Performance, Quality and System Management Directorate

Summary of Foreign Contractors' Performance Evaluation


Reporting Period End of February 2023
Reporting Period 28-Feb-23

Total Contract Time


Actual Aggregated Average Total
Period in 10/9 times Time Elapsed is
Mobilization Cumulative Actual Expected Expected No. of Contracts Additional Average
I. Contractor's Revised Months Contract Elapsed Beyond Pass/ Non
Contract Name Period Commenceme Progress Performance Progress Progress under Expected Expected
No. Name Contract Price (ETB) Considered for Period in Months 10/9 of the Performing
(in months) nt Date todate (%) (%) (%) (%) Consideration Progress Progress
this Evaluation (10/9*A) (C) Contract
(in %)
(A) Period

Construction Works of Menebegna -


1 CGCOC 1,091,950,078.33 4 1-Jun-17 66.81 74.23 54.02 44.78 44.78 43.34 43.34 1 - 43.34 No Pass
Fincha - Shambu

Continuation of Contract 1: Gedo-


Sinohydro
2 Menebegna (80.5km) Road Upgrading 952,077,623.28 4 11-Oct-19 40.47 44.97 40.64 70.73 70.73 60.97 60.97 0 - 60.97 No
Coorporation Limited
Project

Merewa – Somodo – Seka and


3 Somodo – Limu Junction Spur Design 2,268,391,159.90 3 16-Sep-19 48.00 53.33 41.46 21.38 48.14 No
and Build Road Project

Daye - Girja - Kibremengist /


4 Melkadesta and Meleya - Mejo Spur China Tiesiju Civil 1,555,708,167.88 4 29-Dec-20 36.00 40.00 26.01 12.86 35.85 No Not Qualified for
Road 12.40 30.76 4 3.00 33.76
Engineering Group Tendering
Jimma - Chida Road Upgrading
5 2,422,629,267.28 4 8-Mar-21 48.00 53.33 23.74 5.55 19.12 No
Project

Chebera Churchura-Gudumu &


6 2,617,457,394.03 3 28-Jun-21 36.00 40.00 20.05 10.69 23.44 No
Gudumu-Bale Road Project

Modjo - Hawassa Highway Phase


7 I:Modjo - Zeway Lot ll : Arsi Negele- 5,338,512,128.16 4 7-Mar-18 58.59 65.10 59.80 56.79 64.98 No
Hawassa

Fik-Hamero-Imi, Lot II Hamero - Imi


8 1,540,339,628.70 4 8-Nov-18 50.53 56.15 51.72 98.99 65.62 No
(81+000-216+700)

9 Ali town - Agarfa - Wabe River 2,153,060,671.98 4 1-Feb-19 44.88 49.86 48.92 99.10 81.63 No
China Construction
Mekaneyesus/Este - Simada Road Communication 77.15 62.41 7 10.13 72.54 Pass
10 Company (CCCC) 1,541,967,661.59 4 21-Feb-19 46.22 51.36 48.26 72.66 70.58 No
Project

11 Bilalo - Kersa - Arsi Negele 1,668,745,531.74 4 16-Aug-19 46.13 51.25 42.48 83.02 53.12 No

Abay River Bridge and Adjacent


12 1,551,189,441.11 4 5-Aug-19 46.13 51.25 42.84 93.18 53.80 No
Concrete Structures

Construction Works of Robe-Goro-


13 8,798,168,439.12
Sofumer-Ginir Junction Road Project

Tulu Bolo - Kela Design and Build


14 Hunan-Hunda RBC 1,317,881,750.70 4 15-Oct-17 71.87 79.85 64.50 75.26 75.26 51.09 51.09 1 - 51.09 No Pass
Road Project

15 Mota - Jaragedo Road Project 1,640,366,117.06 3 14-Jul-17 59.57 66.19 67.56 73.55 100.00 Yes

Mintamir - Metehbila - Metehara


16 Zhongmei Engineering 1,096,639,115.40 3 18-Oct-17 67.43 74.92 64.41 69.99 56.10 No Not qualified for
Road Project 34.12 35.69 2 - 35.69
Ltd. tendering
Mehal Meda - Gisherabiel - Mekoy -
17 Milamile; Lot 1 : Mehal Meda - Tor 1,781,238,954.95 4 3-Jul-21 36.00 40.00 19.89 12.03 23.12 No
Mesaya

