhamtari Road, Dumartarai
Raipur - 492 015
Email: rdnccr-cgwb@nic.in
2 attachments
Annexure B.docx
16K
Check List and Salient Features.docx
19K
Gmail - Additional information clarification regarding NOCAP… 21-4/329/CT/MIN/2016- M/S KUSMUNDA OPENCAST MINING PROJECT 15/12/22, 12:15 PM
Respected Sir,
Please find enclosed herewith the following documents requested from your kind office via e-mail dated
10.06.2022. Final hydrogeological report and Groundwater modelling report have also been enclosed for your kind
reference.
Regards,
5 attachments
check list.pdf
471K
Salient features.pdf
534K
Final Groundwater modeling report_Kusmunda.pdf
3039K
Comprehensive Hydrogeological report of Kusmunda OCP.pdf
15857K
Affidavit w.r.t ground water renwal NOC KOCP.pdf
1092K
https://mail.google.com/mail/u/0/?ik=f8cf182294&view=pt&searc…d-a%3Ar4415420764310572511&simpl=msg-a%3Ar4417073251822223935 Page 1 of 1
Comprehensive Hydrogeological Report along with
Modelling study
on
Ground Water Conditions in Core and Buffer Zones
for
Kusmunda Opencast Mining Project
of
South Eastern Coalfields Limited
Prepared By
Geo Climate Risk Solutions Pvt Ltd
Accredited by CGWA and ISO 9001:2015 Certified Company
APIS, Sunrise Incubation Tower, Hill No.3, Madhurawada, Visakhapatnam, 530048.
Website: www.gcrs.co.in
Email: business@gcrs.co.in
JUNE 2022
Comprehensive Hydrogeological Report for Kusmunda Opencast Mining Project of SECL
Contents
EXECUTIVE SUMMARY ....................................................................................................... 6
1 SALIENT FEATURES OF THE PROPOSAL ................................................................. 7
2 ABOUT THE PROJECT ................................................................................................... 8
2.1 LANDUSE / LAND COVER OF THE SURROUNDING AREA........................... 13
2.2 DEM / TOPOGRAPHY ............................................................................................ 19
2.3 GEOMORPHOLOGY AND DRAINAGE ............................................................... 21
2.4 DETAILS OF WETLANDS / MAJOR WATER BODIES ...................................... 24
3 HYDROGEOLOGY ........................................................................................................ 27
3.1 GEOLOGICAL SET UP ........................................................................................... 27
3.2 GEOPHYSICAL STUDIES ...................................................................................... 30
3.3 HYDROGEOLOGICAL SET UP ............................................................................. 33
3.3.1 Aquifer Characteristics ...................................................................................... 39
3.3.2 Ground water flow and aquifer interaction with surface water bodies .............. 45
3.3.3 Depth to Water Level ......................................................................................... 45
3.3.4 Long term water level data analysis................................................................... 54
3.3.5 Ground water quality ......................................................................................... 58
3.3.6 Water quality of nearby water bodies ................................................................ 64
4 APPROVED MINE PLAN .............................................................................................. 65
5 ESTIMATION OF MINE SEEPAGE AND ADVANCED DEWATERING PLAN ..... 73
5.1 ESTIMATION OF MINE SEEPAGE....................................................................... 73
5.2 ADVANCED DEWATERING PLAN ..................................................................... 75
5.3 GROUNDWATER MODELLING ........................................................................... 75
6 MINE WATER MANAGEMENT .................................................................................. 76
7 IMPACT OF MINE DEWATERING / ABSTRACTION AND MITIGATION
MEASURES ............................................................................................................................ 77
7.1 IMPACT ON THE GROUNDWATER REGIME.................................................... 77
7.2 IMPACT ON SURFACE WATER SOURCES ........................................................ 77
7.3 IMPACT ON WATER QUALITY ........................................................................... 78
7.4 MITIGATION MEASURES..................................................................................... 78
7.5 SALINE WATER DISPOSAL STRATEGIES ........................................................ 79
8 OTHER DETAILS PERTAINING TO THE PROJECT................................................. 80
9 SUMMARY AND CONCLUSION ................................................................................ 87
10 ACCREDITATION CERTIFICATE............................................................................... 89
Prepared by Geo Climate Risk Solutions Pvt Ltd, an accredited agency by CGWA Page | 2
Comprehensive Hydrogeological Report for Kusmunda Opencast Mining Project of SECL
List of Figures
Figure 2.1: Location map of the mine lease area. .................................................................... 10
Figure 2.2: Toposheet map of the study area. .......................................................................... 11
Figure 2.3: Google earth image of the study area. ................................................................... 12
Figure 2.4: Land use map of the study area (Pre-monsoon 2016-2019). ................................. 14
Figure 2.5: Land use map of the study area (post-monsoon 2016-2019). ............................... 15
Figure 2.6: LULC map of Pre-monsoon (2020). ..................................................................... 16
Figure 2.7: LULC map of Post-monsoon (2020). .................................................................... 17
Figure 2.8: Graphical representation of LULC for post-monsoon (2016-2020). .................... 18
Figure 2.9: Topography map of the study area. ....................................................................... 20
Figure 2.10: Geomorphology map of the study area. .............................................................. 22
Figure 2.11: Drainage map of the study area ........................................................................... 23
Figure 2.12: Map showing Ramsar Wetland Sites of India. .................................................... 25
Figure 2.13: Nearest Ramsar Wetland site to the Project area. ............................................... 26
Figure 3.1: Geology map of the study area .............................................................................. 29
Figure 3.2: Lateral variation of true resistivity on profile P1. ................................................. 31
Figure 3.3: Lateral variation of true resistivity on profile P2. ................................................. 32
Figure 3.4: Lateral variation of true resistivity on profile P3. ................................................. 32
Figure 3.5: Distribution of Monitoring Network. .................................................................... 36
Figure 3.6: Hydrogeology map of the study area (Pre-Monsson). .......................................... 37
Figure 3.7: Hydrogeology map of the study area (Post-Monsson). ......................................... 38
Figure 3.8: Pumping test data analysis by Jacob’s straight-line method of the pumping data of
the Pumping well Kusmunda. .................................................................................................. 41
Figure 3.9: Recovery data of the Pumping well Kusmunda. ................................................... 41
Figure 3.10: Pumping test data analysis by Jacob’s straight-line method of the pumping data of
the Pumping well Gevra........................................................................................................... 44
Figure 3.11: Recovery data of the Pumping well Gevra. ......................................................... 44
Figure 3.12: Pre-monsoon (May, 2021) Depth to Water Level Map....................................... 49
Figure 3.13: Post-monsoon (Nov, 2021) Depth to Water Level Map. .................................... 50
Figure 3.14: Water level fluctuation Map (May/June 2020 vs Nov. 2020). ............................ 51
Figure 3.15: Pre-monsoon water level trend (May 2018-May 2020 Vs May 2021). .............. 55
Figure 3.16: Post-monsoon water level trend (Nov 2018-Nov 2020 Vs Nov 2021). .............. 56
Figure 3.17: Hydrographs ........................................................................................................ 57
Figure 3.18: EC Contour Map. ................................................................................................ 60
Figure 3.19: Chloride Contour Map......................................................................................... 61
Prepared by Geo Climate Risk Solutions Pvt Ltd, an accredited agency by CGWA Page | 3
Comprehensive Hydrogeological Report for Kusmunda Opencast Mining Project of SECL
Prepared by Geo Climate Risk Solutions Pvt Ltd, an accredited agency by CGWA Page | 4
Comprehensive Hydrogeological Report for Kusmunda Opencast Mining Project of SECL
List of Tables
Table 2.1: Silent Features. ......................................................................................................... 8
Table 2.2: District wise and block-wise area coverage in buffer zone. ..................................... 9
Table 2.3: Land Use Pattern of the study area. ........................................................................ 13
Table 2.4: Existing Land Use Pattern of the mine lease area. ................................................. 18
Table 3.1: The stratigraphic succession of the region.............................................................. 27
Table 3.2: Details of the profiles along with coordinates. ....................................................... 30
Table 3.3: Positions of probable aquifer zones on the profile lines. ........................................ 33
Table 3.4: Details of Hydrological units. ................................................................................. 34
Table 3.5: Basic details of established monitoring wells in the study area. ............................ 35
Table 3.6: Pumping test data Kusmunda ................................................................................. 39
Table 3.7: Result of Pumping Test. ......................................................................................... 41
Table 3.9: Pumping test data. ................................................................................................... 42
Table 3.7: Result of Pumping test. ........................................................................................... 44
Table 3.10: Depth to water levels in different periods in the study area. ............................... 46
Table 3.11: Comparisons of water levels (2018-20) with reference to water levels of the year
2021.......................................................................................................................................... 52
Table 3.12: Water quality details of the wells. ....................................................................... 59
Table 3.13: Water quality of surface water bodies. ................................................................ 64
Table 5.1: Estimated Mine seepage ........................................................................................ 74
Table 5.2: Year wise estimated mine seepage ........................................................................ 74
Table 6.1: Usage of pumped water. ........................................................................................ 76
Table 8.1: Runoff Coefficients of common types of roofs. .................................................... 80
Table 8.2: Computation of groundwater recharge by RTRWHS. .......................................... 81
Table 8.3: Details of sumps and recharge from the same in the study area. ........................... 82
Table 8.4: Details of the Rainwater Harvesting Structures (Recharge Ponds) constructed in the
region. ...................................................................................................................................... 83
Table 8.5: Details of ETP/STP generation. ............................................................................. 84
Prepared by Geo Climate Risk Solutions Pvt Ltd, an accredited agency by CGWA Page | 5
Comprehensive Hydrogeological Report for Kusmunda Opencast Mining Project of SECL
EXECUTIVE SUMMARY
All new/existing industries, industries seeking expansion, infrastructure projects and mining
projects abstracting ground water, unless specifically exempted under Para 1.0 of THE
GAZETTE OF INDIA: EXTRAORDINARY notification dated 24.09.2020, will be required
to seek No Objection Certificate from Central Ground Water Authority or, the concerned State/
UT Ground Water Authority as the case may be. The entire process of grant of No Objection
Certificate shall be online through a web-based application system. Water management plans
shall be prepared by all the State Ground Water Authorities/ Organizations for all Over-
exploited, Critical and Semi-critical assessment units starting with Over-exploited units. Water
management plans shall be reviewed and updated periodically. Water management plans, data
on water availability and scarcity and policy framed in this regard shall be placed on the
websites of Central Ground Water Authority/ State Ground Water Authority.
Kusmunda opencast mining project has total lease area of 1603 ha located in Barkuta and
Kusmunda village, Katghora block, Korba District, Chhattisgarh. The study area falls in safe
category of Groundwater resource categorization. The stage of development for the Katghora
block is 68.76 %. About 277 m3/day of water is abstracted from borewells for domestic and
drinking purposes and 13438 m3/day of water from mine pits (mine seepage), with a total
groundwater withdrawal of 13715 m3/day during the five years. The permission to dewater
groundwater for the mining industry was approved by CGWA with application no. 21-
4/329/CT/MIN/2016 and NOC letter no. CGWA/NOC/MIN/ORIG/2017/2416 dated
28/02/2017, The first renewal for the NOC is valid from 9/01/2019 to 18/01/2022. This
comprehensive report for groundwater conditions is prepared for the 2nd renewal of the NOC
mentioned above.
Prepared by Geo Climate Risk Solutions Pvt Ltd, an accredited agency by CGWA Page | 6
Comprehensive Hydrogeological Report for Kusmunda Opencast Mining Project of SECL
Prepared by Geo Climate Risk Solutions Pvt Ltd, an accredited agency by CGWA Page | 7
Comprehensive Hydrogeological Report for Kusmunda Opencast Mining Project of SECL
The Kusmunda Opencast Expansion project was sanctioned for a targeted coal production
of 15 Mty. Presently, it has reached the production level of 15 Mty. The further expansion of
this project has been planned to a targeted capacity of 50 Mty. The additional production has
been linked to various Thermal Power Stations. As such, there will not be any problem to
market the coal from this project. The proposed project is of 50 MTPA (normative) & 62.5
(peak). Coal winning is being done by surface miner & Payloader-tipper combination
&Removal of OB is carried out by shovel-dumper combination. The project currently has
production capacity of 18.75 MTPA. Additional land of 1127.588 Ha is required for proposed
expansion. Total land – 3510.348 Ha. M/s Kusmunda Opencast Coal mining project has total
lease area of 1603 ha located in Barkuta and Kusmunda village, Katghora block, Korba District,
Chhattisgarh. The study area falls in safe category of Groundwater resource categorization
According to the LULC maps prepared from 2016 to 2020, the predominant land use
in the study area is agriculture land, which is occupying 47% (2020) of the study area. Followed
by 38% of Forest land, 6.6 % of Barren land, Built-up of 3.7 %, and water body 3.5 %. The
forest cover area has increased over the period of 2016-2020.
The general topography is flat terrain with minor undulations. The general elevation
ranging from 290 to 320 mamsl. The elevation of the study area varies from 195 to 372 mamsl.
The drainage is by southerly flowing Hasdeo River which lies to the east of the block. Hasdeo
River, a major tributary of Mahanadi River flowing along the eastern side in a north-south
direction, is the master drainage of the area. The Project area is traversed by a small first order
tributary of Gangdel nalla in the South-West. This nalla also flows Southerly and drains into
Hasdeo River. The other nallas, which drain the buffer zone, are Lachhminta, Kholar nalla,
Ahran Nadi, Dhengu nalla and Dom nalla etc. The drainage is mostly dendritic in nature. The
HFL of Hasdeo River, close to the Kusmunda OCP in east was recorded as 295 m in upstream
and 282m in downstream.
The nearest Ramsar site to the project area is Samaspur Bird Sanctuary in Uttar Pradesh
situated at an aerial distance of about 412.88 Km from the site in the NNW direction. So, the
Certificate regarding the same is not applicable for the particular proposal as there is no wetland
in the vicinity of 500 m from the lease area.
Prepared by Geo Climate Risk Solutions Pvt Ltd, an accredited agency by CGWA Page | 87
Comprehensive Hydrogeological Report for Kusmunda Opencast Mining Project of SECL
The major part of the area is occupied by the rocks of Gondwana of Super Group are
overlying the Chhattisgarh Super group and represented by the sandstone, shale and coal seam.
It is estimated that over 1400 m of sedimentaries are preserved in the Korba Coalfield. Korba
Coalfield also occupies a tectonic trough with faulted boundaries. The southern boundary of
this basin is defined by a major E-W (at places NW-SE) trending lineament traced over a
distance of about 150km from Korba to Sambalpur in the vicinity of Talchir coalfield. This
alignment more or less forms the southern limit of Mahanadi Graben. Apart from the boundary
faults, another important lineament running E-W is along the northern boundary of the Dipka,
Gevra and Kusmunda projects which is responsible for the preservation of the thick seams
towards the down throw side of the fault in the south.
To determine the groundwater level condition, total 44 wells are taken into
consideration, 34 wells are present in the core zone and 10 wells falls inside the buffer zone of
the site boundary. The water level depth varies from 4-14.53 m bgl for pre-monsoon season
May,2021. The maximum water level depth in core zone is 14.53 m bgl, while that is case of
buffer zone reaches upto 10.3 mbgl. The water level depth varies from 1-10 m bgl for post-
monsoon season, Nov 2021. The maximum water level depth in core zone is 13.6 m bgl, while
that is case of buffer zone reaches upto 5.6 mbgl. The water level depth in case of post monsoon
season is shallower as compared to the pre-monsoon season, it can be due to high amount of
rainfall in that year.The seasonal water level fluctuation for the year 2021 shows the variation
in water level of pre-monsoon (May) and post-monsoon (November). The water level
fluctuates from -0.6 to 10 m bgl. There is huge fluctuation in seasonal water level which can
be due to high amount of rainfall during the monsoon period of the year 2021 resulting in more
groundwater recharge.
The estimated quantity of mine seepage will be 13438 m3/day during the 5-year period.
The total groundwater abstraction through the borewells (2) will be about 277 m3/day. This
water will be used for different mining activities (both industrial and domestic & drinking). As
per the criteria for categorization of area made by Central Ground Water Authority for the
development point of view (GWRA, 2020) the present study area falls under ‘Safe Category’.
Enough scope exists for withdrawal of required amount (13715 m3/ day) of ground water. It
will not have any appreciable impact on ground water resources in the area.
Prepared by Geo Climate Risk Solutions Pvt Ltd, an accredited agency by CGWA Page | 88
Comprehensive Hydrogeological Report for Kusmunda Opencast Mining Project of SECL
10 ACCREDITATION CERTIFICATE
Prepared by Geo Climate Risk Solutions Pvt Ltd, an accredited agency by CGWA Page | 89
Comprehensive Hydrogeological Report for Kusmunda Opencast Mining Project of SECL
Prepared by Geo Climate Risk Solutions Pvt Ltd, an accredited agency by CGWA Page | 90
Groundwater Modelling Report
for
Kusmunda Opencast Coal Mining Project
of
Prepared By
June 2022
Groundwater Modelling Report
Kusmunda Opencast Coal Mining Project of SECL
based on the rainwater harvesting structures available in the study area. The evapotranspiration
value has been set based on the hydrogeological and surface topographic condition
(https://indiawris.gov.in/wris/#/).
The RMS values and the other results obtained from the simulated model have been discussed
in this section. Also, the correlation between the observed and calculated hydraulic head has
been discussed. A significantly good correlation has been observed between the observed and
calculated hydraulic head.
• Under transient state conditions, the groundwater flow model has been run until December
2031. The model predicts groundwater head changes for the present and future scenarios
from 2022 to 2031.
• The maximum water abstraction rate of 13715 m3/day from 2 existing bore wells (277
m3/day) and dewatering/mining seepage (13438 m3/day) for a year has been taken based
on the total water requirement throughout the model run period.
• The hydraulic head contours have been prepared based on the numerical model from 2014
to 2031.
• The hydraulic head contours of the numerical model from 2014 to 2031 have been
estimated during the present study. Figures 5 to 8 show the groundwater head (m asl) for
2015, 2022, 2026, and 2031. The hydraulic head varies from 260 to 357 m asl during
August 2014, and 259 to 352 m asl during January 2021.This indicates very few changes
in groundwater level during the model period, and the maximum drawdown is 2.5 m in
and around the study area during the prediction period (2031).
• The groundwater observation wells and piezometers records have calibrated and validated
the model. The observed and calculated hydraulic head significantly correlated during the
study period. The Root Mean Squared Error is 3.47 m.
The groundwater investigation has been carried out in and around the model area; 2 existing
bore wells and two dewatering locations are recommended to abstract water (13715 m3/day).
