No. Sent Date Package No. Discipline Title
(Y or N)
1 12/29/2022 Hydrocarbon N EL
2 12/29/2022 Hydrocarbon N EL
3 12/29/2022 Hydrocarbon N EL
4 12/29/2022 Hydrocarbon N EL
5 12/30/2022 Hydrocarbon N EL
6 12/30/2022 Hydrocarbon N EL
7 12/30/2022 Hydrocarbon N EL
8 12/30/2022 Hydrocarbon N X
9 12/30/2022 Hydrocarbon N EL
10 12/30/2022 Hydrocarbon N EL
11 12/29/2022 Hydrocarbon N EL
Non-
12 12/29/2022 Hydrocarbon N X
Non-
13 12/29/2022 Hydrocarbon N EL
PRODUCED
17 12/29/2022 WATER SGSW-1 N PIPING
&SGSW-2
PRODUCED
18 12/29/2022 WATER SGSW-1 N PIPING
&SGSW-2
PRODUCED
19 12/29/2022 WATER SGSW-1 N PIPING
&SGSW-2
25
20 12/29/2022 - I&C Instrumentation cables
(Hydrocarbon)
25
21 12/29/2022 - I&C Instrumentation cables
(Hydrocarbon)
25
23 12/29/2022 - I&C CIT
(Hydrocarbon)
Non
24 12/30/2022 - PIPING
Hydrocarbon
Non
25 12/29/2022 - PIPING
Hydrocarbon
26 12/30/2022 Hydrocarbon N EL
27 12/30/2022 Hydrocarbon N EL
28 12/30/2022 Hydrocarbon N EL
25
30 12/31/2022 N I&C LDS for sour service
(Hydrocarbon)
25
31 12/31/2022 N PIPELINE Sabkha / Sandy Length
(Hydrocarbon)
25
33 12/31/2022 N CONCRETE Rebar & Anchor Bolt Schdule
(Hydrocarbon)
25
34 12/31/2022 N PIPELINE Typical Sabkha Pad
(Hydrocarbon)
25
35 12/31/2022 N PIPING PIPING PLAN
(Hydrocarbon)
25
36 1/2/2023 N PIPING MATERIAL SELECTION
(Hydrocarbon)
25
37 1/2/2023 N PIPING MATERIAL SELECTION
(Hydrocarbon)
25
38 1/2/2023 N PIPING MATERIAL SELECTION
(Hydrocarbon)
25
39 1/2/2023 N PIPING MATERIAL SELECTION
(Hydrocarbon)
676-P-SM-707861
676-P-SM-707866
677-P-SM-707863
676-P-SM-707861 SAF-
PSM-897743
SAF-P-SM897741
SAF-P-SM897742
SAF-A-PKG-25 Non HC
- DCL# SM-856001
- ISS# SAF-J-SM-828099
- DCL# SM-856001
P&ID # 676-SM-255601-
-
003
SM-836603
No dwgs. for 480V power panel for LDS shelter in Safaniyah CPF
N N
facility. IFB say TBD during bid stage
In switch rack data sheets, no.of conductors per phase are shown
2. but in drawings main breaker is MCCB, for which two conductors N N
are not possible to connect in single phase.
1- Please confirm ,compeny will supply the bare mainline pipe for N N
(42'' SRAK, 16'' STNGT-1, STNCL-1, TNSFG-1)or external FBE.
coated pipe.
PIPING MATERIAL
2- Please SPECIFICATION
confirm ,compeny NOT PROVIDED
will supply the INT.FBEFOR ALL LINE
coated N N
CLASS
mainline pipe for 16'' STNGT-1
Feed contractor to provide all the project missing ISS which are not
included in the feed pacakge such as pressure transmitters PIT,
Pressure gauges PG, temperature elements TE, temperature
transmiters TIT,thermowell TW, Scraper detection switch XS,
N N
Corrosion coupon CC, Cossorion transmitters CE/CIT, Junction
boxes JB, LDS, remote terminal unit RTU, level transmitters LIT,
level gauges LG, H2s/LEL gas detectors, horns, beacons, and high
siren alrams.
For ZSW-1 Scarepr area Line class required to select the material N N
All power panel and lighting panels data sheets shall be provided
N N
by bid contractor for all locations of BI.
SOHEB
SOHEB
SOHEB
SOHEB
SOHEB
SOHEB
SOHEB
SOHEB
SOHEB
SOHEB
SOHEB
SOHEB
ABRAR
WASIM
WASIM
WASIM
WASIM
YOUSUF
YOUSUF
YOUSUF
YOUSUF
WASIM
WASIM
WASIM
SOHEB
SOHEB
SOHEB
YOUSUF
AZAD
AZAD
AZAD
AZAD
JEHU
JEHU
JEHU
JEHU
JEHU
JEHU
JEHU