Professional Documents
Culture Documents
Template 5days Sprint Back Log Exampl Incl, Velocity SP Vs Hous
Template 5days Sprint Back Log Exampl Incl, Velocity SP Vs Hous
Planning Sheet:
1. In "Planning Sheet" "Colum "K" you must register "No. of Team member
Available hours of work (resources) in the Sprint is calculated.
This is used to compare with the total amount of hours you allocates to a
If you over allocates / estimates too many hours of work for the period, y
2. In Column "A" register Story ID / Task ID and describe Products and Task
3. Define No. of necessary Resources for each Task in Column "C"
4. Estimate each Task using Three Times Estimation (Value A, B, C) in Colum
The estimate must be based on how many clock hours is necessary for
The Weighted Average ("M") value in column "H" and Standard Deviation
If Standard Deviation > 10% of "Weighted Average", it's recommendable
(You will get a warning in column "J")
The "Total amount of work" for each task (Column "D") is calculated auto
5. The Values of "Total amount of work" in Column "D" is tranferred to the
1
2
3
4
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Sprint
Stories / Tasks
No. of
Total Read note i cells for calculations
team
amount
member
of work Estimate effort in hours
per task
A B C M Sd
4 8 2 2 2 2 0
4 24 6 6 6 6 0
0 0 0 0 0 0
4 8 2 2 2 2 0
4 12 2 3 4 3 0.4
0 0 0 0 0 0
1 3.3 2 3.5 4 3.3 0.4
1 2 1.5 2 2.5 2 0.2
1 2.5 2 2.5 3 2.5 0.2
1 2.9 2 3 3.5 2.9 0.3
2 10.4 4 5 7 5.2 0.6
2 10.4 3 5 8 5.2 1
2 4 2 2 2 2 0
1 1 1 1 1 1 0
0 0 0 0 0 0
0 4 4 5 4.2 0.2
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
ing three time estimates (or PERT) 88.5
1
2
0
3
4
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Sprint
Stories / Tasks
90.0
88.5
80.0
74.5
70.0 70.8
62.5
60.0
Effort left
53.1
50.0
40.0
30.0
20.0
10.0
0.0
1 2 3
Days in Sprint
62.5
53.1
P
D
36.5
35.4 36.5 36.5
17.7
0.0
3 4 5 6
Days in Sprint
PLANNED
DONE
Example: Estimation a Sprint Story Point vs. Person hours
88.5
13.9