• The recommended well must be pumped for the recommended number of hours/ per day
with recommended discharge only.
Prepared by Geo Climate Risk Solutions Pvt Ltd, an accredited agency by CGWA 27
Groundwater Modelling Report
Kusmunda Opencast Coal Mining Project of SECL
Prepared by Geo Climate Risk Solutions Pvt Ltd, an accredited agency by CGWA 28
ANNEXURE-8
Backfilling & technical/biological reclamation is in progress. Out of the earmarked area of 325
Ha for External OB Dumps, only 196.242 Ha has been used for 13 nos. of external OB Dumps.
Out of these External OB Dumps, 7 have been fully or partially re-handled due to upcoming
Infrastructure for Kusmunda Phase-II Expansion project & 6 are old & stabilized with
plantation. No more External dumps will be created in future.
At present, only Backfilling of Internal Dump is being practiced and as on 30.09.2022, total
510.610 Ha area has been backfilled and out of which 203.00 Ha area has been biologically
reclaimed through plantation.
Restoration and reclamation plan is done as per Progressive Mine Closure Plan of
Kusmunda OCP 50.00 MTPA which is given below (year-wise programme):
DUMP Area
DUMP
DUMPING available for
PLAN Plantation
YEAR ACTUAL reclamation Total Area Reclaimed (Ha)
(M cum) (in Nos.)
(M cum) (ha)
(As per PR)
(Proposed)
Technically
Biologically Reclaimed
Reclaimed As Per
Ext. Int. Ext. Int. Ext. Int. (Ha) Achieved
(Ha) PR
Ext. Int. Total Ext. Int. Total
196.242 164.96 361.202 136.43 73.00 209.43
KUSMUNDA OPENCAST EXPANSION PROJECT 1535394
(till (till (till (till (till (till
(till 2012-
(15-50 MTY) WAS CONCEIVED IN 2013-14 2012- 2012- 2012- 2012- 2012- 2012-
13)
13) 13) 13) 13) 13) 13)
2013-14
(1st 10.00 10.73 0.00 24.068 130 8.08 0.00 1.15 1.15 0.00 12.00 12.00 120282 55000
YEAR)
2014-15 10.00 10.73 0.00 18.647 130 8.08 0.00 32.77 32.77 23.00 0.00 23.00 137529 125000
2015-16 0.00 20.73 0.00 29.252 32.50 15.61 0.00 15.80 15.80 20.00 0.00 20.00 345203 140000
2016-17 0.00 29.89 0.00 35.965 32.50 22.51 0.00 29.20 29.20 16.812 40.00 56.812 345203 140000
2017-18 0.00 40.56 0.00 37.598 0.00 30.55 0.00 60.40 60.40 0.00 40.00 40.00 76369 106855
2018-19 0.00 40.46 0.00 44.071 0.00 30.47 0.00 38.50 38.50 0.00 30.00 30.00 76181 126000
2019-20 0.00 50.24 0.00 32.201 0.00 37.84 0.00 33.50 33.50 0.00 08.00 08.00 94595 70000
2020-21 0.00 66.71 0.00 33.960 0.00 50.24 0.00 40.70 40.70 0.00 00.00 00.00 125606 50000
2021-22 0.00 66.88 0.00 37.624 0.00 50.37 0.00 70.18 70.18 0.00 0.000 00.00 125926 53000
2022-23 0.00 66.97 0.00 22.890 0.00 50.44 0.00 23.45 23.45 0.00 0.000 0.000 126096 50000
ANNEXURE-8
Afforestation is carried out through Chhattisgarh Rajya Van Vikas Nigam & year-
wise plantation details of Kusmunda OCP is as follows:
Safety Zone of 75m thickness has been developed in Northern & Eastern Boundary of
the Kusmunda Project in FY 2020-21. Kusmunda Mine is currently proceeding in Southern &
Western direction. Land has already been acquired by Kusmunda Project for an area of 752.456
ha after Section 9(i) dated 28.03.2010 & for an area of 1050.593 ha after Section 9 (i) dated
18.07.2018 in Southern & Western Directions under Coal Bearing Areas (land & Acquisition)
Act, 1957. Some Photographs of safety zone are shown below:
The detailed action plan for the development of the green belt around mine lease area and the
details of the species proposed to be planted are given below:-
1. Green belt barrier for a width of (75-100 m) will be provided all around the periphery of
the mine in safety zone area.
2. Three tier plantations will be done with native species (neem, semal, palash, amaltas,
gulrnohar, etc.).
3. Provision of Rs 2.00 crores has been made in the PR.
4. Recommendations of ICFRE audit team in their Final Environmental Compliance
Report, September 2018 will be followed as guidelines for plantation of native species.
ANNEXURE-8
For the time being for compliance of EC Conditions, Mine management had taken an
exercise with local villagers/ representatives & had planted a total of 6,855 Nos. of saplings of fruit-
bearing in nature in FY 2017-18 in a Govt. Land of 2.742 Ha at Bata village (a village selected
outside the final mine lease boundary of Kusmunda Project in the downwind direction for
mitigating the effects of dust pollution in the surrounding villages). A total of 9000 cum (approx.) of
top soil was also used for this purpose. These trees will take a mature shape when the mine reaches
that boundary in future. Photographs are shown below:
5. INFRASTRUCTURE DEVELOPMENT
' ~~o/
1 Condition: - The Project Authority shall adopt best mining practices for the given mining
conditions. In the mining area, adequate number check dams, retaining wall/structures,
garland drains and settling ponds should be provided to arrest the wash- off with rain water
in catchment area.
Compliance: -Being complied by PP.
Kusmunda OCP practices one of the best mining methods available by using Surface miner
and 42Cum. Shovel-240T Dumper combination for coal and OB excavation. All the upcoming
machineries, infrastructures are being equipped with new state of the art technology to encourage
Green mining. Adequate number of check dams and garland drains are appropriately constructed all
along the periphery of the quarry for channeling of run- off water during rainy season. Kuccha/
garland drain of average dimension 3500m x 4.0m x 2.5m (as shown below) has been constructed
all along the periphery of the mine for channeling of run-off water during rainy season. The drains
are periodically de-silted before Monsoon every year. Copy of some work orders are attached as
Annexure-32.
External dumps around the river periphery have been completely stabilized with dense
plantation & have been provided with check dams, retaining walls etc. to avoid the flow of silt into the
rivers. Sump capacity and pumping capacity for dewatering of quarry area are planned properly for
monsoon as well as lean period so as to provide adequate retention period to allow proper settling of silt
material. Copy of Monsoon Action Plan for FY 2022-23 is enclosed as Annexure-33. Mine water is
stored in the mine sumps and the settled water after sedimentation is used for industrial demand like
dust suppression, HEMM washing, plantation and in CHP. The excess treated water available after
mine usage is discharged into the main water stream/nallah.
SUMPS INSTALLED WITH PUMPS FOR DEWATERING FROM THE MINE PIT
KUSMUNDA OCP
Kuccha/ garland drain of average dimension 2.5m x 300m x 2m and 600m x 1.5m x 1.5m (as
shown below) have been constructed on both sides of Coal stock yard to channel run-off water and
prevent ground water contamination from coal fines. This mine water is directed to settling tank and
used in water sprinkling.
A RCC retaining wall of dimensions 590Mx0.375Mx4.5M constructed at a cost of Rs. 1.09 Crore
exists at toe of old dump parallel to the railway track. New retaining walls have been constructed alongside
toe of dump slopes having TRS section of the new 20,000 Te bunker & near partially re-handled external OB
dumps to avoid soil erosion. Work has been awarded for construction of gabion walls at various locations of
mine on 07.09.2022. Photograph of retaining wall are as follows-
Various Check Dams/ Stop Dams have been constructed to arrest the flow of Rain Water in nearby
Nallahs/ surface water bodies like Laxman Nallah etc.
2 Condition: - The natural water bodies and or streams which are flowing in and around the
village should not be disturbed. The water table should be nurtured so as not to go down
below the pre-mining period, in case of any water scarcity in the area.
Compliance: Being complied by PP.
No major drainage is being altered or impacted by mining at Kusmunda OCP. Mining is being
carried at a considerable distance from the Hasdeo/Ahiran rivers & Laxman nallah which are major
channels around the mine. External dumps around the river periphery have been completely
stabilized with dense plantation & have been provided with check dams, retaining walls etc. to avoid
the flow of silt into the rivers.
Chhattisgarh Council of Science & Technology (CCOST), Raipur has carried out a work on
“Comprehensive Catchment Treatment Plan in the area to arrest flow of silt in the Hasdeo River &
to improve water regime in respect of Kusmunda Expansion OC Project”. Its report is enclosed as
Annexure- 25.
Regular ground water level is being monitored through existing wells in nearby villages and 4
sets/ 11 Nos. of Piezometers located at GM Office (02), Sarvamangla Nagar (03), Padania (02)&
Amgaon (04). Piezometer readings for the year 2022 is enclosed as Annexure 45. Open Dug Well
Monitoring is being done at 28 locations on a quarterly basis (Readings enclosed as Annexure-47)
& the report for is enclosed as a part of Half Yearly Compliance and submitted to Regional Office of
the Ministry and State Pollution Control Board. A Report on six monthly basis on changes in
Ground water level and quality is submitted to the Regional Office of the Ministry, CGWA &
Member Secretary, CECB, Raipur on a half yearly basis.
Many artificial recharge measures have been taken to replenish the ground water table at
Kusmunda OCP. Only Mine water is used and re-used for mining activities like dust suppression of
haul roads, Washing of HEMMs, CHP, quenching and plantation activities. Groundwater to the tune
of 277 KLD through 2 Bore wells is being used for meeting the needs of domestic uses within
the mining area. Rain water harvesting system is being practiced to recharge the ground with rain
water at Kusmunda House (1 no.), CGM Office (1 no.), DAV School Kusmunda, Central School
Kusmunda (2 no.), Dispensaries of Vikas Nagar and Adarsh Nagar (1 no.) each and CAAQMS/
Environment Office, AHQ. Apart from the above, Rain Water Harvesting is also a part of all
upcoming infrastructure activities at Kusmunda Area thereby increasing the groundwater recharge
potential of the area.
The project authority also meets the requirement of the Drinking water in nearby villages by
supplying potable water through mobile tankers in the lean period. Various bore wells, ponds have
been constructed and regularly maintained under CSR head to avoid any water scarcity in the area.
3 Condition: - The illumination and sound at night at project sites disturb the villages in respect
of both human and animal population. Consequently, sleeping disorders and stress may affect
the health in the villages located close to mining operations. Habitations have a right for
darkness and minimal noise levels at night. The Project Proponents must ensure that the
biological clock of the villagers is not disturbed by orienting the floodlights/masks away from
the villagers and keeping the noise levels well within the prescribed limited for daylight hours.
Compliance: Being complied by PP.
The Lighting system of the mines is designed as per DGMS regulations with installation of
proper lamps and fixtures so as to secure a uniform distribution of light on the localized area only.
Sharp contrasts of intensity, glare, light clutter is highly avoided to prevent light pollution and
prevent strain in the work place as well as the surroundings. Lighting survey is carried out once in a
month to measure the adequacy of illumination (Annexure-14).
To control the Noise Pollution at Kusmunda Open Cast Mine, the following measures are adopted:
Stress on use blasting free technology of Surface Miner mining in coal mines.
Proper maintenance of equipment to minimize vibration;
Thick green belts developed around residential areas, along colony roads, coal transportation
road and around the mine infrastructure, also act as noise barrier.
All HEMMs are provided with noise proof cabins for operators. Extensive plantation done on
over burden dumps, which act as noise barrier between mines area and residential area.
Employees who are exposed to higher level of noise are provided with ear plugs.
Generally blasting operation is carried out between 1 pm to 3 pm with minimum no. of persons
within the mine premises.
Noise Monitoring report for the month of September, 2022 is enclosed in Annexure-15 which
clearly shows that the noise levels at Kusmunda area are well below 85 dB (A).
4 Condition: - The Project Proponent shall make necessary alternative arrangements, when and
where required, in consultation with the State Government to provide alternate areas for
livestock grazing. In this context Project Proponent should implement the directions of the
Hon’ble Supreme Court with regard to acquiring grazing land. The sparse trees on such
grazing ground, which provide midday shelter from the scorching sun should be scrupulously
guarded against felling, the cattle abandon the grazing ground or return home by noon.
Suitable Grazing Land will be provided for livestock grazing beyond the safety zone of the
mine leasehold area after necessary possession of the acquired land of Kusmunda Opencast
Expansion Project 50 MTY & development of safety zone area.
5 Condition: - Where ever blasting is undertaken as part of mining activity, the Project
Authority shall carry on vibration studies well before approaching any such habitants or other
buildings to evaluate the zone of influence and impact of blasting on the neighborhood. Within
500 meters of such sites vulnerable to blasting vibrations, avoidance of use of explosives and
adoption of alternative means of mineral extraction such as ripper/dozer combination/rock
breakers/ surface miners etc. should be seriously considered and practiced wherever
practicable. A provision for monitoring of each blast should be made so that the impact of
blasting on nearby habitation and dwelling units to be ascertained. The covenant of lease deed
under Rule 31 of MCR 1960 provides that no mining operations shall be carried out within
500 meters of public works such as public roads and buildings or inhabited sites except with
the prior permission from the Competent Authority.
Compliance: Being Complied by PP.
Mining at Kusmunda OCP is being carried out as per the approved mining plan(PR
approved by CIL Board on 03/08/2013 including Mine Closure Plan) & all mining laws related to
coal mining and the relevant circulars issued by Directorate General Mines Safety (DGMS) are
being abided by the project proponent.
Majority coal production of Kusmunda Open Cast Project is done by surface miner which
eliminates blasting in coal. However, at OB benches, blasting is done by controlled blasting
technique with delay detonators and blasting is carried out only during day time. Controlled
blasting is practiced as per rules and regulations stipulated by the DGMS and monitoring of the
ground vibration during blasting is done regularly. Some Vibration-cum-blast reports are enclosed
as Annexure-37.
6 Condition: - Main haulage road in the mine should be provided with permanent water
sprinklers and other roads should be regularly wetted with water sprinklers. Crusher and
material transfer points should be invariably provided with bag filters and or dry fogging
system. Belt-conveyors should be fully covered to avoid air borne dust.
Compliance: Being complied by PP
At Kusmunda OCP, Mitigative measures to control dust and fugitive emission such as mist
sprayers, perforated pipe systems, water guns & long range fogging machine are regularly
monitored, and changes are made as per requirements.
All Departmental Mobile water sprinklers (10 Nos: 70KL & 5 Nos: 28 KL capacity) for haul
roads are equipped with Mist Spray Sprinkling System. CHP Phase-I (20,000 Te Bunker & Truck
Receiving Station -1) and coal crushing units have been equipped with Mist and nozzle spray
arrangement to arrest fugitive emission. The nozzles are checked daily and repaired/cleaned on daily
basis if necessary. CHP Phase-II (4 no. of Silos & Truck Receiving Station -2) have also been
equipped with Mist and nozzle spray arrangement to arrest fugitive emission. The nozzles are
checked daily and repaired/cleaned on daily basis if necessary. CHP Phase-III – In-Pit Belt
Conveyors: Work has been awarded for Construction of In-pit belt conveyor at a cost of Rs. 544.59
Crores on 18.01.2021. Progress of work as on date is 34% & is likely to be completed by
31/12/2023.
Details of Water spraying arrangement provided at CHP, coal yard and haul road at Kusmunda open
cast project is given below-
COAL
FIXED SPRINKLING MOBILE WATER
CHP STOCK
ARRANGEMENT SPRINKLER
YARD
Departmental: In-built Mist spray
NO. OF LENGTH
70 KL: 10 nos. arrangements at Truck
POSTS (METER)
28 KL: 05 nos. receiving station and 16 Nos.
hopper points of newly Spray Guns
constructed 20,000 Te at Coal
Contractual:
40 2.5 Kms Bunker & CHP Phase-II Stock Yard
09 KL: 06 nos. for Project Silos with Rapid
Loading System
One No. of “Dust Suppression System with mist blower/fog forming long range water
sprinkler with horizontal throw of 40 mtrs (min) mounted on truck chassis of GVW-25T(min)” for
Kusmunda Area at a cost of Rs 47.69 Lakhs has been procured and commissioned from
19.07.2019. Supply order for one no. of additional Dust Suppression System with mist blower/fog
forming long range water sprinkler has been placed on 04.05.21. Delivery has been delayed by the
agency & it is expected to be procured and commissioned in FY 22-23.
A proposal for procurement of 15 nos. of fixed mist cannon/ fogging machines for coal stock
yards & railway sidings has been approved by the competent authority. Tender will soon be
floated.
All Fixed & Mobile Crushers are well equipped with Mist and nozzle spray arrangement at
unloading & transfer points to arrest fugitive emissions. All surface approach roads to CHP and
sidings are being converted from WBM to RCC & 60% of the work has been completed in FY
2022-23. A fund of Rs 40 lakhs has been earmarked for fixed sprinklers along the alignment of
this road in Capital Expenditure FY 2023-24.
7 Condition: - The Project Authority shall ensure that the productivity of agricultural crops is
not affected due to mining operations. Crop liability Insurance Policy has to be taken by the
PP as a precaution to compensate for any crop loss. The impact zone shall be 5 km from the
boundary of mine lease area for such insurance policy. In case, several mines are located in a
cluster, the Associations of owners of the cluster mines, formed inter alia to sub serve such an
objective shall take responsibility for securing such crop liability policy.
Chhattisgarh Council of Science & Technology (CCOST), Raipur has carried out a work on
“Comprehensive Catchment Treatment Plan in the area to arrest flow of silt in the Hasdeo River &
to improve water regime in respect of Kusmunda Expansion OC Project”. Its report is enclosed as
Annexure- 25. Its recommendations are being followed for improving water regime in the whole
catchment area.
8 Condition: - In case any village is located within the mining leasehold which is not likely to be
affected due to mining activities during the life of the mine, the Expert Appraisal committee
(EAC) should consider the proposal of Environment Clearance (EC) for reduced mining area.
The mining lease may be executed for the area for which EC is accorded. The mining plan may
also be accordingly revised and required stipulations under the MMDR Act, 1957 and MCR,
1960 met.
Compliance: Agreed.
There are 10 villages located within the present mine lease hold area. However, EC has been
granted for a reduced mining leasehold area & mining is presently being undertaken in reduced area.
Villages lying outside the EC boundary are being rehabilitated & resettled as per the approved R&R
Policy of Coal India Limited 2012 & Chhattisgarh Rajya Adarsh Punarvas Niti-2007 .