Page 1
Performance, Quality and System Management Directorate
Summary of Foreign Contractors' Performance Evaluation
Reporting Period End of February 2023
Reporting Period 28-Feb-23

Total Contract Time


Actual Aggregated Average Total
Period in 10/9 times Time Elapsed is
Mobilization Cumulative Actual Expected Expected No. of Contracts Additional Average
I. Contractor's Revised Months Contract Elapsed Beyond Pass/ Non
Contract Name Period Commenceme Progress Performance Progress Progress under Expected Expected
No. Name Contract Price (ETB) Considered for Period in Months 10/9 of the Performing
(in months) nt Date todate (%) (%) (%) (%) Consideration Progress Progress
this Evaluation (10/9*A) (C) Contract
(in %)
(A) Period

Sodo - Tercha Road Upgrading Project


18 1,805,510,307.00 4 2-Jun-15 84.63 94.03 92.98 81.57 83.67 No
Contract 2: Omo River-Tercha

19 Sodo - Dinke 1,054,003,610.30 4 14-May-18 58.52 65.02 57.57 84.42 58.58 No

Tercha – Weldehane – Omonada


20 Junction Road Project, Contract I: 2,450,000,000.00 4 10-Mar-20 54.00 60.00 35.67 16.11 30.58 No
Tercha – Weldehane – Werebo

Tercha – Weldehane – Omonada


21 Junction Road Project, Contract-II: 1,450,000,000.00 4 27-Feb-20 48.00 53.33 36.07 16.58 38.37 No
Werebo – Gona – Omonada Junction th
China Railway 7 Not Qualified for
38.42 46.39 7 10.13 56.51
Group (CRSG) Tendering
Gode – Kelafo – Ferfer Design and
22 Build Road Project, Contract 1: Gode 1,530,000,000.00 6 17-Mar-20 42.00 46.67 35.44 46.44 46.41 No
– Kelafo
Gambella - Abobo - Goge-Dima Road
23 project; Lot II Pungido - Gog - Gilo 1,342,000,000.00 4 10-Jul-20 36.00 40.00 31.66 61.19 49.51 No
River-km 72
Shashemene - Alaba Design and Build
24 2,900,000,000.00 4 13-Jan-21 36.00 40.00 25.51 9.83 34.65 No
Road Project
Dembidolo - Mughi - Dola - Gambela,

25 Lot 1: Dembidolo - Mughi - Dola 1,600,000,000.00 6 1-Dec-20 42.00 46.67 26.93 0.00 29.24 No

Design and Build Road Project


26 Gashena - Bilbala 1,722,784,493.09 3 12-Feb-14 92.45 102.72 89.62 96.57 57.34 No
China Railway 3rd
27 Muketuri - Kokebmesk 802,613,689.29 3 23-May-17 71.21 79.12 69.27 83.76 79.45 57.63 56.75 3 2.00 58.75 No Pass
Group (CRTG)
28 Iteya - Robe 1,423,913,338.81 4 7-Nov-17 67.20 74.67 63.75 56.30 55.53 No

Ethiopia - Djibouti Transport


JMC Project (India) Not Qualified for
29 Corridor Project, Phase I: Adama - 6,688,456,565.74 4 10-Jul-21 54.00 60.00 19.66 7.87 7.87 10.12 10.12 1 - 10.12 No
Ltd. Tendering
Km 60 Expressway

Ethiopia - Djibouti Transport


Longjian Road & Not Qualified for
30 Corridor Project, Phase I: Adama - 6,688,456,565.74 4 10-Jul-21 54.00 60.00 19.66 7.87 7.87 10.12 10.12 1 - 10.12 No
Bridge Tendering
Km 60 Expressway

China First Highway


31 Bilbala - Sekota 1,947,702,042.61 3 12-Jun-15 77.62 86.25 84.66 91.03 91.03 81.75 81.75 1 - 81.75 No Pass
Eng. Co. Ltd.

