TAMILNADAU GENERATION AND DISTRIBUTION CORPORATION

From To
Er. S. Daniel Dhinakaran, B.E., Assistant Executive Engineer
Assistant Engineer / Electrical Security
BAP-1/SD-II/MRT/ NCTPS - II Ennore Thermal power Station
Chennai - 120 Chennai - 57

Lr.No. AE/E/BAP-1/ MRT /NCTPS-II/F.ON/D.No /22 . Dt. .05.2022


Sir,
Sub : Elcy - NCTPS-II - MRT - Diversion of materials from ETPS to NCTPS-II on non-
returnable basis - Vehicle and staff permit - requesting - reg.
Ref : 1) Lr.No.CE/ETPS/SE/EE/PUR/AEE/MM/F. Div./D.No.92 /2022, Dt.18.05.2022
2) Lr.No. SE/ES/NCTPS-II/EA/F.ON.Sl.No.2/22, Dt.27.04.2022
*******

Kindly permit contract staff from M/s Mathuram Contractors with their vehicle, for
transporting the materials that are diverted from ETPS to NCTPS-II on non-returnable basis
vide ref cited above.

Enclosed :
1) Diversion order
2) Authorisation Letter Assistant Engineer / Electrical
BAP-1/SD-II/MRT/NCTPS - II