9 Condition: - Transportation of minerals by roads passing though the village shall not be
allowed. A bypass road should be constructed (say, leaving a gap of at least 200 meters) for the
purpose of transportation of the minerals so that the impact of sound, dust and accidents
could be mitigated. The PP shall bear the cost towards the widening and strengthening of
existing public road network in case the same is proposed to be used for the Project. No road
movement should be allowed on existing village road network without appropriately
increasingly the carrying capacity of such roads.
Compliance: Being Complied by PP.
The transportation of coal is being carried out as per the provisions and route proposed in the
approved Mining Plan. As the Mine is in an expansion stage, Final layout of the mine according to
the Project Report has not been achieved yet & existing road network is being utilized by Kusmunda
as well as its nearby mines.
Transportation of coal through village roads is mostly avoided & trucks are being plied on
roads / routes approved in consultation with the State Government.
Meanwhile, measures such as widening of existing roads, cementation of some roads, regular
water sprinkling on the public roads, dense plantation on road sides, sign hoardings etc. is being
practiced in consultation with the State govt. to minimize the impact of sound, dust & accidents. A
provision of Rs 63.55 Crores has been provided in the Project Report for Cement Concretization of
Colony, Service, Approach & other roads in & around the mine premises.
An amount of Rs. 199.20 crore has been sanctioned for construction of 02 nos. of CC roads for
easy movement of Coal carrying tippers as well as public transportation around 3 mega mines of
SECL. Work is under progress. Construction is likely to be completed by May, 2023.
Construction of approach road for connecting ROB with Gevra- Korba Road at Kusmunda
Project of Kusmunda (Ph-I) completed at a cost of Rs 4.15 crores for direct mine entry. This will
reduce the distance travelled by trucks & will be integrated with above four laning project of
public transportation CC road being carried out by PWD department.
Construction of WBM/bypass road at an estimated cost of Rs 1.94 crores (Length: 1.1 kms and
width is 7.0 kms) from Mangaon village to Naraibodh village to avoid road transportation
through Gevra Basti village. NOC has been obtained from Collector, Korba for diversion of
0.936 ha Revenue Forest Land. Estimate is under process of approval.
Thus, Alternative roads or bypass roads are being constructed in a phased manner like new
entry into the mine through ROB to avoid residential areas, four laning of roads to avoid
decongestion on roads, new bypass road to avoid densely populated villages etc with the finalization
of mine layout & infrastructure creation in Kusmunda OCP.
Apart from the above, Majority of coal at Kusmunda OCP is being transported through:
A new overhead state-of-the-art 20,000 Te Bunker & Truck Receiving Station (CHP Phase – I)
which has been commissioned from 08.02.2020. Annually 7.00 MT coal is transported through a
closed conveyor belt to nearby thermal power station.
Four nos. of new SILO’s with Rapid Loading System (4000 Te capacity each) along with New
Railway Siding (CHP Phase- II) has been commissioned from 24.08.2021.
In addition to this, Connectivity of New Railway Siding to East-West Rail Corridor Project (Rs.
27 crores)is in progress. 13% of the work has been completed up to 30.09.2022. This will
facilitate faster integration & movement of coal across the country.
Minimal coal capacity is transported through trucks. These trucks are optimally loaded and
covered with tarpaulin before leaving the premises.
10 Condition: - Likewise, alteration or re-routing of footpaths, pagdandies, cart roads and village
infrastructure/public utilities or roads (for purposes of land acquisition for mining) shall be
avoided to the extent possible and in case such acquisition is inevitable, alternative
arrangements shall be made first and then only the area acquired. In these types of cases,
inspection reports by site visit by experts may be insisted upon which should be done through
reputed institutes.
Compliance: Being Complied by PP.
Mining is a site-specific activity. So, Alternate arrangements like Construction of toads and
culverts, schools, medical facilities, health camps, markets providing basic facilities like toilets,
drinking water, and hand pumps are being constructed under CSR head and R&R schemes. ·
11. Condition: - As CSR activities including the mining Establishment bas become n,andatory
up to 2% of the financial turn over, Socio Economic Development of the neighborhood
habitants could also be planned and executed by the PPs more systematically based on tl!e
'N eed based door to door survey' by established Social Institutes/Workers on the lines
as required under TOR. "R&R plan/ compensation details for the Project Affected people·
(PAP) should be furnished. While preparing the R&R plan, the relevant State/N ational
Rehabilitation & Resettlement policy should be kept h• the view. In respect of SC/STs and
other weaker sections of the society in the study area, a need based sample survey sample
survey, family-wise should be undertaken to assess the requirements and action programmes
prepared and sµbmitted accordingly, ~ntegrating the sectoral programmes of the line
departments of the State Government. It may be clearly brought out whether the village
located in the mine lease area will be shifted or not. The issues relating to shifting of villages
include their R&R and socio- economic should be discussed in the EIA report.
Compliance: Being Complied by PP.
CIL has modified & made one of the best & well-defined CSR Policy which was framed after
incorporating the fea~res of the Companies Act 2013 and as per notification issued by Ministry of
Corporate Affairs, Govt. of India on 27.02.2014 as well as DPEs guidelines. Expenses of CSR/CD
work taken up by Kusrtmnda Area for past 10 years is enclosed as Annexure-41. CSR Expenditure for
FY 2022-23 (Apr-Sep) is Rs 1.75 Lakhs. R&R programmes are being followed as mentioned and
discussed in Chapter no. IV and VII of EWEMP report prepared by CMPDIL, which is a QCI
NABET accredited consultant organization for preparation of Environmental Impact Assessment
(EIA) reports.
I,_;,
,:_d ~t ;:II~-~,.,· .. ,;,
',;,
I \,
'!
., .
.f.~ ,' ,.t
,I
... \
l•'t-' .... i~'!".~;.
ti._,
COPYRIGHT WITH
CMPDI
A MINI RATNA
ISO 9001 COMPANY
(KUSMUNDA AREA)
SEPTEMBER - 2022
CONTENTS No. of
Page No.
samples
Sl.No. Name of Air Sampling Station
1 Vikas Nagar 8 1
3 Sarvamangla Nagar 8 2
5 Churail Village 8 3
6 Khairbhawna Village 8 3
7 Padania Village 8 4
Total 72
No. of
Sl.No. Name of Noise Sampling Station Page No.
samples
1 Vikas Nagar 2 6
3 Sarvamangla Nagar 2 6
4 Env.Lab.Kusmunda 2 6
5 Vaishali Nagar 2 6
6 Jatraj Village 2 6
7 Pali Village 2 6
Total 18
No. of
Sl.No. Name of Effluent Sampling Station Page No.
samples
Total 12
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Page 1 of 22
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of Issue 15.10.2022
Name of the Project Kusmunda OC Sample Reference No. 5-6
Parameter PM100 PM10 PM2.5 SO2 NO2
Industrial Zone -(G.S.R. 742(E), A-O 600 300 - 120 120
µg/m3)-24
Limit (in
24.09.2022 27.09.2022
166 70 34 41 34
27.09.2022 07.10.2022 165 67 33 40 28
Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of Issue 15.10.2022
Name of the Project Kusmunda OC Sample Reference No. 7-8
Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of Issue 15.10.2022
Name of the Project Kusmunda OC Sample Reference No. 9
Parameter PM100 PM10 PM2.5 SO2 NO2
Industrial Zone -(G.S.R. 742(E), A-O 600 300 - 120 120
µg/m3)-24
Limit (in
Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of Issue 15.10.2022
Name of the Project Kusmunda OC Sample Reference No. N22-N30
Station Date of
Station (Code) Station Name Value in dB(A) Value in dB(A)
category measurement
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 7 of 22
TEST & SAMPLING REPORT OF (EFFLUENT WATER FORTNIGHTLY )
Unique Report No. TC-74012212416 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Indra Date of 17-09-2022 Sample ID 12765
Sampling
Sampling Mine water at discharge point Sampling Plan Fortnightly Sampling CMPDI/BSP/LSOP
Location Kusmunda (WBP) Method
Sample APPROPRIATE Date of Receipt 19-09-2022 Date of Analysis From 24-09-2022 To 28-09-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 8 of 22
TEST & SAMPLING REPORT OF (EFFLUENT WATER FORTNIGHTLY )
Unique Report No. TC-74012210254 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Ratan Gope Date of 03-09-2022 Sample ID 12559
Sampling
Sampling Upstream of Hasdeo river near Sampling Plan As Per Monthly Sampling CMPDI/BSP/LSOP
Location railway bridge Kusmunda (WBP) Plan Method
Sample APPROPRIATE Date of Receipt 06-09-2022 Date of Analysis From 06-09-2022 To 25-09-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 9 of 22
TEST & SAMPLING REPORT OF (EFFLUENT WATER FORTNIGHTLY )
Unique Report No. TC-74012212420 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Indra Date of 17-09-2022 Sample ID 12766
Sampling
Sampling Upstream of Hasdeo river near Sampling Plan Fortnightly Sampling CMPDI/BSP/LSOP
Location railway bridge Kusmunda (WBP) Method
Sample APPROPRIATE Date of Receipt 19-09-2022 Date of Analysis From 24-09-2022 To 28-09-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 10 of 22
TEST & SAMPLING REPORT OF (EFFLUENT WATER FORTNIGHTLY )
Unique Report No. TC-74012210242 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Ratan Gope Date of 03-09-2022 Sample ID 12556
Sampling
Sampling Downstream of Hasdeo river after Sampling Plan As Per Monthly Sampling CMPDI/BSP/LSOP
Location joining mine discharge Kusmunda Plan Method
(WBP)
Sample APPROPRIATE Date of Receipt 06-09-2022 Date of Analysis From 06-09-2022 To 25-09-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 11 of 22
TEST & SAMPLING REPORT OF (EFFLUENT WATER FORTNIGHTLY )
Unique Report No. TC-74012212408 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By A Raju Date of 17-09-2022 Sample ID 12763
Sampling
Sampling Downstream of Hasdeo river after Sampling Plan Fortnightly Sampling CMPDI/BSP/LSOP
Location joining mine discharge Kusmunda Method
(WBP)
Sample APPROPRIATE Date of Receipt 19-09-2022 Date of Analysis From 19-09-2022 To 19-09-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 12 of 22
TEST & SAMPLING REPORT OF (EFFLUENT WATER FORTNIGHTLY )
Unique Report No. TC-74012210258 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Ratan Gope Date of 03-09-2022 Sample ID 12560
Sampling
Sampling Workshop effluent Kusmunda Sampling Plan As Per Monthly Sampling CMPDI/BSP/LSOP
Location (WBP) Plan Method
Sample APPROPRIATE Date of Receipt 06-09-2022 Date of Analysis From 06-09-2022 To 25-09-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 13 of 22
TEST & SAMPLING REPORT OF (EFFLUENT WATER FORTNIGHTLY )
Unique Report No. TC-74012212424 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Indra Date of 17-09-2022 Sample ID 12767
Sampling
Sampling Workshop effluent Kusmunda Sampling Plan Fortnightly Sampling CMPDI/BSP/LSOP
Location (WBP) Method
Sample APPROPRIATE Date of Receipt 19-09-2022 Date of Analysis From 24-09-2022 To 28-09-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 14 of 22
TEST & SAMPLING REPORT OF (EFFLUENT WATER FORTNIGHTLY )
Unique Report No. TC-74012210238 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Ratan Gope Date of 03-09-2022 Sample ID 12555
Sampling
Sampling DETP of Kusmunda Kusmunda Sampling Plan As Per Monthly Sampling CMPDI/BSP/LSOP
Location (WBP) Plan Method
Sample APPROPRIATE Date of Receipt 06-09-2022 Date of Analysis From 06-09-2022 To 25-09-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 15 of 22
TEST & SAMPLING REPORT OF (EFFLUENT WATER FORTNIGHTLY )
Unique Report No. TC-74012210212 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Imte Date of 01-09-2022 Sample ID 12484
Sampling
Sampling DETP of Kusmunda Kusmunda Sampling Plan Fortnightly Sampling CMPDI/BSP/LSOP
Location (WBP) Method
Sample APPROPRIATE Date of Receipt 02-09-2022 Date of Analysis From 02-09-2022 To 06-09-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 16 of 22
TEST & SAMPLING REPORT OF (EFFLUENT WATER FORTNIGHTLY)
Unique Report No. 10212 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Imte Date of 01-09-2022 Sample ID 12484
Sampling
Sampling DETP of Kusmunda Kusmunda Sampling Plan Fortnightly Sampling CMPDI/BSP/LSOP
Location (WBP) Method
Sample APPROPRIATE Date of Receipt 02-09-2022 Date of Analysis From 02-09-2022 To 06-09-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 17 of 22
TEST & SAMPLING REPORT OF (EFFLUENT WATER FORTNIGHTLY )
Unique Report No. TC-74012212404 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By A Raju Date of 17-09-2022 Sample ID 12762
Sampling
Sampling DETP of Kusmunda Kusmunda Sampling Plan Fortnightly Sampling CMPDI/BSP/LSOP
Location (WBP) Method
Sample APPROPRIATE Date of Receipt 19-09-2022 Date of Analysis From 19-09-2022 To 19-09-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 18 of 22
TEST & SAMPLING REPORT OF (EFFLUENT WATER FORTNIGHTLY )
Unique Report No. TC-74012212318 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Nitesh Date of 18-09-2022 Sample ID 12740
Sampling
Sampling DETP of Kusmunda Kusmunda Sampling Plan Fortnightly Sampling CMPDI/BSP/LSOP
Location (WBP) Method
Sample APPROPRIATE Date of Receipt 19-09-2022 Date of Analysis From 20-09-2022 To 22-09-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 19 of 22
TEST & SAMPLING REPORT OF (EFFLUENT WATER FORTNIGHTLY)
Unique Report No. 12318 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Nitesh Date of 18-09-2022 Sample ID 12740
Sampling
Sampling DETP of Kusmunda Kusmunda Sampling Plan Fortnightly Sampling CMPDI/BSP/LSOP
Location (WBP) Method
Sample APPROPRIATE Date of Receipt 19-09-2022 Date of Analysis From 20-09-2022 To 22-09-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 20 of 22
TEST & SAMPLING REPORT OF (EFFLUENT WATER FORTNIGHTLY )
Unique Report No. TC-74012210246 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Ratan Gope Date of 03-09-2022 Sample ID 12557
Sampling
Sampling Mine water after settling tank Sampling Plan As Per Monthly Sampling CMPDI/BSP/LSOP
Location (Lagoon) Kusmunda (WBP) Plan Method
Sample APPROPRIATE Date of Receipt 06-09-2022 Date of Analysis From 06-09-2022 To 25-09-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 21 of 22
TEST & SAMPLING REPORT OF (EFFLUENT WATER FORTNIGHTLY )
Unique Report No. TC-74012212412 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Indra Date of 17-09-2022 Sample ID 12764
Sampling
Sampling Mine water after settling tank Sampling Plan Fortnightly Sampling CMPDI/BSP/LSOP
Location (Lagoon) Kusmunda (WBP) Method
Sample APPROPRIATE Date of Receipt 19-09-2022 Date of Analysis From 24-09-2022 To 28-09-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 22 of 22
Under jurisdiction of Bilaspur Court only Tel : 07815 -271233 (0)
cti1~cfil~-sfl Rl~t-s
"\
Fax: 07815 - 271250
Dear Sir,
Please find enclosed herewith the report on Self-Environmental Audit for stipulated
conditions of Environmental Clearance in respect of Kusmunda Opencast Project for the FY
2022-23 (Capacity: 50 MTPA (Normative)/62.5 MTPA (Peak)) of SECL, Kusmunda Area.
Encl: as above
Yours faithfully,
~-:1r-'i'V
CJ;
Nodal Officer (Env/F)
Kusmunda Area
~ ~- -
Copy to:
1. General Manager (Env.), SECL, Bilaspur-For kind appraisal.
2. General Manager, Kusmunda Area. - For kind information please.
3. Staff Officer (Mining), Kusmunda Area.
u#uriieedieietionifercrfeorfenly Tel:07815-271233
tfr. - -
®
Fax:07815-271250
SOUTII EASTERN COALFIELDS LIMITED
(ed en ffl air A Subsidiary of coal India Ltd.) fan dr ¢Tr.)
(A MINI RATI`IA COMPANY) fir. i 495454
GIN : U10102CT1985G01003161
Regd. Ofrice
I L,I. q5"ian,i5qudr PO : KUSMUNDA
SEEP.IT ROAD, COLLIERY DI
POST BO.I \-a: 60 OFFICE OF THE GENERAL MANAGER KOREA (CG)
BIL.\Spl-R(CG) KUSMUNDA AREA Pin 495454
Website: wi`rw+sect. rowin, e-mail: gln op. ksm.secl@coalind ia.in
Ffa`
tt I lt, RE(#/\=1,
q5qu dr
HrcirTcirTLj:_
1 q© q5qu ch - flTer ut
2, F€7iF ('ETF) t5flTU5T llit<tlull
3. afirf faa rfe7tF q55¥u€T dr
4. RTtF 3Tf" (th.;qfi.) z5HguBT dr
5. qiT mTtF q5HEu5T vRq`NiTil
6. ffi rfu 3Trm BHg05T ha
7. RitF GTfen (H Ta tr.) q5Hgu€T dr
8 ha GTfrm ( Tti. pj FT) qHBu5T dr
YEARLY OF MINE PLAN
MINE
(AsPerClause7ofamexureoftheGuidelinesforpreparationofMineClosurePlan;
No.55011-01-2009-CP"dt:07/01/2013tobesubmittedbeforelstJulyofevery
Date 17.06.2022
year)
To'
The Coal Controller,
Office of the Coal Controller,
1, Council House Street,
Kolkata-700001
Sir,
PleasefindherewiththeyearlyreportofMineClosureActivitiesfortheyear2021-]2
for Kusmunda OCP of Kusmunda Area of SECL Company as given below:
iiq Kusmunda OCP
1 `-ame ofcoal/Li nite minefolock:a)T\e:OpcruG"ixed:btTotallifeofthemine:
encast24Years as er 50 MTY P]
1 5 Years
ci Balance life of the mine.:`-ameandaddressoftheowner:
shri s K PALDirector(T)(P&P)SECL'Se patRoad,Bilaspur -495006Email:dtoseclh.comTelephone:07752-246309,246310FAX:07752-246453H
28.70 Ha
i) Physical:70.10HaiiBioloical:NilaTotalPlantationin
Area Reclaimed:DetailsofAfforestation:
11.
12 `1\»
2021-22: 53,000 mos.ttproessive:26,88,549 nos.fmonitoring
Photocopy 0reoutencLOsf:onitorlng I
Details of Water Quality Management:
13.