Albereketi - Gelemso-Mechara,
32 1,037,532,714.98 4 25-May-15 77.42 86.03 93.24 80.49 100.00 Yes
Contract 1 : Albereketi - Gelemso
Not Qualified for
Al Asab 76.92 100.00 2 - 100.00
Albereketi - Gelemso - Mechara, Tendering
33 Contract 2 : Gelemso - Mechara - 998,043,132.31 4 16-Nov-15 74.20 82.45 87.48 73.20 100.00 Yes
Micheta
Aykel - Zufan - Angereb, Lot II: Km
34 1,473,670,095.45 4 20-Jun-17 68.55 76.16 68.35 70.72 59.75 No
69+000 - Angereb
35 Daye - Chiri - Nansebo 1,723,608,314.49 3 27-Sep-17 73.41 81.57 65.10 75.64 50.14 No

Yaso - Gelasa - Dibate; Lot 1: Yaso - China Wu Yi 46.94 40.36 3 2.00 42.36 Pass
36 3,283,694,543.90 4 0.00 - No
Km 100 Road Project

Yaso - Gelaso - Dibate - Chagni; Lot 2


37 2,706,318,636.38 4 4-Dec-20 48.00 53.33 26.83 15.72 23.56 No
: Km 100 - Dibate - Chagni Page 2
Performance, Quality and System Management Directorate
Summary of Foreign Contractors' Performance Evaluation
Reporting Period End of February 2023
Reporting Period 28-Feb-23

Total Contract Time


Actual Aggregated Average Total
Period in 10/9 times Time Elapsed is
Mobilization Cumulative Actual Expected Expected No. of Contracts Additional Average
I. Contractor's Revised Months Contract Elapsed Beyond Pass/ Non
Contract Name Period Commenceme Progress Performance Progress Progress under Expected Expected
No. Name Contract Price (ETB) Considered for Period in Months 10/9 of the Performing
(in months) nt Date todate (%) (%) (%) (%) Consideration Progress Progress
this Evaluation (10/9*A) (C) Contract
(in %)
(A) Period

Abobo - Meti; (Contract 2: Kubito


38 1,621,434,669.77 4 13-Nov-17 61.55 68.38 63.55 56.83 67.82 No
Mazoria - Meti-km 76) China Gezhouba Group Not Qualified for
51.45 62.05 2 - 62.05
Company Limited Tendering
39 Tepi - Mizan Road Project 1,276,922,787.69 4 26-Jan-18 65.06 72.29 61.12 44.62 54.72 No

Gambela - Abobo - Gog -Dima;


40 (Contract 1: Gambela -Abobo- 1,310,919,269.00 3 16-Oct-17 78.02 86.68 64.47 64.24 44.90 No
Pugnido)
st
Not Qualified for
Jimma - Agaro Dedesa River Road China Railway 21 44.49 47.26 3 2.00 49.26
41 Bureau Group Co., Ltd 1,386,413,235.18 4 1-Jan-19 54.44 60.49 49.94 46.16 52.80 No Tendering
Upgrading project
Construction Works of Shishinda –
42 1,556,573,045.57 4 8-Oct-18 64.34 71.49 52.73 26.38 44.31 No
Tepi Road Project

Jiangxi Water and


Gambela -Abobo - Gog -Dima;
Hydropower
43 (Contract 1: Gambela -Abobo- 1,310,919,269.00 3 16-Oct-17 78.02 86.68 64.47 64.24 64.24 44.90 44.90 1 - 44.90 No Pass
Construction Co., Ltd.
Pugnido)
(JWHC)

Modjo - Hawassa Highway project


SBI International
44 Phase II: Zeway - Hawassa Lot 1: 3,308,243,094.13 4 23-Feb-18 67.40 74.89 60.20 55.73 55.73 50.71 50.71 1 - 50.71 No Pass
Holding AG
Zeway - Arsi Negele (57.1km)

