Labour Rate of Analsis of Tile 10 sqm

Rate of 12mm thick 50 rs Per Sft.


A For Foundation Unit Amount
Cost of Tile 10 Sqm Sqm 10.000 538.200 5382.000
Add Wastage 5% Sqm 0.500 538.200 269.100
Add For Cement : Sand (1:4) for 40mm Thick
Vol. in Cum. 0.400
Cement 2.304 300.000 691.200
Sand 512.000 1.300 665.600
White Cement For Grouting
Cement Sqm 10.000 11.500 115.000
Colour Pigment 0.100 800.000 80.000
7202.900
Add 2% For Water & Electricity Charges 144.058

Labour Rate of Tile Flooring


1st Class Mason 1.250 650 812.500
Beldar 1.250 500 625.000
Bhisti 1.250 500 625.000
Total Cost For 10 Sqm 9409.458
Add Contractor Profit 15% 10820.877
For 1 Sqm 1082.088
Roundoff 1083.000

Note
Tile Cost 50 rs. Sft
Cement 300 Rs per Bag 8640 rs. Per Cum.
Sand 1.3 Rs. Per Kg 2080 Per Cum.
White Cement 11.5 Rs per Kg
Colour Pigment 80 Rs per KG
Carpenter 650
Helper 500
Details of cost for 1 cum
1.0 Cement mortar (1 cement : 1 fine sand)
(0.7175 cum. of cement = 1.02 tonne)
Cement required for cement mortar is 71.25%
Portland Cement 1.02 MT
Fine Sand (Zone IV) 0.7125 CUM

2.0 Cement mortar 1:2 (1 cement : 2 fine sand).


(0.475 cum. of cement = 0.68 tonne)
required for cement mortar is 47.50%
Portland Cement 0.68 MT
Fine Sand (Zone IV) 0.95 CUM

3 Cement mortar 1:3 (1 cement : 3 fine sand).


(0.357 cum. of cement = 0.51 tonne)
Cement required for cement mortar is 35.7%
Portland Cement 0.51 MT
Fine Sand (Zone IV) 1.07 CUM

4 Cement mortar 1:4 (1 cement : 4 fine sand).


(0.268 cum. of cement = 0.38 tonne)
Cement required for cement mortar is 26.8%
Portland Cement 0.38 MT
Fine Sand (Zone IV) 1.07 CUM

5 Cement mortar 1:5 (1 cement : 5 fine sand).


(0.214 cum. of cement = 0.31 tonne)
Cement required for cement mortar is 21.4%
Portland Cement 0.31 MT
Fine Sand (Zone IV) 1.07 CUM

6 Cement mortar 1:6 (1 cement : 6 fine sand).


(0.178 cum. of cement = 0.25 tonne)
Cement required for cement mortar is 17.8%
Portland Cement 0.25 MT
Fine Sand (Zone IV) 1.07 CUM
FOR 1CUM OF MORTAR
Ratio (1:1)
Portland Cement (CUM) 0.718
Portland Cement (MT) 1.020
Fine Sand (Zone IV) (CUM) 0.713
FOR 1CUM OF MORTAR
(1:2) (1:3) (1:4) (1:5) (1:6)
0.475 0.357 0.268 0.214 0.178
0.680 0.510 0.380 0.310 0.250
0.950 1.070 1.070 1.070 1.070