Photocopy 0reortenclosed
Details of Air Quality Management:WasteManaement2021-22:-
114.
]5.
35.936 Million cu. in.28.90MillionTe.
a uanti ofoverburdenremoval:buantiofcoal/Liitere.ect enerated:cUtilizationofwastematerialdone: f
Total uanti inbackfil ingCheckDam,Grassbedding.RetainingwallanddenseAfforestationisbeingdoneonreularbasis.
material'
Closure Plan
•r; To soil Mana ement:- 22.
YesForPlantation Reclamation.NA
17'18 Details of coal beneficiation facilities ado ted..SubsidenceMamaementforUGmineInfrastructure:ExistingandFutureUtilization NANA (mine is in operation )I)
i ,,19
and maintenance :(Roads,AerialRopeways, Conveyor belts,Railway,Bridge]Culverts,Powerlines,Buildingandstructures,WatertreatmentPlant,Watersupplyresources,Gaspipeline,Sewerlines,TelehonecablesTransformersetc.
NA (mine is in operation
DisposalofMachinery:-DecommissioningofMining machinery and theirossibleostminimutilization:Safeandsecuri:-
20.
2 K\ fi#/
NA (mine is in operation)NAmineisinoeration
Arrangement made up to the site being opened forgeneralpublic:
C
NA mine is in o eration
NA (mine is in operation)
b
97 t`)
Vcicational/ skill development training for sustainable,Cincomeofaffectedpeople:
:+ PostEn\ironmentalMonitoringfor3years(tobe NA(mineisinoperagi`enafterclosingofmine:Theabci`Leinformationgivenistruetothebestofmyknowledge.
t± -i;*<, •-L
.Igent GM (Mining)
kusmunda (OCP)
unddi:
Kusmunda AIea
-~ ~\~"
NODAL OFFICER (ENV/FOREST)
SECL KUSMUNDA AREA
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
Annexure-40
S. Main Issues Raised by the Then Comments of the Action Taken by the Project
No Public Project proponent till Date
1. Air quality data provided in Query refers to page XI-29 of Presently, the monitoring in
EIA/EMP in table no. 3.14 EIA/EMP regarding Air Quality. Kusmunda Area is being done at a
(a) is incorrect because the frequency of TWICE in a WEEK at
EIA compares the air quality All the parameters required in item no. Nine different locations. With this
data to the short term, rather XIV of TOR have been covered and frequency the total number of
than the long term data has been provided in chapter III of observations in a year comes to 104
permissible limits of the EIA/EMP report. per location which is as per NAAQS
MoEF, which are provided in It has been asked to compare the 2009 standards.
table 11.07 of the EIA. values of pollutant levels with
Because one season (3 concentration limit of annual time As per the compliance of EC
months) of base line air weighted average. It is evident from condition no. (i) for 36 MTY dated
rd
quality data were collected, it the literary meaning of word annual 3 July 2018, One Season
is inapt to compare the data that it is a period of 12 months i.e. all Baseline Data has been completed
to the 24 hours standards for four seasons including monsoon season by the CMPDIL. Report of the same
PM10 & PM2.5 which are 60 then its average value has to be has been enclosed as Annexure-
compared with annual time weighted 10.1.
and 40 ug/m3, respectively.
average.
In the present case the monitoring has As per the compliance of EC for 40
been done in one season only i.e. from MTPA, Work has been awarded to
15 Dec.2013 to 15 March 2014 (as per IIT Kharagpur for monitoring of air
TOR item no. XIV) and daily peak quality at identified locations of
values have been reported in the report Kusmunda OCP, both ambient and
not the average value. Accordingly, the the process area vid Ref no:
values have been compared with time SECL/GM/KA/ENV/19-20/161
weighted average of 24 hours i.e. for
dated 14.06.2019. Final Report has
PM10 is 100ug/m3 and PM2.5 is
60ug/m3 in spite of annual time been obtained from IIT Kharagpur in
weighted average values for PM 10 is the month of July, 2020. Copy of the
60 ug/m3 and for PM 2.5 is 40ug/m3. same has been submitted to Regional
Office, MoEF&CC, Nagpur vide ref
no.1756 dated: 26.07.2020. Suitable
measures are being complied as per
the recommendations of the above
study. Compliance Report of the
same has been enclosed as
Annexure-03.
Annexure-40
2. According to the TOR given to Query refers to item no. XXIV- AERMOD VIEW is a complete and
the mine, the measurement of impacts of mining on AAQ. powerful air dispersion modeling
effects of mining on the The modeling exercise has been package which seamlessly
Ambient Air Quality should be carried out using USEPA’S incorporates air dispersion models
carried out using I.S.C.S.T AERMOD View v.8.4.2, ISCST3.
(revised) or any other latest incorporating all the measures
model. provided in the Project Report of
Kusmunda OCP (62.5Mty) such as
in- pit conveyor belt system for the
transportation of coal inside
Kusmunda OCP. All the results
shown on page VII-21 of EIA/EMP
report are as predicted by the
aforementioned internationally
accepted AQ model. The impacts of
Kusmunda OC Expansion have been
summarized thoroughly in the
modeling.
3. According to the TOR given to Query refers to item no. XXVII of Green belt and afforestation plan is
the mine, Green Belt TOR- Progressive Green Belt and being carried out as per the EIA/EMP
development & Afforestation plan. of the mine. Action plan for green belt
Afforestation plan should be The progressive green belt and development is enclosed as Annexure-
carried out according to the afforestation plan has been provided 08.
following chart: Annexure – I. in table 4.52 along with details on
selection of species on page no. X-
6&7. The table provided in TOR
requires details of reclamation at an
interval of every five year is enclosed
as Annexure –
II. The relevant details have been
discussed thoroughly and the top soil
management programme has been
provided in table 4.31. The action
programme for EMP implementation
has been provided in fig. 16, page
no. VI – 5 of EIA along with details
of reclamation activities in phased
manner. Also various stage plans of
land reclamation have been provided
in plate VII, VIII, IX, X and XI. The
satellite imagery provided in plate
IV(d) provides figures of land
reclamation and detailed land use.
However, details in desired table 1 of
Term of Reference will be
incorporated in the final EIA/EMP
report, as has been provided herewith
as Annexure – XIV(A).
4. In EIA/EMP of the mine, Query refers to item no. XXXVIII - The conceptual final mine Closure
Conceptual Final Mine Closure Conceptual Final Mine Closure Plan. Plan has been discussed in chapter IV
Plan of the mine does not The conceptual final Mine Closure and details of fund to be deposited
provide any details about the Plan has been discussed in chapter IV every year and to be reimbursed at the
Physical, Chemical & and details of fund to be deposited end of every 5 years along with
Biological stability of the land every year and to be reimbursed at the tentative expenditure on suggested
at the time of Mine Closure end of every five years along with mine closure activities like OB dump
tentative expenditure on suggested reclamation (including backfilling,
mine closure activities like OB dump landscaping, biological reclamation
reclamation (including backfilling, and post closure monitoring) have
Annexure-40
landscaping, biological reclamation been provided therein. The provisions
and post closure monitoring) have have been made in accordance with
been provided therein. The provisions guidelines of Ministry of Coal issued
have been made in accordance with vide no. 55011-01-2009-CPAM dated
guidelines of Ministry of Coal issued 7.01.2013 regarding Mine closure
vide no. 55011-01- 2009-CPAM Plan.
dated 7th January, 2013 regarding
Mine Closure Plan.
5. It has been observed that 7 Query refers to item no. XXXIV Kusmunda Opencast is an ongoing
villages had been acquired regarding rehabilitation and project. The area of existing acquired
under the mine take of 10 resettlement. Kusmunda Opencast land is 3433.359 Ha (8484 acres) only
MTPA, & 5 villages under the Project had acquired 12 villages in after Section 11 of CBA, 1956 Act
mine take of 15 MTPA. Thus the mine lease area of 18.75 MTY. which contains total 17 villages under
the mine management had Their R&R is ongoing & till date total 50 MTPA capacity.
acquired a total of 12 villages 1142 people have already been
in the existing mine lease area. rehabilitated out of which 55 opted But present EC has been obtained for
Moreover, 5 more villages, for Cash Compensation & total 1578 1655.825 Ha (4091.6 acres for Phase-
namely- Amgaon, Churail, people have been given Employment I) which has only 7 villages. Rest
Khodri, Khairbhawna & Gevra, & 5 have opted for cash villages are currently under various
are to be acquired under the compensation. stages of R&R and are not yet under
proposed mine lease area of 50 In Kusmunda Opencast Expansion complete possession. Action Plan &
MTPA. In 1st phase (1655 Ha.) Project of 50 MTY, 5 more villages, Timeline of R&R of Phase-II villages
total of 1344 families would be namely- Amgaon, Churail, Khodri, is enclosed in Annexure 40.1
rehabilitated & 1142 families Khairbhawna & Gevra are to be
would have to be resettled. acquired in the upcoming years. In R&R is being done as per CIL R&R
Also, it was earlier said that thenormal course of action R&R policy 2012 & Chhattisgarh Rajya
land of 2166 families would be activities are being planned for 5 Adarsh Punarvas Niti-2007 and
acquired out of which 1543 years term. Present 5 year plan is employment is provided to Project
people would get employment from 2014-15 to 2018-19 which Affected People as per approved CIL
& 4 more would get cash includes rehabilitation and Policy.
Compensation. resettlement of Jatraj, Sonpuri & Pali
However, no details about village & its detail up to year 2018-19 Village wise status of Employment
the R&R of the above five has been provided in Chapter 4, Para given to PAPs is enclosed as
villages had been provided in 4.7.1 of Draft EIA/EMP. Annexure 40.1
the EIA/EMP of the Kusmunda
Thus, when the mine will advance
Opencast Expansion project of
towards the 5 villages in question,
50 MTPA. villagers and affected persons will be
informed & detailed Action
Programme for their R&R will be
prepared in 5 year advance to actual
rehabilitation and resettlement.
6. Kusmunda Opencast Coal Land acquisition work of expansion In the process of preparation and
Mine, SECL, Kusmunda Area project (50 MTPA) of Kusmunda approval of Project Report of
is undergoing capacity Open Cast Mines is being done under Kusmunda 50 MTPA, Techno-
expansion for 50 MTPA under CBA Act 1957, after techno- economic study has been considered
which additional land will be economic study of the project by at various stages and after that the
acquired. As such, “Techno- Ministry of Coal, Govt. of India, New approval has been granted by the CIL
Economic” study of the land Delhi and their approval of the same. Board.
must be done prior to the
acquisition.
Annexure-40
7. It has been observed that no Diversion of right back canal has not Work of Feasibility Study has been
techno- economic study have been covered in the existing PR and given to Central Water Commission.
been done in consultation with only Feasibility Study has been They have submitted an Interim
Irrigation Department Korba proposed. Report. Further action by SECL
regarding diversion of right SECL Management has conducted a management will be taken as per the
bank canal. high level meeting with Chhattisgarh Final Study Report of the
state irrigation and Central Water Commission.
Commission. A letter has been
written for feasibility study of
diversion of right bank canal to Water
resource Department. Acquisition of
land has been done As per CBA
(A&D) Act
8. Mine activities should be Coal is not only a natural resource but Mine activities are moving away from
restricted 8 to 10 Km away national property also. Due to mining Sarvamangla Mandir and Mahakali
from Sarvamangla Mandir and activities if reestablishment of Mandir. As per the Progressive Mine
Mahakali Mandir and proper Sarvamangla and Mahakali Mandir is Closure Plan & CC road, a four lane
road should be maintained needed than it will be done as per rule is under construction for easy
between these 2 temples. and with due consideration of the movement of Coal carrying tippers as
emotions of local people. well as public transportation around
Dipka, Gevra& Kusmunda on deposit
basis through PWD Govt. of CG at a
cost of 199.20 crores. Construction is
expected to be completed by May,
2023.
9. Under the proposed capacity There is no proposal of diversion of Work of Feasibility Study has been
enhancement of M/s Hasdeo River in the approved Project given to Central Water Commission.
Kusmunda Opencast Coal Report of Kusmunda Expansion They have submitted an Interim
Mine, SECL, Kusmunda Area, Project (50 MTY). Diversion of right Report. Further action by SECL
no techno-economic analysis bank canal has not been covered in management will be taken as per the
has been made in relation with the existing PR and only Feasibility Final Study Report of the
the diversion of Canal, Canal Study has been proposed. Commission.
road, HT line, & Hasdeo river.
Expansion Boundary should be
limited only up to the Right
Bank Canal.
10. Kusmunda Project, SECL is Various basic amenities is being CSR Work Action Plan is being
not carrying out community provided under the CSR activities prepared in consultation with local
development works in the around Kusmunda Project in radius of villagers every year & finalized with
affected villages. Roads in 25 Km. like Community Hall, School, the approval of District Collector
these villages are in very poor Market place, Stop Dam, Roads, hand under Deposit Scheme.
condition & even basic pumps, bore wells, overhead water Various CSR work for basic
amenities like drinking water tanks, etc. Regular maintenance of amenities are being done like
facilities are pending since Road in and around Kusmunda Community Hall, School, Market
many years. Project is being carried out. place, Stop Dam, Roads, hand pumps,
Kusmunda Area meets the bore wells, overhead water tanks, etc.
requirement of drinking water in In Addition to above, free medical
nearby villages by supplying potable facility is being provided to the BPL
water through mobile tankers as per Card holders & the project affected
requirement. persons in SECL Hospitals. Medical
Camps are also being organized in
affected villages for regular health
check & monitoring.
Details of Basic Amenities
provided by under CSR head for last
years is enclosed as Annexure-40.2.
CSR Expenditure for FY 2022-23
(Apr-Sep) is Rs 1.75 Lakhs.
Annexure-40
11. SECL management should SECL Management had conducted a Various CSR work for basic
provide basic facilities like survey of status of resources in amenities are being done like
Electricity, Water, Roads, villages in and around the project Community Hall, School, Market
Hospital facility, Education etc. area by CHHATTISGARH CENTRE place, Stop Dam, Roads, hand pumps,
in the affected villages. FOR ENTREPRENURSHIP bore wells, overhead water tanks, etc.
DEVELOPMENT In Addition to above, free medical
(an ISO 9001-2008 organization). facility is being provided to the BPL
Copy of survey report is enclosed as Card holders & the project affected
Annexure – VI. On the basis of persons in SECL Hospitals. Medical
survey report various CSR work for Camps are also being organized in
basic amenities are being done like affected villages for regular health
Community Hall, School, Market check & monitoring.
place, Stop Dam, Roads etc. In
addition to above free medical Details of Basic Amenities provided
facility is being provided to the BPL by under CSR head for last years is
card holders and the project effected enclosed as Annexure-40.2. CSR
persons. Also medical camp is being Expenditure for FY 2022-23 (Apr-
organized in affected villages. Sep) is Rs 1.75 Lakhs.
Details of basic facilities provided are
given in Annexure – XIV (D).
12. Blasting is carried out for coal Winning of Coal is being done by Winning of Coal is being done by
mining because of which rock surface miner which eliminates surface miner which eliminates
fragments fly to the nearby Blasting in Coal. However in OB Blasting in Coal. However, in OB
areas & also because of this control blasting is being practiced control blasting is being practiced
blasting, cracks develop in the which minimize ground vibration and which minimizes ground vibration
houses in the nearby villages fly rock. Regular monitoring of and fly rock. Regular monitoring of
which creates the possibility of ground vibration is being done and ground vibration is being done and
accidents. complete operation of blasting is complete operation of blasting is
carried out as per the standards laid carried out as per the standards laid
down by DGMS. Result of vibration down by DGMS. Result of vibration
study shows that it is well within the study shows that it is well within the
limits as per DGMS guidelines. Copy limits as per DGMS guidelines. Copy
of the study is enclosed as Annexure of the study is enclosed as
– XI. ANNEXURE –37.
13. In Kusmunda Open Cast An amount of Rs. 949.02 Crores is R&R is being done as per CIL R&R
expansion Project, due to land allocated In the approved Project policy 2012 & Chhattisgarh Rajya
acquisition and mining Report of Kusmunda expansion Adarsh Punarvas Niti-2007 and
activities nearby villages were Project (50 MTY) for Land employment is provided to project
effected. The acquisition and R&R. Now CIL’s affected persons as per approved
employment and R&R Policy 2012 has been framed policy.
compensation has not been and presently approval of the same
given by SECL for acquisition of land (10-15 MTY) Village wise status of Employment
management. has been obtained from State given to PAPs is enclosed as
Authorities. Presently, employment Annexure-40.1.
facilities are being given according to
this policy.
14. Kusmunda mine is operational Only regular back filling is being There are total 13 external dumps &
from the year 1979, back practiced in Kusmunda Open Cast one internal dump / backfilled dump
filling works are kept pending. Project. Since last 4 years all the OB at Kusmunda OCP. An area 0f 325
Management should produced is being back filled. Ha has been allocated for external
simultaneously carry out mine An area of 325 Ha has been allocated OB dump as per EC, out of which
back filling activities in order for external OB dump, out of which only 196.242 Ha has been utilized.
to maintain the groundwater only 196 Ha. has been utilized for the No more external dumps will be
level in the surrounding same. As per the operational plan of created in future & all the
villages. Moreover, dense Kusmunda OCP no further external overburden is planned for backfilling
plantation should be carried out dumping will be done. in the internal dump only.
on the back filled land. The effect of mining on ground water
is being monitored by 2 sets (4 nos.)
Annexure-40
of piezometers. The study of last 3 Currently, the effect of mining on
years clearly shows a positive growth ground water is being monitored by
in ground water level in lean period. 4 sets (10 nos.) of piezometers.
However further 2 new set (07 Nos.)
of piezometers is being installed on Moreover, out of 7 nos. of Automatic
dip & rise side of mine for close Digital Water Level Recorder one
monitoring of ground water at various no. has been installed at GM office
levels. Complex and the remaining are
Regular dense plantation is being being installed for continuous
done on backfilled area. Since monitoring of ground water level.
inception of the mines till date more
than 20 lakhs saplings has been A total of 18.00 lakhs plants have
planted, this creates dense forest on been planted till date on OB Dumps
our overburden dump. of Kusmunda OCP. Gap Plantation
has been undertaken by PP in past 4
years to strengthen the existing green
belt.
15. Agricultural activities also get On the basis of technical study it is Currently, the effect of mining on
affected by the coal mining in concluded that ground water level is ground water is being monitored by 4
Kusmunda Project. affected up to a distance 0.65 to 1.4 sets (10 nos.) of piezometers.