Not Qualified for


45 Tercha-Chida Investroy Proekt LLC 1,076,472,453.67 3 8-Sep-17 56.45 62.72 65.72 36.61 36.61 100.00 100.00 0 - 100.00 Yes
Tendering

Jigjiga - Tulu - Lowwanja - Dul'ad -


46 1,551,507,344.53 4 27-Jun-19 52.87 58.74 44.12 62.76 45.61 No
Samekab - Harmukale Junction

Dire Dawa - Shinile and Dire Dawa


47 By-Pass Design and Build Road 1,318,064,901.10 4 19-Oct-20 36.00 40.00 28.34 33.25 41.49 No
Project
China Civil
Arsi Robe - Agarfa - Ali; Lot 2: Arsi Engineering Not Qualified for
17.13 19.17 5 4.50 23.67
Robe - Wabe River Bridge; Terta - Construction Company Tendering
48 (CCECC) 4,158,806,181.69 4 12-Sep-21 48.00 53.33 17.56 8.06 10.24 No
Jawe & Gado - Jawe Approaches
Road Projects

Kessa – Gimjabet – Azena – Ambela


49 2,200,961,348.65 3 18-Nov-21 36.00 40.00 15.35 7.14 14.43 No
Road Project

50 Lalibela - Kulmesk - Muja 1,888,292,297.10 4 21-Feb-22 39.91 44.35 12.23 0.00 7.08 No

51 Dabark - Zarima 2,412,000,000.00 4 1-Jan-19 48.00 53.33 49.94 24.76 69.70 No


Bejing Urban
Not qualified for
52 Dinke - Sawla Construction Group 1,062,134,906.29 4 16-Jan-19 48.00 53.33 49.45 56.24 54.03 67.23 61.17 2 - 61.17 No
tendering
Ltd.
53 Morka - Gircha - Chencha 1,928,084,952.42 4 13-Mar-19 48.82 54.25 47.61 52.82 57.83 No

Gore - Masha - Tepi Road Upgrading Hyundai Development Not Qualified for
54 4,468,211,740.75 4 1-Jan-19 62.83 69.81 49.94 40.34 40.34 42.15 42.15 1 - 42.15 No
Project Company Tendering

Tenta Junction-Wegeltena-Kurba
55 1,873,489,476.53 4 1-Apr-19 36.00 40.00 28.01 38.69 40.69 No
(31+500-110+740) Hebei Contruction Not Qualified for
44.90 59.28 1 - 59.28
Group Co. Ltd. Tendering
Adiale – Girawa Design and Build
56 1,436,300,000.00 4 9-Mar-20 36.00 40.00 35.70 44.90 59.28 No
Road Project Page 3
Performance, Quality and System Management Directorate
Summary of Foreign Contractors' Performance Evaluation
Reporting Period End of February 2023
Reporting Period 28-Feb-23

Total Contract Time


Actual Aggregated Average Total
Period in 10/9 times Time Elapsed is
Mobilization Cumulative Actual Expected Expected No. of Contracts Additional Average
I. Contractor's Revised Months Contract Elapsed Beyond Pass/ Non
Contract Name Period Commenceme Progress Performance Progress Progress under Expected Expected
No. Name Contract Price (ETB) Considered for Period in Months 10/9 of the Performing
(in months) nt Date todate (%) (%) (%) (%) Consideration Progress Progress
this Evaluation (10/9*A) (C) Contract
(in %)
(A) Period

Zhejiang Bayong
Lare - New Jinkawo - Ninighang Not Qualified for
57 Highway Engineering 1,420,584,397.57 4 2-May-19 71.28 79.20 45.96 27.67 27.67 29.49 29.49 1 - 29.49 No
Road Project Tendering
Co. Ltd.
Mesle/Musle-Kore/Kori-Ture Road
58 Project; Contract I: Mesle/Musle Km 1,513,594,498.55 4 11-Feb-19 46.88 52.09 48.59 27.68 68.75 No
84+200
China State
Mesle/Musle-Kore/Kori-Ture Road
Construction Not Qualified for
59 Project; Contract II: Km 84+200- 1,333,044,610.39 4 11-Feb-19 49.84 55.38 48.59 27.46 30.32 57.82 57.83 3 2.00 59.83 No
Engineering Corp. Ltd. Tendering
Teru(km 156+589)
(CSCEC)