Groundwater level has also km due to open cast mining activities Moreover, out of 7 nos. of Automatic
gone down creating drinking of Kusmunda. The effect of mining Digital Water Level Recorder one no.
water problems & non- on ground water is being monitored has been installed at GM office
availability of adequate water by 4 sets (11 nos.) of piezometers. Complex and the remaining are being
for irrigation thereby affecting The study of last 3 years clearly installed for continuous monitoring of
crop growth. shows a positive growth in ground ground water level.
water level in lean period. Kusmunda
area meets the requirement of the Kusmunda area also meets the
drinking water in nearby villages by requirement of the drinking water in
supplying of potable water through nearby villages by supplying of
mobile tankers in lean period as per potable water through mobile tankers
requirement. in lean period as per requirement
(Annexure-36).
16. There is discrepancy in the There is no discrepancy in the Data There is no discrepancy in the Data
Data provided in the Executive provided in the Executive summary provided in the Executive summary
summary & EIA Report. Please & EIA Report. & EIA Report.
clarify the situation.
17. Due to coal transportation 1. Only 5% of coal is to be Action Plan for Coal Evacuation at
activities air pollution is transported through road and Kusmunda OCP is as follows:
increasing which is having an major quantity will be transported A new overhead state-of-the-art
adverse effect on the health of through railway and belt 20,000 Te Bunker & Truck
people in the nearby villages & conveyor. Receiving Station (CHP Phase – I)
SECL management is not 2. In addition to that in 50 MTY has been commissioned from
carrying out appropriate expansion project, coal 08.02.2020. Annually 7.00 MT coal
arrangement for dust transportation will be executed by is transported through a closed
suppression. covered conveyer belt from pit conveyor belt to nearby thermal
bottom to silo and from silo to power station.
railway wagon. This system will Four nos. of new SILO’s with
effectively control fugitive dust Rapid Loading System (4000 Te
emission during the coal capacity each) along with New
transportation. Railway Siding (CHP Phase- II)
3. To reduce the fugitive dust has been commissioned from
generation during the 24.08.2021. This eliminates the
transportation of coal all the
need of loading of coal by pay
internal and external roads in
and around of Kusmunda Project loaders into rail wagons. It also
are black toped and maintained enhances the capacity of despatch
in good condition and regular of coal from Kusmunda Project
Annexure-40
water sprinkling is being done. (40.00 MTPA) & further eliminates
Thick plantation is done on both road transport of coal outside the
sides of coal transportation road mine to end consumers.
and around colony area to arrest CHP Phase-III – In-Pit Belt
the fugitive dust. Conveyors: Work has been
awarded for Construction of In-pit
belt conveyor on 18.01.2021.
Physical progress: 31% upto
30.09.2022. It is likely to be
completed by 31/12/2023.
Connectivity of New Railway
Siding to East-West Rail Corridor
Project (Rs. 27 crores):- Work
progress 13% up to 30.09.22. This
will facilitate faster integration &
movement of coal across the
country.
Construction of Integrated Main
Workshop Complex:- Work
Progress 96% upto 30.09.2022.
This will reduce the movement of
HEMM to multiple locations & will
provide a single location for
undertaking pollution control
measures.
Construction of 02 Nos.CC Roads
(Four-Lane) for easy movement of
Coal carrying tippers as well as
public transportation around three
Mega Opencast project of SECL
(Dipka, Gevra & Kusmunda) on
deposit basis through PWD Govt.
of CG at a cost of 199.20 crores.
Construction is likely to be
completed by May, 2023.
Construction of approach road for
connecting ROB with Gevra-
Korba Road at Kusmunda Project
of Kusmunda (Ph-I) completed at a
cost of Rs 4.15 crores for direct
mine entry has been completed.
This will reduce the distance
travelled by trucks & will be
integrated with above four laning
project of public transportation CC
road being carried out by PWD
department.
Construction of CC road from
Weigh Bridge No. 02 to TRS
Phase-I with five year maintenance
and a project cost of 11.37 crores
has been completed. This
minimizes road dust within mine
premises till CHP phase-III until
the completion of In-pit belt
conveyor i.e. 31.12.2023.
Annexure-40
18. Management does not provide Management gives employment to Management gives employment to
employment to the land oustees those land oustees who are found those land oustees who are found
whose land is acquired for the eligible. Before 1991, employment eligible. Before 1991, employment
mining purposes. and compensation was given as per and compensation was given as per
the guide line of Govt. of India. In the guide line of Govt. of India. In
1991 R&R policy of MP Govt. came 1991 R&R policy of MP Govt. came
in to force and it was amended in in to force and it was amended in
1995. Till date employment was 1995. Till date employment was
being given according to this policy. being given according to this policy.
Now CIL’s R&R Policy 2012 has Now, R&R is being done as per CIL
been framed and presently approval R&R policy 2012 & Chhattisgarh
of the same is pending at State Rajya Adarsh Punarvas Niti-2007 and
Authority As soon as it will get employment is provided to project
approved, the employment facility affected persons as per approved
will be given according to this policy. policy.
19. Mine Management does not SECL management had already Measures such as widening of
maintaining the roads properly provided black topped/ paved roads in existing roads, construction of speed
due to which rate of road & around Kusmunda:- e.g., 10 km breakers at strategic locations,
accidents are increasing. road from Kusmunda to Gevra, 10 km cementation of some roads, regular
road from Kusmunda to Banki, 12 km water sprinkling on the public roads,
road from Kusmunda to Hardi Bazar, sign hoardings, proper lighting along
& 10 km road from Kusmunda to the public roads etc. are being
Korba etc. & these roads are practiced in consultation with the
maintained in excellent condition. State govt. and reviewed by DGMS to
minimize the no. of accidents.
20. SECL Management does not SECL management is maintaining a Medical Camps, Plantation
maintaining proper relations cordial relation with the villagers of Programmes, Swacchta Abhiyan
with the villagers of nearby nearby affected villages and regular Programmes, etc. are being regularly
villages & also does not give dialogue is being practiced with conducted with active participation of
adequate attention to the PAPs. Also the project affected nearby villagers. Camps are being
employment & health of the people are freely treated in the health organized with the help of District
people. centers of SECL & also regular health Govt. for expediting the pending
check-up / Medical Camps are being cases of land compensation, cash
organized in effected villages. compensation & employment.
21. SECL management has carried Afforestation activities in the SECL Plantation activities is
out plantation but fruit bearing Kusmunda area are carried out by carried out by SECL,
as well as medicinal plants had Chhattisgarh Rajya Van Vikas Nigam Kusmunda Area in MoU
not been planted. Hence, (CGRVVN) & the breakup of types with CGRVVN and the
plantation of fruit bearing & of plants are as follows: 35% - break-up of type of plants
medicinal plants should be medicinal / herbal, 15% - fruit are as follows: 35%-
medicinal/herbal; 15%-fruit
done. bearing, 48% - timber / forest & 2% -
bearing; 48%- timber/forest
ornamental species are being planted. & 2%-ornamental species
are being planted.
Apart from the yearly
plantation programmes on
Dump as well as Non-Dump
Area, SECL is carrying out
plantation in the
surrounding villages in
consultation with the
villagers. A total of 6,855
Nos. of Fruit Bearing
Species were planted at Bata
Village in 2017-18.
Moreover, 100 Saplings
Fruit Bearing Species were
planted in Green Haat, Birda
Village near Kusmunda in
2018-19 under Swachhta
Annexure-40
Pakhwada Programme.
During 2019-20, 1100
saplings have been planted
at schools, colonies and
distributed during
environment day and
Swachhta Pakhwada
Programmes as well.
During 2020-21, 500
saplings were distributed on
behalf of “Vanmahostav”
programme to local
residents.
During 2021-22, about 1100
saplings & 100 quintals of
vermin-compost was
distributed during
“Vanmahostav” programme
to common villagers along
with massive plantation
drive & awareness
campaign with local
representatives & schools.
During the year 22-23, over
3600 saplings and have been
distributed and 5,000 kgs of
vermicompost has been
distributed with massive
plantation drives and
campaigns with local
community and schools.
22. In villages Barkuta, Ganga Village Barkuta has already been Details of Basic Amenities provided
Nagar, Yamuna Nagar and rehabilitated & basic amenities has by Kusmunda Area are enclosed as
Vaishali Nagar there is no been provided in R&R village of ANNEXURE-40.2.
drinking water available. Kusmunda area the list of basic
Management is acquiring lands amenities provided as Annexure
only & not providing XIV (D). The facility of employment
employment to the land is being given on the basis of
oustees, there is no basic prevailing laws at that time.
amenities provided in
rehabilitated villages.
23. There is no drinking water in In and around Kusmunda Area, a Details of Basic Amenities provided
the villages, & the ponds are survey of status of resources in by Kusmunda Area are enclosed as
filled up with black dust & no villages was conducted through ANNEXURE- 40.2.
measures are being taken up by CHHATTISGARH CENTRE FOR
the management. ENTREPRENURSHIP Kusmunda area also meets the
DEVELOPMENT (an ISO 9001-2008 requirement of the drinking water in
organization). Copy of survey report nearby villages by supplying of
is enclosed as Annexure – XIV (D). potable water through mobile tankers
On the basis of survey report as per in lean period as per requirement
requirement basic amenities regarding (ANNEXURE-36).
drinking water is being provided
under CSR work. In addition to this, In addition to this, time to time
time to time cleaning and deepening cleaning and deepening of ponds are
of ponds is being done under CSR. In being done under CSR. Boreholes,
effected villagers, potable drinking Submersible Pumps & Tanks are
water is being supplied through provided. Work has been completed
tankers. To control the fugitive dust for deepening of pond at Sarvamangla
emission, heavy plantation is done all nagar (up dip side) of Kusmunda
along coal transport road inside the
OCP under CSR head.
mine and around the colony area and
Annexure-40
effective water spraying is done on A suitable plan for de-siltation &
coal transportation road by fixed and deepening of about 33 no. of village
mobile sprinklers. tanks & other water bodies (along
with their GPS Coordinates) located
within 5 kms from the Mine Lease
Boundary of Kusmunda OC Project
has been prepared for a four year
period (i.e. from, FY 2022-23 to FY
2025-26) by Kusmunda Area & duly
verified by DFO, Katghora. Work has
been awarded.
24. Under Kusmunda expansion Copy of the Section 4 has been Copy of the Section 4 has been
project, to acquire villages, distributed to the Sarpanchs of the distributed to the Sarpanchs of the
Section 4 have been published. concerned villages for wide publicity concerned villages for wide publicity.
But no information given to & they were meant to be pasted on
effected villagers. The project the notice boards of the Panchayat
proponent should give Bhawan.
information to the local
affected villagers.
25. Affected People are highly For land acquisition SECL R&R is being done as per CIL R&R
disappointed with the management, worked on the basis of policy 2012 & Chhattisgarh Rajya
management for not following prevailing laws at that time. Adarsh Punarvas Niti-2007 and
the policies of R&R & Land employment is provided to project
Acquisition or any other affected persons as per approved
related policies. policy. Village wise status of
Employment given to PAPs is
enclosed as ANNEXURE –40.1.
26. SECL management, after land Employment is provided to project Employment is provided to project
acquisition gives employment Affected persons as per vacancy exist affected persons as per vacancy exist
to male dependent only. Why in the company. Presently, major in the company.
no employment is being given vacancy in the company is in Presently, eligible female dependents
to the female dependent? underground mines, as per Mines Act, are also being given employment as
1952, women cannot be deployed in per the policy of the company.
underground mines. Hence no
employment is being given to women
PAPs.
27. EIA report mentions 8676 Kusmunda Opencast is an ongoing Kusmunda Opencast is an ongoing
acres of land which will be project. The area of existing acquired project. The area of existing acquired
acquired, but in reality, there land is 2382.764 Ha (5887.8 acres) land is 1655.825 Ha (4091.6 acres)
exists only 4645 acres of land under 18.75 MTPA capacity. For 50 under 40 MTPA capacity for 50
in the 5 villages to-be acquired. MTPA capacity expansion, additional MTPA capacity expansion, an extra
Therefore, it fails to provide 1127.56 Ha (2786.2 acres) land will 1777.534 Ha (4392.38 acres) land
any information about the rest be acquired. Hence, for 50 MTPA needs to be acquired out of which
4028 acres of land. expansion capacity, total land 726.941 Ha (1796.3 acres) only has
becomes 3510.348 Ha (8674 acres) already been acquired under 18.75
only. MTY. Thus, only an additional land
of 1050.593 Ha (2596.07 acres) was
acquired under 50 MTY capacity
expansion under Section11 of CBA,
1956 Act.
Hence, for 50 MTPA expansion
capacity, total land becomes
3433.359 Ha (8484 acres) only after
Section 11 of CBA, 1956 Act.
XXX -XXX
COPYRIGHT WITH
CMPDI
A MINI RATNA
ISO 9001 COMPANY
(KUSMUNDA AREA)
`Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of issue 17.03.2022
Sample Reference No. CMPDI/Q12/59, Dated: 16.02.2022
Name of the Project Kusmunda
Date of Analysis 18.02.2022 to 16.03.2022
LDL 0.01 µg/ m3 0.01 µg/ m3 1.0 ng/m3 1.0 ng/m3 1.0 ng/m3 0.01 µg/ m3
Uncertainty of Measurement ±1.185 µg/m3 ±1.185 µg/m3 ±0.146 ng/m3 ±0.146 ng/m3 ±0.146 ng/m3 ±1.185 µg/m3
(95% C.L & K=1.96) at 51.034µg/m3 at 51.034µg/m3 at 9.917ng/m3 at 9.917 ng/m3 at 9.917 ng/m3 at 51.034µg/m3
USEPA Method USEPA Method USEPA Method USEPA Method USEPA Method USEPA Method
Method of Analysis IO-3.2 IO-3.2 IO-3.2 IO-3.2 IO-3.2 IO-3.2
4. CGM office, Kusmunda Area 02.02.2022 BDL 0.08 BDL BDL BDL BDL
8. Workshop No. 3, KOCP 01.02.2022 BDL BDL BDL BDL BDL BDL
9. Workshop No. 1, KOCP 01.02.2022 BDL BDL BDL BDL BDL BDL
Page 1 of 1
COPYRIGHT WITH
CMPDI
A MINI RATNA
ISO 9001 COMPANY
(KUSMUNDA AREA)
2022 - 2023
INDEX
04 Workshop effluent 4
05 DETP Kusmunda 5
TOTAL 6
TEST & SAMPLING REPORT OF (EFFLUENT WATER )
Unique Report No. TC-740122006874 Report Issue Date 26-07-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Nitesh Date of 10-07-2022 Sample ID 11973
Sampling
Sampling Mine Water at Discharge Point Sampling Plan Annual Sampling CMPDI/BSP/LSOP
Location Kusmunda (WBP) Method
Sample APPROPRIATE Date of Receipt 11-07-2022 Date of Analysis From 11-07-2022 To 24-07-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
1 of 6
TEST & SAMPLING REPORT OF (EFFLUENT WATER )
Unique Report No. TC-740122006876 Report Issue Date 26-07-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Nitesh Date of 10-07-2022 Sample ID 11974
Sampling
Sampling U/S of Hasdeo river near railway Sampling Plan Annual Sampling CMPDI/BSP/LSOP
Location bridge Kusmunda (WBP) Method
Sample APPROPRIATE Date of Receipt 11-07-2022 Date of Analysis From 11-07-2022 To 24-07-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
2 of 6
TEST & SAMPLING REPORT OF (EFFLUENT WATER )
Unique Report No. TC-740122007058 Report Issue Date 04-08-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Nitesh Date of 10-07-2022 Sample ID 11970
Sampling
Sampling D/S Hasdeo river after joining mine Sampling Plan Annual Sampling CMPDI/BSP/LSOP
Location discharge Kusmunda (WBP) Method
Sample APPROPRIATE Date of Receipt 11-07-2022 Date of Analysis From 11-07-2022 To 02-08-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
3 of 6
TEST & SAMPLING REPORT OF (EFFLUENT WATER )
Unique Report No. TC-740122006878 Report Issue Date 26-07-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Nitesh Date of 10-07-2022 Sample ID 11975
Sampling
Sampling Workshop effluent Kusmunda Sampling Plan Annual Sampling CMPDI/BSP/LSOP
Location (WBP) Method
Sample APPROPRIATE Date of Receipt 11-07-2022 Date of Analysis From 11-07-2022 To 24-07-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
4 of 6
TEST & SAMPLING REPORT OF (EFFLUENT WATER )
Unique Report No. TC-740122007061 Report Issue Date 04-08-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Nitesh Date of 10-07-2022 Sample ID 11971
Sampling
Sampling DETP Kusmunda Kusmunda (WBP) Sampling Plan Annual Sampling CMPDI/BSP/LSOP
Location Method
Sample APPROPRIATE Date of Receipt 11-07-2022 Date of Analysis From 11-07-2022 To 02-08-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
5 of 6
TEST & SAMPLING REPORT OF (EFFLUENT WATER )
Unique Report No. TC-740122007064 Report Issue Date 04-08-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Nitesh Date of 10-07-2022 Sample ID 11972
Sampling
Sampling Mine Water after Settling Tank Sampling Plan Annual Sampling CMPDI/BSP/LSOP
Location Kusmunda (WBP) Method
Sample APPROPRIATE Date of Receipt 11-07-2022 Date of Analysis From 11-07-2022 To 02-08-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
* General Standards for Discharge of Environmental Pollution(Part A:Effluent) as per Schedule VI,Environment (Protection) Rules
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
6 of 6
Ground Water Quality Report
Kusmunda Area
Through
Prepared by
Shraddha Kere
Authorised Signatory
1
GROUND WATER QUALITY REPORT
(July to September - 2022)
Month July, 2022 Area Kusmunda Report No. NIL/CMPDI/RPT/22/07/016
Customer South Eastern Coalfields Ltd. (SECL), Bilaspur Date of Issue 31-Jul-2022
Project Kusmunda Mines Sample Ref. No. NIL/W/07/22/274-275
1 Birda - Govt. Well Date of Sampling 21-Jul-2022
Sampling Stations
2 Risdi - Prem Singh Date of Sampling 21-Jul-2022
Page No. 2 of 2 Date of Analysis 25-Jul-2022 to 29-Jul-2022
Observed Values IS 10500:2012 Measurement Uncertainty
Sl.
Parameter Meathod of Analysis Acceptable Limit Permissible Limit** (@ 95% Confidence level &
No. 1 2 K=1.96)
(Max)* (Max)
Temperature : °C IS 3025 (Part 9)
27 33.5 30.2 --- --- NA
LDL : 0.1 Direct Measurement Method
Colour : Hazen IS 3025 (Part 4)
28 BDL BDL 5 15 NA
LDL : 5 Platinum cobalt Method
Ca⁺⁺ : mg/L IS 3025(Part 40)
29 113 32 --- --- 200 mg/l±3.98 mg/l
LDL : 5 EDTA method
Mg⁺⁺ : mg/L IS 3025(Part 46)
30 45 28 --- --- 120 mg/l±3 mg/l
LDL : 5 Calculation Method
Carbonates : mg/L IS 3025 (Part 23)
31 0 0 --- --- 500 mg/l±8.6mg/l
LDL : Indiacator Method
Bicarbonates : mg/L IS 3025 (Part 23)
32 512 30 --- --- 500 mg/l±8.6mg/l
LDL : Indiacator Method
Dissolved Oxygen (DO) : mg/L APHA 4500-O(B), 23ʳᵈ Edition
33 6.2 6 --- --- NA
LDL : Iodometric method
Mercury : mg/L IS 3025 (Part 48)
34 BDL BDL 0.001 No relaxation NA
LDL : Atomic Absorption Method
Selenium : mg/L IS 3025 (Part 56)
35 BDL BDL 0.01 No relaxation NA
LDL : Atomic Absorption Method
Arsenic : mg/L IS 3025 (Part 37)
36 BDL BDL 0.01 No relaxation NA
LDL : Atomic Absorption Method
Barium : mg/L IS 13428 (Annex F)
37 BDL BDL 0.7 No relaxation 5mg/l±0.62mg/l
LDL : 5 Nitrous Oxide- Acetylene Flame Method
Total Coliforms : MPN/100ml IS 1622-1981
38 Absent Absent Absent No relaxation NA
LDL : 0 ---
Ion Balance (Percent Difference) By Calculation
39 -2.19 -2.53 --- --- ---
--- ---
Note : 1. LDL indicates Lower Detection Limit & BDL indicates Below Detection Limit 4. This Test Report shall not be reproduced except in full, without written approval of the Laboratory.
2. *Except Sl. No. 10 which Acceptable limit is Min 5. This Test Report refers only to the sample tested.
3. **Permissible Limit in the Absence of Alternate Source 6. The complaint register is available with the Laboratory as per Environment Protection Act, 1986.
***End of Report***
Shraddha Kere
Authorised Signatory
2
TC-6709
Shraddha Kere
Authorised Signatory
3
GROUND WATER QUALITY REPORT
(July to September - 2022)
Month July, 2022 Area Kusmunda Report No. NIL/CMPDI/RPT/22/07/017
Customer South Eastern Coalfields Ltd. (SECL), Bilaspur Date of Issue 31-Jul-2022
Project Kusmunda Mines Sample Ref. No. NIL/W/07/22/276-277
3 Bhatapara - Govt Well Date of Sampling 21-Jul-2022
Sampling Stations
4 Khairbhawana - Pvt. Well Date of Sampling 21-Jul-2022
Page No. 2 of 2 Date of Analysis 25-Jul-2022 to 29-Jul-2022
Observed Values IS 10500:2012 Measurement Uncertainty
Sl.
Parameter Meathod of Analysis Acceptable Limit Permissible Limit** (@ 95% Confidence level &
No. 3 4 K=1.96)
(Max)* (Max)
Temperature : °C IS 3025 (Part 9)
27 32.7 33.4 --- --- NA
LDL : 0.1 Direct Measurement Method
Colour : Hazen IS 3025 (Part 4)
28 BDL BDL 5 15 NA
LDL : 5 Platinum cobalt Method
Ca⁺⁺ : mg/L IS 3025(Part 40)
29 54 76 --- --- 200 mg/l±3.98 mg/l
LDL : 5 EDTA method
Mg⁺⁺ : mg/L IS 3025(Part 46)
30 18 24 --- --- 120 mg/l±3 mg/l
LDL : 5 Calculation Method
Carbonates : mg/L IS 3025 (Part 23)
31 0 0 --- --- 500 mg/l±8.6mg/l
LDL : Indiacator Method
Bicarbonates : mg/L IS 3025 (Part 23)
32 220 104 --- --- 500 mg/l±8.6mg/l
LDL : Indiacator Method
Dissolved Oxygen (DO) : mg/L APHA 4500-O(B), 23ʳᵈ Edition
33 5.4 5.2 --- --- NA
LDL : Iodometric method
Mercury : mg/L IS 3025 (Part 48)
34 BDL BDL 0.001 No relaxation NA
LDL : Atomic Absorption Method
Selenium : mg/L IS 3025 (Part 56)
35 BDL BDL 0.01 No relaxation NA
LDL : Atomic Absorption Method
Arsenic : mg/L IS 3025 (Part 37)
36 BDL BDL 0.01 No relaxation NA
LDL : Atomic Absorption Method
Barium : mg/L IS 13428 (Annex F)
37 BDL BDL 0.7 No relaxation 5mg/l±0.62mg/l
LDL : 5 Nitrous Oxide- Acetylene Flame Method
Total Coliforms : MPN/100ml IS 1622-1981
38 Absent Absent Absent No relaxation NA
LDL : 0 ---
Ion Balance (Percent Difference) By Calculation
39 -2.25 -1.99 --- --- ---
--- ---
Note : 1. LDL indicates Lower Detection Limit & BDL indicates Below Detection Limit 4. This Test Report shall not be reproduced except in full, without written approval of the Laboratory.
2. *Except Sl. No. 10 which Acceptable limit is Min 5. This Test Report refers only to the sample tested.
3. **Permissible Limit in the Absence of Alternate Source 6. The complaint register is available with the Laboratory as per Environment Protection Act, 1986.
***End of Report***
Shraddha Kere
Authorised Signatory
4
TC-6709
Shraddha Kere
Authorised Signatory
5
GROUND WATER QUALITY REPORT
(July to September - 2022)
Month July, 2022 Area Kusmunda Report No. NIL/CMPDI/RPT/22/07/018
Customer South Eastern Coalfields Ltd. (SECL), Bilaspur Date of Issue 31-Jul-2022
Project Kusmunda Mines Sample Ref. No. NIL/W/07/22/278-281
5 Sonpuri - Govt. Well Date of Sampling 21-Jul-2022
Sampling Stations
6 Sandel - Bhaktu Ram Date of Sampling 21-Jul-2022
Page No. 2 of 2 Date of Analysis 25-Jul-2022 to 29-Jul-2022
Observed Values IS 10500:2012 Measurement Uncertainty
Sl.
Parameter Meathod of Analysis Acceptable Limit Permissible Limit** (@ 95% Confidence level &
No. 5 6 K=1.96)
(Max)* (Max)
Temperature : °C IS 3025 (Part 9)
27 32.8 32.7 --- --- NA
LDL : 0.1 Direct Measurement Method
Colour : Hazen IS 3025 (Part 4)
28 BDL BDL 5 15 NA
LDL : 5 Platinum cobalt Method
Ca⁺⁺ : mg/L IS 3025(Part 40)
29 24 122 --- --- 200 mg/l±3.98 mg/l
LDL : 5 EDTA method
Mg⁺⁺ : mg/L IS 3025(Part 46)
30 18 48 --- --- 120 mg/l±3 mg/l
LDL : 5 Calculation Method
Carbonates : mg/L IS 3025 (Part 23)
31 0 0 --- --- 500 mg/l±8.6mg/l
LDL : Indiacator Method
Bicarbonates : mg/L IS 3025 (Part 23)
32 50 432 --- --- 500 mg/l±8.6mg/l
LDL : Indiacator Method
Dissolved Oxygen (DO) : mg/L APHA 4500-O(B), 23ʳᵈ Edition
33 4.8 4.5 --- --- NA
LDL : Iodometric method
Mercury : mg/L IS 3025 (Part 48)
34 BDL BDL 0.001 No relaxation NA
LDL : Atomic Absorption Method
Selenium : mg/L IS 3025 (Part 56)
35 BDL BDL 0.01 No relaxation NA
LDL : Atomic Absorption Method
Arsenic : mg/L IS 3025 (Part 37)
36 BDL BDL 0.01 No relaxation NA
LDL : Atomic Absorption Method
Barium : mg/L IS 13428 (Annex F)
37 BDL BDL 0.7 No relaxation 5mg/l±0.62mg/l
LDL : 5 Nitrous Oxide- Acetylene Flame Method
Total Coliforms : MPN/100ml IS 1622-1981
38 Absent Absent Absent No relaxation NA
LDL : 0 ---
Ion Balance (Percent Difference) By Calculation
39 -2.28 -2.32 --- --- ---
--- ---
Note : 1. LDL indicates Lower Detection Limit & BDL indicates Below Detection Limit 4. This Test Report shall not be reproduced except in full, without written approval of the Laboratory.
2. *Except Sl. No. 10 which Acceptable limit is Min 5. This Test Report refers only to the sample tested.
3. **Permissible Limit in the Absence of Alternate Source 6. The complaint register is available with the Laboratory as per Environment Protection Act, 1986.
***End of Report***
Shraddha Kere
Authorised Signatory
6
TC-6709
Shraddha Kere
Authorised Signatory
7
GROUND WATER QUALITY REPORT
(July to September - 2022)
Month July, 2022 Area Kusmunda Report No. NIL/CMPDI/RPT/22/07/019
Customer South Eastern Coalfields Ltd. (SECL), Bilaspur Date of Issue 01-Aug-2022
Project Kusmunda Mines Sample Ref. No. NIL/W/07/22/312-346
7 Chunchuni (Kabir Chuok) - Ram Krishna Chandra Date of Sampling 19-Jul-2022
Sampling Stations
8 Kandhaikhar - Ganesh Ram Date of Sampling 22-Jul-2022
Page No. 2 of 2 Date of Analysis 26-Jul-2022 to 30-Jul-2022
Observed Values IS 10500:2012 Measurement Uncertainty
Sl.
Parameter Meathod of Analysis Acceptable Limit Permissible Limit** (@ 95% Confidence level &
No. 7 8 K=1.96)
(Max)* (Max)
Temperature : °C IS 3025 (Part 9)
27 26.6 28.3 --- --- NA
LDL : 0.1 Direct Measurement Method
Colour : Hazen IS 3025 (Part 4)
28 BDL BDL 5 15 NA
LDL : 5 Platinum cobalt Method
Ca⁺⁺ : mg/L IS 3025(Part 40)
29 44 18 --- --- 200 mg/l±3.98 mg/l
LDL : 5 EDTA method
Mg⁺⁺ : mg/L IS 3025(Part 46)
30 11 10 --- --- 120 mg/l±3 mg/l
LDL : 5 Calculation Method
Carbonates : mg/L IS 3025 (Part 23)
31 0 0 --- --- 500 mg/l±8.6mg/l
LDL : Indiacator Method
Bicarbonates : mg/L IS 3025 (Part 23)
32 40 18 --- --- 500 mg/l±8.6mg/l
LDL : Indiacator Method
Dissolved Oxygen (DO) : mg/L APHA 4500-O(B), 23ʳᵈ Edition
33 5.8 5.8 --- --- NA
LDL : Iodometric method
Mercury : mg/L IS 3025 (Part 48)
34 BDL BDL 0.001 No relaxation NA
LDL : Atomic Absorption Method
Selenium : mg/L IS 3025 (Part 56)
35 BDL BDL 0.01 No relaxation NA
LDL : Atomic Absorption Method
Arsenic : mg/L IS 3025 (Part 37)
36 BDL BDL 0.01 No relaxation NA
LDL : Atomic Absorption Method
Barium : mg/L IS 13428 (Annex F)
37 BDL BDL 0.7 No relaxation 5mg/l±0.62mg/l
LDL : 5 Nitrous Oxide- Acetylene Flame Method
Total Coliforms : MPN/100ml IS 1622-1981
38 Absent Absent Absent No relaxation NA
LDL : 0 ---
Ion Balance (Percent Difference) By Calculation
39 -0.27 -0.65 --- --- ---
--- ---
Note : 1. LDL indicates Lower Detection Limit & BDL indicates Below Detection Limit 4. This Test Report shall not be reproduced except in full, without written approval of the Laboratory.
2. *Except Sl. No. 10 which Acceptable limit is Min 5. This Test Report refers only to the sample tested.
3. **Permissible Limit in the Absence of Alternate Source 6. The complaint register is available with the Laboratory as per Environment Protection Act, 1986.
***End of Report***
Shraddha Kere
Authorised Signatory
8
TC-6709
Shraddha Kere
Authorised Signatory
9
GROUND WATER QUALITY REPORT
(July to September - 2022)
Month July, 2022 Area Kusmunda Report No. NIL/CMPDI/RPT/22/07/020
Customer South Eastern Coalfields Ltd. (SECL), Bilaspur Date of Issue 30-Jul-2022
Project Kusmunda Mines Sample Ref. No. NIL/W/07/22/350-352
9 Jamnipali-2 - Ganga Prasad Sahu Date of Sampling 19-Jul-2022
Sampling Stations
10 Kohariya - Gewalsai Yadav Date of Sampling 20-Jul-2022
Page No. 2 of 2 Date of Analysis 24-Jul-2022 to 28-Jul-2022
Observed Values IS 10500:2012 Measurement Uncertainty
Sl.
Parameter Meathod of Analysis Acceptable Limit Permissible Limit** (@ 95% Confidence level &
No. 9 10 K=1.96)
(Max)* (Max)
Temperature : °C IS 3025 (Part 9)
27 26.1 26.5 --- --- NA
LDL : 0.1 Direct Measurement Method
Colour : Hazen IS 3025 (Part 4)
28 BDL BDL 5 15 NA
LDL : 5 Platinum cobalt Method
Ca⁺⁺ : mg/L IS 3025(Part 40)
29 77 56 --- --- 200 mg/l±3.98 mg/l
LDL : 5 EDTA method
Mg⁺⁺ : mg/L IS 3025(Part 46)
30 25 16 --- --- 120 mg/l±3 mg/l
LDL : 5 Calculation Method
Carbonates : mg/L IS 3025 (Part 23)
31 0 0 --- --- 500 mg/l±8.6mg/l
LDL : Indiacator Method
Bicarbonates : mg/L IS 3025 (Part 23)
32 350 256 --- --- 500 mg/l±8.6mg/l
LDL : Indiacator Method
Dissolved Oxygen (DO) : mg/L APHA 4500-O(B), 23ʳᵈ Edition
33 6.4 4.8 --- --- NA
LDL : Iodometric method
Mercury : mg/L IS 3025 (Part 48)
34 BDL BDL 0.001 No relaxation NA
LDL : Atomic Absorption Method
Selenium : mg/L IS 3025 (Part 56)
35 BDL BDL 0.01 No relaxation NA
LDL : Atomic Absorption Method
Arsenic : mg/L IS 3025 (Part 37)
36 BDL BDL 0.01 No relaxation NA
LDL : Atomic Absorption Method
Barium : mg/L IS 13428 (Annex F)
37 BDL BDL 0.7 No relaxation 5mg/l±0.62mg/l
LDL : 5 Nitrous Oxide- Acetylene Flame Method
Total Coliforms : MPN/100ml IS 1622-1981
38 Absent Absent Absent No relaxation NA
LDL : 0 ---
Ion Balance (Percent Difference) By Calculation
39 -0.06 1.32 --- --- ---
--- ---
Note : 1. LDL indicates Lower Detection Limit & BDL indicates Below Detection Limit 4. This Test Report shall not be reproduced except in full, without written approval of the Laboratory.
2. *Except Sl. No. 10 which Acceptable limit is Min 5. This Test Report refers only to the sample tested.
3. **Permissible Limit in the Absence of Alternate Source 6. The complaint register is available with the Laboratory as per Environment Protection Act, 1986.
***End of Report***
Shraddha Kere
Authorised Signatory
10
TC-6709
Shraddha Kere
Authorised Signatory
11
GROUND WATER QUALITY REPORT
(July to September - 2022)
Month July, 2022 Area Kusmunda Report No. NIL/CMPDI/RPT/22/07/021
Customer South Eastern Coalfields Ltd. (SECL), Bilaspur Date of Issue 30-Jul-2022
Project Kusmunda Mines Sample Ref. No. NIL/W/07/22/353-359
11 Gopalpur - Govt. Well Date of Sampling 19-Jul-2022
Sampling Stations
12 Jambahar - Govt. Well Date of Sampling 20-Jul-2022
Page No. 2 of 2 Date of Analysis 24-Jul-2022 to 28-Jul-2022
Observed Values IS 10500:2012 Measurement Uncertainty
Sl.
Parameter Meathod of Analysis Acceptable Limit Permissible Limit** (@ 95% Confidence level &
No. 11 12 K=1.96)
(Max)* (Max)
Temperature : °C IS 3025 (Part 9)
27 28.5 26.5 --- --- NA
LDL : 0.1 Direct Measurement Method
Colour : Hazen IS 3025 (Part 4)
28 BDL BDL 5 15 NA
LDL : 5 Platinum cobalt Method
Ca⁺⁺ : mg/L IS 3025(Part 40)
29 33 76 --- --- 200 mg/l±3.98 mg/l
LDL : 5 EDTA method
Mg⁺⁺ : mg/L IS 3025(Part 46)
30 15 33 --- --- 120 mg/l±3 mg/l
LDL : 5 Calculation Method
Carbonates : mg/L IS 3025 (Part 23)
31 0 0 --- --- 500 mg/l±8.6mg/l
LDL : Indiacator Method
Bicarbonates : mg/L IS 3025 (Part 23)
32 152 340 --- --- 500 mg/l±8.6mg/l
LDL : Indiacator Method
Dissolved Oxygen (DO) : mg/L APHA 4500-O(B), 23ʳᵈ Edition
33 5.3 5.3 --- --- NA
LDL : Iodometric method
Mercury : mg/L IS 3025 (Part 48)
34 BDL BDL 0.001 No relaxation NA
LDL : Atomic Absorption Method
Selenium : mg/L IS 3025 (Part 56)
35 BDL BDL 0.01 No relaxation NA
LDL : Atomic Absorption Method
Arsenic : mg/L IS 3025 (Part 37)
36 BDL BDL 0.01 No relaxation NA
LDL : Atomic Absorption Method
Barium : mg/L IS 13428 (Annex F)
37 BDL BDL 0.7 No relaxation 5mg/l±0.62mg/l
LDL : 5 Nitrous Oxide- Acetylene Flame Method
Total Coliforms : MPN/100ml IS 1622-1981
38 Absent Absent Absent No relaxation NA
LDL : 0 ---
Ion Balance (Percent Difference) By Calculation
39 -1.77 0.68 --- --- ---
--- ---
Note : 1. LDL indicates Lower Detection Limit & BDL indicates Below Detection Limit 4. This Test Report shall not be reproduced except in full, without written approval of the Laboratory.
2. *Except Sl. No. 10 which Acceptable limit is Min 5. This Test Report refers only to the sample tested.