Muketuri Alem Ketema Road Project,


60 1,616,065,592.00 4 19-Sep-19 48.23 53.59 41.36 35.14 47.61 No
Lot 2: Kokeb Mesk – Alem Ketema

Construction Works of Hamusit – Estie Ningxia


61 Road Upgrading Project Communications 1,395,881,640.48 4 14-Feb-20 49.12 54.58 36.49 39.37 39.37 37.64 37.64 1 - 37.64 No Pass
Construction Co.‚ Ltd.

Construction Works of Fisiha Genet –


Kele – Segen – Gebelbano; Lot 2: China Railway 14th Not Qualified for
62 Bureau Group Co., 1,800,000,000.00 4 29-May-20 36.00 40.00 33.04 6.64 6.64 52.85 52.85 1 - 52.85 No
Chulese – Soyama – km 79+500 Tendering
Ltd.
Design and Build Road Project

Jiangxi the 2nd Not Qualified for


63 Gimba - Tenta Road Project 2,185,228,256.12 4 9-Oct-20 36.00 40.00 9.70 5.00 5.00 5.70 5.70 1 - 5.70 No
Construction Co., LTD Tendering
Mellodoni Junction – Manda – Bure
64 2,085,985,162.60 4 16-Oct-20 44.52 49.46 28.44 17.47 29.08 No
Road Project Shandong Luqiao Not Qualified for
17.47 29.08 1 - 29.08
Group Co., LTD Tendering
65 Shambu - Agamsa Road Project 2,080,273,817.86 4 1-Jun-21 42.00 46.67 20.94 0.00 19.41 No

Nekempt - Bure; Lot 1 : Nekemte –


66 Chongqing 1,600,000,000.00 4 10-Dec-20 36.00 40.00 26.63 4.21 37.36 No
Anger Guntin – Andhode Section
International
35.37 20.55 1 - 20.55 Pass
Construction Group
Nekempt - Bure; Lot 3: Agamsa – Co. (CICO)
67 2,042,000,000.00 4 10-Dec-20 51.68 57.42 26.63 35.37 20.55 No
Bure Section (84.56km)
Durbete – Kunzila; Lot 1; Durbete -
68 2,655,040,000.00 4 12-Aug-21 42.05 46.72 18.58 7.64 15.48 No
Km 136
Zhejiang
69 Dolosebro - Jara - Shekhussen 1,592,270,000.00 4 1-Oct-21 42.00 46.67 16.93 10.51 12.82 No
Communications Not Qualified for
7.69 15.23 3 2.00 17.23
Construction Group Tendering
Durbete - Kunzila - Gelago - Metema; Co., Ltd.
70 Lot 3: Km 170 - Metema (Gelago - 2,719,264,301.40 4 26-Jul-21 42.05 46.72 19.13 6.09 16.40 No
Genddewuha )

DOGUSAN INSAAT
Gode-Kelafo - Ferfer Lot 2: Kelafo - Not Qualified for
71 TIC. A.S in JV with 2,497,881,730.00 4 24-Aug-21 42.00 46.67 18.18 0.00 - 14.87 14.87 1 - 14.87 No
Ferfer Tendering
Rabah and Sons P.L.C

Not Qualified for


72 Robe - Seru UNIMPRESA 2,291,343,381.66 4 26-Sep-22 36.00 40.00 5.10 0.36 0.36 1.10 1.10 1 - 1.10 No
Tendering

1 2
Formula to
Category of Contract Period be used Contractors who failed to complete projects after one ninth of the contract
First (1/3)rd 8(t1) period elapsed beyond the Contract period will be Disqualified
Second(1/3)rd 8+23(t2)
last (1/3)rd 31+29(t3) Page 4
Beyond Contract period 60+40(t4)