3. **Permissible Limit in the Absence of Alternate Source 6. The complaint register is available with the Laboratory as per Environment Protection Act, 1986.
***End of Report***
Shraddha Kere
Authorised Signatory
12
TC-6709
Shraddha Kere
Authorised Signatory
13
GROUND WATER QUALITY REPORT
(July to September - 2022)
Month July, 2022 Area Kusmunda Report No. NIL/CMPDI/RPT/22/07/022
Customer South Eastern Coalfields Ltd. (SECL), Bilaspur Date of Issue 30-Jul-2022
Project Kusmunda Mines Sample Ref. No. NIL/W/07/22/364-378
13 Korba -D - Mandir Well Date of Sampling 20-Jul-2022
Sampling Stations
14 Bhadrapara - Nirmal Yadav Date of Sampling 19-Jul-2022
Page No. 2 of 2 Date of Analysis 24-Jul-2022 to 28-Jul-2022
Observed Values IS 10500:2012 Measurement Uncertainty
Sl.
Parameter Meathod of Analysis Acceptable Limit Permissible Limit** (@ 95% Confidence level &
No. 13 14 K=1.96)
(Max)* (Max)
Temperature : °C IS 3025 (Part 9)
27 28 32.7 --- --- NA
LDL : 0.1 Direct Measurement Method
Colour : Hazen IS 3025 (Part 4)
28 BDL BDL 5 15 NA
LDL : 5 Platinum cobalt Method
Ca⁺⁺ : mg/L IS 3025(Part 40)
29 24 20 --- --- 200 mg/l±3.98 mg/l
LDL : 5 EDTA method
Mg⁺⁺ : mg/L IS 3025(Part 46)
30 12 10 --- --- 120 mg/l±3 mg/l
LDL : 5 Calculation Method
Carbonates : mg/L IS 3025 (Part 23)
31 0 0 --- --- 500 mg/l±8.6mg/l
LDL : Indiacator Method
Bicarbonates : mg/L IS 3025 (Part 23)
32 100 32 --- --- 500 mg/l±8.6mg/l
LDL : Indiacator Method
Dissolved Oxygen (DO) : mg/L APHA 4500-O(B), 23ʳᵈ Edition
33 6.2 4.8 --- --- NA
LDL : Iodometric method
Mercury : mg/L IS 3025 (Part 48)
34 BDL BDL 0.001 No relaxation NA
LDL : Atomic Absorption Method
Selenium : mg/L IS 3025 (Part 56)
35 BDL BDL 0.01 No relaxation NA
LDL : Atomic Absorption Method
Arsenic : mg/L IS 3025 (Part 37)
36 BDL BDL 0.01 No relaxation NA
LDL : Atomic Absorption Method
Barium : mg/L IS 13428 (Annex F)
37 BDL BDL 0.7 No relaxation 5mg/l±0.62mg/l
LDL : 5 Nitrous Oxide- Acetylene Flame Method
Total Coliforms : MPN/100ml IS 1622-1981
38 Absent Absent Absent No relaxation NA
LDL : 0 ---
Ion Balance (Percent Difference) By Calculation
39 1.04 0.45 --- --- ---
--- ---
Note : 1. LDL indicates Lower Detection Limit & BDL indicates Below Detection Limit 4. This Test Report shall not be reproduced except in full, without written approval of the Laboratory.
2. *Except Sl. No. 10 which Acceptable limit is Min 5. This Test Report refers only to the sample tested.
3. **Permissible Limit in the Absence of Alternate Source 6. The complaint register is available with the Laboratory as per Environment Protection Act, 1986.
***End of Report***
Shraddha Kere
Authorised Signatory
14
COPYRIGHT WITH
CMPDI
A MINI RATNA
ISO 9001 COMPANY
(KUSMUNDA AREA)
SEPTEMBER - 2022
Page No
Sl.No Name of stations
KUSMUNDA AREA
Kusmunda OC
i Well water of Kusmunda Chunchuni colony 1-2
ii Gevra Basti well water from Lakeshwar Singh's House 3-4
iii Colony drinking water Vikashnagar (Becon School) 5-6
Total Number Of Samples 3
TEST & SAMPLING REPORT OF (DRINKING WATER)
Unique Report No. TC-740122009702 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Indar Kumar Date of 01-09-2022 Sample ID 12500
Sampling
Sampling Well water of Kusmunda Chunchuni Sampling Plan Monthly Sampling CMPDI/BSP/LSOP
Location colony Kusmunda OC Method
Sample APPROPRIATE Date of Receipt 02-09-2022 Date of Analysis From 02-09-2022 To 06-10-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 1 of 6
TEST & SAMPLING REPORT OF (DRINKING WATER)
Unique Report No. 9702 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Indar Kumar Date of 01-09-2022 Sample ID 12500
Sampling
Sampling Well water of Kusmunda Chunchuni Sampling Plan Monthly Sampling CMPDI/BSP/LSOP
Location colony Kusmunda OC Method
Sample APPROPRIATE Date of Receipt 02-09-2022 Date of Analysis From 02-09-2022 To 06-10-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 2 of 6
TEST & SAMPLING REPORT OF (DRINKING WATER)
Unique Report No. TC-740122009687 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Indar Kumar Date of 01-09-2022 Sample ID 12499
Sampling
Sampling Gevra Basti well water from Sampling Plan Monthly Sampling CMPDI/BSP/LSOP
Location Lakeshwar Singhs House Method
Kusmunda OC
Sample APPROPRIATE Date of Receipt 02-09-2022 Date of Analysis From 02-09-2022 To 06-10-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 3 of 6
TEST & SAMPLING REPORT OF (DRINKING WATER)
Unique Report No. 9687 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Indar Kumar Date of 01-09-2022 Sample ID 12499
Sampling
Sampling Gevra Basti well water from Sampling Plan Monthly Sampling CMPDI/BSP/LSOP
Location Lakeshwar Singhs House Method
Kusmunda OC
Sample APPROPRIATE Date of Receipt 02-09-2022 Date of Analysis From 02-09-2022 To 06-10-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 4 of 6
TEST & SAMPLING REPORT OF (DRINKING WATER)
Unique Report No. TC-740122009672 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Indar Kumar Date of 01-09-2022 Sample ID 12498
Sampling
Sampling Colony drinking water Vikashnagar Sampling Plan Monthly Sampling CMPDI/BSP/LSOP
Location (Becon School) Kusmunda OC Method
Sample APPROPRIATE Date of Receipt 02-09-2022 Date of Analysis From 02-09-2022 To 06-10-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 5 of 6
TEST & SAMPLING REPORT OF (DRINKING WATER)
Unique Report No. 9672 Report Issue Date 12-10-2022
Customer Name South Estern Coal Field Ltd Address & Contact Details SEEPAT ROAD BILASPUR
Bilaspur 7752241927
Sampling By Indar Kumar Date of 01-09-2022 Sample ID 12498
Sampling
Sampling Colony drinking water Vikashnagar Sampling Plan Monthly Sampling CMPDI/BSP/LSOP
Location (Becon School) Kusmunda OC Method
Sample APPROPRIATE Date of Receipt 02-09-2022 Date of Analysis From 02-09-2022 To 06-10-2022
Condition of Sample
Note:
* This is computer generated report and does not require signature
a. The results relate only to the item sampled and tested.
b. This report shall not be reproduced except in full without approval of the laboratory.
Page 6 of 6
WELL MONITORING DETAILS IN AND AROUND
KUSMUNDA OPENCAST PROJECT
SI.
Village Name DEC2021 MAR 2022 JUN 2022 OCT2022
No.
1 Amgaon / Bata 4.30 4.80 7.00 2.60
2 Barpali CLOSED CLOSED CLOSED CLOSED
3 Balpahri FULL FULL FULL FULL
4 Birda 2.80 4.30 5.30 0.90
5 Chandranagar / CLOSED CLOSED CLOSED CLOSED
chainpur (old jatraj)
6 Chunchuni 4.50 6.00 8.00 5.00
~v
Nodal Offic.er(Env/F)
S~smunda Area
ENVIRONMENTAL AUDIT STATEMENT
2021-22
For
KUSMUNDA OC PROJECT
Under
(KUSMUNDA AREA)
South Eastern Coalfields Limited
(A Mini Ratna Company)
1
ENVIRONMENTAL AUDIT STATEMENT (2021 – 22)
CHAPTER-I
TABLE-1.1
2
g) No. of villages/ families : 17 villages/5457 Land Owners/
9340 Families
h) (i) Mining area (in Ha.) : 788.874 Ha (As per 50 MTPA EC)
(iii)Total Leasehold Area (in : 1655.825 Ha. (as per 50 MTPA EC)
Ha.)
1.1 Brief Geology of Mine : The area of Kusmunda Open cast mine
is covered generally by soil/sub-soil and
detrimental. Upper Kusmunda seam in –
crops below a cover of 06m to 31m in
an elliptical fashion and overlies lower
Kusmunda seam sand stone parting of
65m to 75m.
1.2 Mining Method Description : The method of winning coal is by
Surface Miner in combination with Pay
Loader &Tipping Trucks and the method
of overburden removal is by
conventional Shovel & Dumper
combination.
1.3 Present Status of the mine :
1. Production Figures :
3
3. Shafts : NA
4. No. of quarries : 01
4
CHAPTER-II
FORM-V
(See rule 14)
PART-A
(i) Name and address of the mine : Kusmunda Open Cast Mine
Kusmunda Area, SECL
Post-Kusmunda Colliery,
Dist.-Korba (C.G). Pin-495454
(v) Date of the last environmental : Environmental audit statement for the
Statement Submitted financial year 20-21 has been
submitted to Member Secretary,
CECB, Raipur vide letter no. 425 dated
13/09/21 and to Regional Officer,
Integrated Regional Office, MoEF&CC,
Raipur vide letter no. 424 dated
13/09/21 respectively.
5
PART-B
PART-C
6
PART-D
HAZARDOUS WASTES
(As specified under Hazardous Wastes/ Management Handling Rule, 1989)
Total quantity
Hazardous Wastes During the previous During the current
financial year 2020-21 financial year 2021-22
From Process 1. Used Oil: 395 KL 1. Used Oil: 380 KL
From Pollution control 2. Oil & Grease skimming 2. Oil & Grease skimming
facilities residue: 0.79 KL residue: 0.80 KL
3. Waste/Residue 3. Waste/Residue containing
containing Oil filter & Oil filter & Filter materials:
Filter materials:10.52 MT 4.5 MT
Neither liquid nor solid hazardous wastes are generated during underground coal
mining.
PART-E
SOLID WASTES
Total quantity
Removal of overburden During the previous During the current
financial year 2020-21 financial year 2021-22
Total O.B. (M.Cum) 33.960 37.624
Total O.B. For back filling All OB is being used for All OB is being used for
Total O.B. disposed backfilling only. No more backfilling only. No more
External Dumps are being External Dumps are being
created (i.e, other than created (i.e, other than
the originally earmarked the originally earmarked
13 External OB Dumps) 13 External OB Dumps)
PART-F
Please specify the characterization (in terms of composition and quantum) of
hazardous as well as solid wastes and indicate disposal practice adopted for both
these categories of wastes.
Description Qty. MT / Year (21-22) Collection Method
Steel Scrap 1671 MT Collected from site, weighed and
Copper Scrap Nil then stored in covered sheds and
Aluminum Scrap Nil auctioned.
Used Oil 380 KL Collected in Barrel, stored at storage
sites under covered sheds and over
concrete platforms. Later, auctioned
to authorized recyclers.
7
PART-G
Impact of the pollution abatement measure taken on conservation of natural
resources and on the cost of production.
Pollution control measures and plantations have helped to a great extent in
conservation of natural resources like water, soil, air, flora and fauna. The financial
impact on the cost of production due to the expenditure on pollution abatement
measures is approximately Rs 11.028 per tonne (Rupees 31.87 crores is the
Environmental expenses for 2021-22) of coal produced.
---------------------------------------------------------------------------------------------------------------------
PART-H
1) Use of surface miners for coal winning & production eliminates the requirement of
drilling and blasting in coal and further need of crushing of coal in crushers.
2) All Drill machines are provided with a Dust extractor equipped with fabric filter and
wet drilling arrangement.
3) All Departmental Mobile water sprinklers for haul roads are equipped with Mist Spray
Sprinkling System.
4) Water guns are installed at coal stock yard & railway sidings to suppress fugitive
dust emission.
5) All surface approach roads to CHP and sidings are being converted from WBM to
RCC & 50% of the work has been completed in FY 2021-22. A fund of Rs 40 lakhs
has been earmarked for fixed sprinklers along the alignment of this road in Capital
Expenditure FY 2022-23. All Haul roads leading to the quarry face inside the mine
area are WBM.
6) All internal roads of the residential areas and approach roads to the mine and all
other roads which are in regular use are black topped.
7) A new overhead state-of-the-art 20,000 Te Bunker & Truck Receiving Station (CHP
Phase – I) has been commissioned from 08.02.2020. Annually 7.00 MT coal is
transported through a closed conveyor belt to nearby thermal power station.
8) Four nos. of new SILO’s with Rapid Loading System (4000 Te capacity each) along
with New Railway Siding (CHP Phase- II) has been commissioned from 24.08.2021.
This eliminates the need of loading of coal by pay loaders into rail wagons. It also
enhances the capacity of despatch of coal from Kusmunda Project (40.00 MTPA) &
further eliminates road transport of coal outside the mine to end consumers.
9) One No. of “Dust Suppression System with mist blower/fog forming long range water
sprinkler with horizontal throw of 40 mtrs(min) mounted on truck chassis of GVW-
8
25T(min)” for Kusmunda Area at a cost of Rs 47.69 Lakhs has been procured and
commissioned from 19.07.2019.
10) Supply order for one no. of additional Dust Suppression System with mist blower/fog
forming long range water sprinkler has been placed on 04.05.21. Delivery has been
delayed by the agency & it is expected to be procured and commissioned in FY 22-
23.
11) Dust Breaking arrangement & Vertical Greenery System (VGS) is operational at NK-
II Railway Siding. Work for VGS has also been awarded in Kusmunda Guest House
in FY 2021-22.
12) A Field Experiment study for “Erosion Prevention & Soil Dump Stabilization at
Overburden dumps through implementation of Vetiver system technology for
development of horticulture on restored mine sites” has been carried out at
Kusmunda OCP by IIT, Kharagpur. One Lakh Vetiver saplings were planted on a
1.00 ha site earmarked for the study in 2017-18. Growth of the saplings is
satisfactory.
13) 2 Nos. of 28 KL and 70 KL capacity water tankers with mist spray arrangements
have been additionally commissioned in last three years.
14) Dust masks are being distributed regularly to workers operating in dusty areas. No of
dust masks provided during 2021-22:45789 nos.
15) Plantation in all important areas like sites earmarked for infrastructure such CHP,
crushers, coal stock yards, ETP, workshops and road sides of the mining lease are
undertaken to increase the density of plantation. A total of 24.11 lakhs plants have
been planted till date in Kusmunda OCP including 50000 saplings planted during FY
2021-22. A total of 6.12 lakhs of plant species have been planted around Non-dump
areas in Kusmunda OCP till date.
16) Mechanical Vacuum Air cleaning machines are used for dust control in workshops.
17) All Staff are provided with LPG connections, restricting burning of coal for domestic
use. Number of LPG connections provided till date: 5070 nos.
18) Trucks are optimally loaded to prevent spillage on haul roads. It is strictly ensured
that Coal loaded trucks are covered with Tarpaulin before leaving the mine
premises.
19) In order to reduce the pollution load, high capacity equipment has been planned in
phased manner at Kusmunda OCP:
S. HEMM Population as on
HEMM Equipment & Capacity
No 01.04.2020 01.04.2021 01.04.2022
Surface Miner
01 NIL 05 10
(5 MT)
Shovel
02 04 03 03
(P&H - 10 Cum)
Shovel
03 02 01 Nil
(EKG - 5 Cum)
9
04 Shovel (BE1800E – 10 Cum) Nil 03 03
08 Dumper (BH60-60T) 32 68 86
20) Moreover, other upcoming & other associated developmental activities according
to the Kusmunda 50 MTY Project Report (Approved by CIL Board on 03/08/2013)
are as follows:-
Construction of CHP Phase-III: In-Pit Belt Conveyors:- Work progress 28%
upto 30.06.2022. This will further eliminate the need for surface transport of
coal by tippers from face to TRS & minimize road transport within the mine.
Connectivity of New Railway Siding to East-West Rail Corridor Project (Rs. 27
crores):- Work progress 10% upto 30.06.2022. This will facilitate faster
integration & movement of coal across the country.
Construction of Integrated Main Workshop Complex:- Work Progress 90%
upto 30.06.2022. This will reduce the movement of HEMM to multiple
locations & will provide a single location for undertaking pollution control
measures.
Procurement of 15 nos. of fixed mist cannon/ fogging machines for coal
stock yards & railway sidings is under process of approval.
Procurement of two no. of mechanized sweeping machines is under process
of approval.
10
Opencast project of SECL (Dipka, Gevra & Kusmunda) on deposit basis
through PWD Govt. of CG at a cost of 199.20 crores. Construction is likely
to be completed by May, 2023.
Construction of approach road for connecting ROB with Gevra- Korba Road
at Kusmunda Project of Kusmunda (Ph-I) completed at a cost of Rs 4.15
crores for direct mine entry has been completed. This will reduce the
distance travelled by trucks & will be integrated with above four laning
project of public transportation CC road being carried out by PWD
department.
Other CC Roads under construction within mine premises are:
11
Cleaning of roads is being done on regular basis. All the haul roads &
service roads are lined with drains which are also cleaned from time to
time. Separate roads have been constructed for heavy vehicle and light
vehicle movement in the mine.
Only Mine water is used and re-used for mining activities like dust suppression of
haul roads, Washing of HEMMs, CHP, quenching and plantation activities.
One Domestic Effluent Treatment Plant (DETP) of capacity 2 MLD for treating
waste water from the township is commissioned in 2001 at a cost of 222 Lakhs
and it is functioning efficiently and satisfactorily.
Regular Monitoring of Effluent Water Quality, Sewage Water Quality, River Water
Quality both before and after discharge, Drinking Water Quality, Groundwater
Quality & Quantity in bore & open wells etc is being carried out by CMPDIL,
having a NABL certified Lab & an ISO 14001 certified company, in & around
Kusmunda OCP.
An RCC Settling Tank with Sludge Drying Bed (Capacity: 540m3) for treatment
of mine discharge water for industrial use at an estimated cost of Rs 27.65 Lakhs
has also been constructed and commissioned along with newly constructed
CHP.
Kuchha/ garland drain of average dimension 4500m x 3.5m x 3.0m has been
constructed all along the periphery of the mine for channeling of run-off water
during rainy season.
Kuchha/garland drain of average dimension 2.5 m x 300 m x 2 m and 600 m x
1.5 m x 1.5 m have been constructed around coal stock yards to channel run-
off water and prevent ground water contamination from coal fines. This mine
water is directed to settling tank and used in CHP.
Old Oil & Grease Trap has been dismantled in March 2022. A new Effluent
Treatment Plant (ETP) (Estimated Cost: 40 Lakhs) of enhanced capacity for
meeting the requirement of new HEMMs, as per PR of 50 MTY, is under
construction at new integrated workshop of Kusmunda OCP. It is expected to be
12
commissioned by 31.10.2022.
Work has been awarded for construction of settling tank (1 no.) for a capacity of
454m3 (20.8mx10.15mx2.15m) during March, 2021 for settling final mine water
discharge near Workshop no.1. Work could not be started in FY 2021-22
because of hindrance of railway construction work. Separate site is under
survey.
External dumps around the river periphery have been completely stabilized with
dense plantation & have been provided with check dams, retaining walls etc. to
avoid the flow of silt into the rivers.
Rain water harvesting system is being practiced to recharge the ground with rain
water at following eight locations at present:
There are 12 Piezometers to measure the Ground water level in and around
Kusmunda OCP including 3 Nos. of newly constructed Piezometers have
additionally constructed in Padania village which lies in the dip side of the
Kusmunda OCP.
Seven nos. of automatic water level recorders with telemetry systems for
piezometers at Kusmunda OCP have been procured. One no. has been installed
at CGM office as per Ground water NOC condition.
Separate sludge collecting tanks and oil filter tanks have been constructed to
avoid ground water contamination at Workshop no.1 & 3 of Kusmunda OCP.
Display boards have been set up near these sites for prominent display of
Hazardous waste authorization.
During the FY 20-21, 9.15 MT of Hazardous waste (waste or waste containing
oil, Schedule-I, Category no.2) quantity was handed over and disposed to MP
waste Management, Pithampur for safe disposal and incineration. Around 5 MT
of waste containing oil filters have been accumulated in FY 2021-22.
A total quantity of 483 KL Used Oil (Hazardous waste, Schedule-I, Category
no.5.1) has been auctioned off during FY 21-22 from Kusmunda OCP.
13
The project authority also meets the requirement of the Drinking water in nearby
villages by supplying potable water through mobile tankers.
A suitable plan for de-siltation & deepening of about 33 no. of village tanks &
other water bodies (along with their GPS Coordinates) located within 5 kms
from the Mine Lease Boundary of Kusmunda OC Project has been prepared for
a four year period (i.e. from, FY 2022-23 to FY 2025-26) by Kusmunda Area &
duly verified by DFO, Katghora. Work has been completed in two ponds till
date.
Measures adopted under Catchment Area Treatment Plan & “Narwa garwa
ghurwa badi” Yojana of Chhattisgarh by State Forest Department will further add
to the capacity of groundwater recharge in the whole catchment area.
To control the Noise Pollution at Kusmunda Open Cast Mine the following
measures are adopted:
Stress on use blasting free technology of Surface Miner mining in coal mines.
Proper maintenance of equipment to minimize vibration;
All HEMMs are provided with noise proof cabins for operators. Extensive
plantation done on over burden dumps, which act as noise barrier between
mines area and residential area.
Thick green belts developed around residential areas, along colony roads, coal
transportation road and around the mine infrastructure, also act as noise barrier.
Employees who are exposed to higher level of noise are provided with ear plugs.
Generally blasting operation is carried out between 1 pm to 3 pm with minimum
no. of persons within the mine premises.
Vocational, Special training and On spot training is also carried out to provide
information about safety and health aspects by VTC personnel/Safety
Personnel regularly.
Noise Level Monitoring is being regularly done on a fortnightly basis & values are
below the standard limits.
---------------------------------------------------------------------------------------------------------------------
14
PART-I
Any other particulars for improving the quality of the environment.
CAAQMS is installed in front of GM(Mining) Office which gives real time data for
PM10,PM2.5,SO2,NOX,CO, Temperature, Rainfall, Atmospheric Pressure, Solar
Radiation, Relative Humidity, Wind Speed & Wind Direction.
LPG is given to 100% employees.
Energy efficient lighting is being practiced at area and project level as well. Timers
have been provided in all colonies and mines for auto start and stop to save energy.
Expenditure towards energy conservation for the FY 20-21 is 1.12 crores. For the FY
21-22 expenditure incurred is 2.18 crores.
Work has been awarded for installation of solar panels/rooftops for a quantity of 65
units at a cost of 26.43 lakhs for Kusmunda Area. Site visit has been completed and
locations have finalised at GM Office, Kusmunda Bhavan and Rescue office for
installation.
Proper maintenance of Lighting, working of AC cabins, electrical equipment etc in
HEMM helps in maintaining efficiency of their working & thus reduces energy
consumption.
The workers are adequately trained and informed regularly by experienced Doctors
about the safety and health aspect during vocational training / special training at
group VTC Kusmunda Area. And On spot training is also carried out at the working
site itself to provide information about safety and health aspects by VTC personnel
regularly.
Kusmunda Area focuses on conducting Plantation Program associated with every
celebration. Saplings of different varieties of medicinal and fruit bearing plants were
given to the students at the end of the competitions conducted in connection with
World Earth Day, World Environment Day & World Ozone Day. During 2021-22, 1100
saplings & 1200 kgs of vermin-compost have been distributed at schools, colonies as
a part of Vanmahotsav programme.
Work has been completed for pond deepening at Sarvamangla Nagar which acts as
an active ground water recharge towards the up-dip side of the mine.
A total of 1671 Metric Tonne of scraps have been auctioned off during FY 21-22 from
Kusmunda OCP.
Two SLRM centers have been constructed at Vikasnagar and Vaishalinagar for
segregation of solid waste and its disposal at residential colonies of Kusmunda Area.
Drinking water facilities (RO plants) have been provided at CGM office campus,
Project office, canteen and workshops.
Water ATMs have also been installed at Adarshnagar and Vikasnagar by mine
management.
15
Various other initiatives are taken by the firm to implement recharge measures along
with provision of safe drinking water and sanitation:
Drinking water is being supplied to different villages like Pali, Padania, Khodri,
Birda, Amgaon (Approximate cost Rs. 20 Lakhs) under Kusmunda Area
throughout the year.
One bore hole including submersible pump & Sanitation facilities / toilets for
girls & boys have been provided by SECL Kusmunda Area in 3 nos. of school
premises, namely Birda (Lat 220 16’ 51.157” N & Long 820 38’ 50.858”E)
(Cost: 9.03 Lakhs), Bhatikuda (Lat 22015’ 50.345” N & Long 820 37’ 52.307”E)
(Cost: 8.00 Lakhs) & Nawagaon (Lat 220 17’ 52.067” N & Long 820 38’
42.733”E) (Cost: 8.00 Lakhs) in FY 2019-20 & 2020-21.
One bore hole including submersible pump was provided in school at ward
No.57 at Mongrabhata and one bore hole including submersible pump has
been provided in school at ward 56 has been constructed under CSR head of
Kusmunda Area.
Financial Assistance (Rs. 171.86 Lakhs) has been provided to Distt. Collector,
Korba for construction of 1299 no. of toilets for Open defecation free (ODF) on
saturation basis at 9 no. of gram panchayats of Korba district under CSR head
of SECL Kusmunda Area.
Under the initiation of WIPS various books, sewing kits, computers have been
provided to nearby schools and regular plantation is also being carried out at schools
and several villages.
Various initiatives like Smokeless Korba, Ozone day, Environment day celebrations
and rallies are organized to help create awareness among schools and local
residents.
-----------------------------------------------------------------------------------------------------------------
*****
16
ÛÒÊ×ÎÑÒÓÛÒÌßÔ ÓÑÒ×ÌÑÎ×ÒÙ
ÎÛÐÑÎÌ
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Analyzed by Dy.Manager-Environment
Page 1 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Analyzed by Dy.Manager-Environment
Page 2 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of Issue 18.02.2022
Name of the Project Kusmunda OC Sample Reference No. 5-6
Parameter PM100 PM10 PM2.5 SO2 NO2
Industrial Zone -(G.S.R. 742(E), A-O 600 300 - 120 120
µg/m3)-24
Limit (in
Analyzed by Dy.Manager-Environment
Page 3 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of Issue 18.02.2022
Name of the Project Kusmunda OC Sample Reference No. 7-8
Analyzed by Dy.Manager-Environment
Page 4 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of Issue 18.02.2022
Name of the Project Kusmunda OC Sample Reference No. 9
Parameter PM100 PM10 PM2.5 SO2 NO2
Industrial Zone -(G.S.R. 742(E), A-O 600 300 - 120 120
µg/m3)-24
Limit (in
Analyzed by Dy.Manager-Environment
Page 5 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of Issue 18.02.2022
Name of the Project Kusmunda OC Sample Reference No. N22-N30
Station Date of
Station (Code) Station Name Value in dB(A) Value in dB(A)
category measurement
Analyzed by Dy.Manager-Environment
Page 6 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Analyzed by Dy.Manager-Environment
Page 7 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
±11.7596682 mg/I
±0.0884 at ±0.445mg/l at ±6.209 mg/l at ±1.81 mg/l at at 202.4 mg/l
Uncertainty of Measurement 4.025 24.429 mg/l 247.427 mg/l 9.94 mg/l
(at 95% C.L & K= 1.96)
6.Mine 12.01.2022
1st 10.01.2022 6.85 32 8 BDL - -
water to 27.01.2022
settling tank
Work shop 25.01.2022
2nd 24.01.2022 6.92 45 8 BDL - -
effluent. to 04.02.2022
Analyzed by Dy.Manager-Environment
Page 8 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Analyzed by Dy.Manager-Environment
Page 1 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Analyzed by Dy.Manager-Environment
Page 2 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of Issue 10.03.2022
Name of the Project Kusmunda OC Sample Reference No. 5-6
Parameter PM100 PM10 PM2.5 SO2 NO2
Industrial Zone -(G.S.R. 742(E), A-O 600 300 - 120 120
µg/m3)-24
Limit (in
Analyzed by Dy.Manager-Environment
Page 3 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of Issue 10.03.2022
Name of the Project Kusmunda OC Sample Reference No. 7-8
Analyzed by Dy.Manager-Environment
Page 4 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of Issue 10.03.2022
Name of the Project Kusmunda OC Sample Reference No. 9
Parameter PM100 PM10 PM2.5 SO2 NO2
Industrial Zone -(G.S.R. 742(E), A-O 600 300 - 120 120
µg/m3)-24
Limit (in
Analyzed by Dy.Manager-Environment
Page 5 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of Issue 10.03.2022
Name of the Project Kusmunda OC Sample Reference No. N22-N30
Station Date of
Station (Code) Station Name Value in dB(A) Value in dB(A)
category measurement
Analyzed by Dy.Manager-Environment
Page 6 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Analyzed by Dy.Manager-Environment
Page 7 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
±11.7596682 mg/I
±0.0884 at ±0.445mg/l at ±6.209 mg/l at ±1.81 mg/l at at 202.4 mg/l
Uncertainty of Measurement 4.025 24.429 mg/l 247.427 mg/l 9.94 mg/l
(at 95% C.L & K= 1.96)
Station Date of
FN Date of
Name sampling
analysis
08.02.2022 to
1st
07.02.2022 6.62 107 BDL BDL - -
4. Work 04.03.2022
shop
16.02.2022 18.02.2022 to 6.59 BDL BDL BDL - -
effluent. 2nd
04.03.2022
08.02.2022 to
5. DETP - 07.02.2022 6.50 55 16 BDL Nil BDL
1st 04.03.2022
Kusmunda.
18.02.2022 to
2nd
16.02.2022 6.53 BDL 40 BDL Nil BDL
04.03.2022
6.Mine 08.02.2022 to
1st 07.02.2022 6.69 45 8 BDL - -
water 04.03.2022
settling tank
Work shop 18.02.2022 to
2nd 16.02.2022 6.87 BDL BDL BDL - -
effluent. 04.03.2022
Analyzed by Dy.Manager-Environment
Page 8 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Analyzed by Dy.Manager-Environment
Page 1 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Analyzed by Dy.Manager-Environment
Page 2 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of Issue 01.04.2022
Name of the Project Kusmunda OC Sample Reference No. 5-6
Parameter PM100 PM10 PM2.5 SO2 NO2
Industrial Zone -(G.S.R. 742(E), A-O 600 300 - 120 120
µg/m3)-24
Limit (in
Analyzed by Dy.Manager-Environment
Page 3 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of Issue 01.04.2022
Name of the Project Kusmunda OC Sample Reference No. 7-8
Analyzed by Dy.Manager-Environment
Page 4 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of Issue 01.04.2022
Name of the Project Kusmunda OC Sample Reference No. 9
Parameter PM100 PM10 PM2.5 SO2 NO2
Industrial Zone -(G.S.R. 742(E), A-O 600 300 - 120 120
µg/m3)-24
Limit (in
Analyzed by Dy.Manager-Environment
Page 5 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of Issue 01.04.2022
Name of the Project Kusmunda OC Sample Reference No. N22-N30
Station Date of
Station (Code) Station Name Value in dB(A) Value in dB(A)
category measurement
Analyzed by Dy.Manager-Environment
Page 6 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Analyzed by Dy.Manager-Environment
Page 7 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
Environment Laboratory, Regional Institute-V,
Phone: (07815) 271646, email: rdri5.cmpdi@coalindia.in,
website: www.cmpdi.co.in
Station Date of
FN Date of
Name sampling
analysis
09.03.2022 to
1st
07.03.2022 7.98 10 16 BDL - -
4. Work 21.03.2022
shop
16.03.2022 17.03.2022 to 7.82 10 24 BDL - -
effluent. 2nd
21.03.2022
09.03.2022 to
5. DETP - 07.03.2022 7.97 24 24 BDL Nil BDL
1st 21.03.2022
Kusmunda.
17.03.2022 to
2nd
16.03.2022 8.01 17 16 BDL Nil BDL
21.03.2022
6.Mine 09.03.2022 to
1st 07.03.2022 8.03 12 24 BDL - -
water 21.03.2022
settling tank
Work shop 17.03.2022 to
2nd 16.03.2022 7.59 14 24 BDL - -
effluent. 21.03.2022
Analyzed by Dy.Manager-Environment
Page 8 of 8
Note: 1) The results above relate to the samples tested.
2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, RI-V.
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
CMPDI Complex, Songanga Colony
Environment Laboratory, Regional Institute-V
Bilaspur (C.G.)- 495 006
DRINKING WATER ANALYSIS REPORT Phone: (07752) 258485
email: hk.gour@coalindia.in; mr.singh@coalindia.in
Month January 2022 Area Kusmunda Report No. JN22KM
Customer South Eastern Coalfields Ltd (SECL), Bilaspur Date of Issue 14-02-22 11:16
Project Kusmunda OC Sample Ref. No. CMPDI/Q9/02, Date:- 03/01/2022
i Well Water of Kusmunda Chunchuni Colony Date of Sampling 3-Jan-2022
Sampling Stations
ii Gevra Basti-Well Water(Lakeshwar Singh House) Date of Sampling 3-Jan-2022
Date of Analysis 3-Jan-2022 to 05 February, 2022
Observed Values IS 10500: 2012
Uncertainty of
Permissible Limit in
Sl. Acceptable Measurement
Parameter Method of Analysis the Absence of
No. i ii Limit
Alternate Source
(at 95% Confidence Level &
(Max)* K= 1.96)
(Max)
APHA, 23rd Edition,2017, 2120. C. Spectrometric single
1 Colour, Hazen 12 2 5 15 ±1.05 Hazen at 49.86 Hazen
wavelength method
LDL: 1.0 Hazen
2 Odour IS 3025 (Part 5):1983, Physical (Qualitative) Agreeable Agreeable Agreeable Agreeable None
Phenolic compounds, mg/l APHA, 23rd Edition,2017, 5530. C, Chloroform
3
LDL: 0.001 mg/l Extraction Method BDL BDL 0.001 0.002 ±0.0204 mg/l at 0.100 mg/l
Turbidity, NTU
4
LDL: 1.0 NTU
IS 3025 (Part 10):1984, R : 2006, Nephelometric Method 5 1 1 5 ±0.855 NTU at 41.58 NTU
pH IS 3025 (Part 11):1983,
5
LDL: 4.00 R : 2012, Electrometric Method 7.05 6.98 6.5-8.5 No relaxation ±0.1272 at 7.01
Fluoride, mg/l
17
LDL: 0.1 mg/l
APHA, 23rd Edition,2017, 4500, F- D SPADNS Method 0.98 0.40 1 1.5 ±0.014 mg/l at 0.98 mg/l
Zinc, mg/l
21
LDL: 0.01 mg/l
IS 3025 ( Part 49 ) : 1994, R : 2009, AAS-Flame Method 0.1 0.5 5 15 ±0.0013 mg/l at 0.01 mg/l
Fluoride, mg/l
17
LDL: 0.1 mg/l
APHA, 23rd Edition,2017, 4500, F- D SPADNS Method 0.47 1 1.5 ±0.014 mg/l at 0.98 mg/l
Zinc, mg/l
21
LDL: 0.01 mg/l
IS 3025 ( Part 49 ) : 1994, R : 2009, AAS-Flame Method 0.01 5 15 ±0.0013 mg/l at 0.01 mg/l
Fluoride, mg/l
17
LDL: 0.1 mg/l
APHA, 23rd Edition,2017, 4500, F- D SPADNS Method 0.48 0.21 1 1.5 ±0.014 mg/l at 0.98 mg/l
Zinc, mg/l
21
LDL: 0.01 mg/l
IS 3025 ( Part 49 ) : 1994, R : 2009, AAS-Flame Method BDL 0.24 5 15 ±0.0013 mg/l at 0.01 mg/l
Fluoride, mg/l
17
LDL: 0.1 mg/l
APHA, 23rd Edition,2017, 4500, F- D SPADNS Method 0.45 1 1.5 ±0.014 mg/l at 0.98 mg/l
Zinc, mg/l
21
LDL: 0.01 mg/l
IS 3025 ( Part 49 ) : 1994, R : 2009, AAS-Flame Method 0.22 5 15 ±0.0013 mg/l at 0.01 mg/l
ENVIRONMENT DEPARTMENT
Regd.Office: Seepat Road,
Post box No.60 Bilaspur (CG) P.O.: KUSMUNDA COLLIERY
Pin:495006 Dist.: Korba (C.G.) 495454
Email: envtksm@gmail.com