Professional Documents
Culture Documents
Internship Report
Internship Report
A PROJECT REPORT
Submitted by
CERTIFICATE
This is to certify that the project report submitted along with the project entitled
internship in Fives combustion system pvt. ltd. in has been conducted by Om
ahjoliya under my guidance in partial fulfillment for the degree of Bachelor of
Engineering in control and instrumentation department 8th Semester of Gujarat
Technological University, Ahmadabad during the academic year 2021-22.
We hereby declare that the Internship report submitted along with the Internship
entitled in fives combustion system pvt. Ltd submitted in partial fulfillment for
the degree of Bachelor of Engineering in instrumentation and control to Gujarat
Technological University, Ahmedabad, is a bonafide record of original project work
carried out by me at fives combustion system under the supervision of Hardik
Panchal (HOD & manager of C&I department) and that no part of this report
has been directly copied from any students’ reports or taken from any other source,
without providing due reference.
I would also like to express my appreciation to my colleagues and the staff at fives
combustion system for their warm welcome and assistance during my internship. It
was a pleasure to work with such a talented and supportive team.
From the moment I arrived, my colleagues were quick to introduce themselves and
make me feel welcome. They were always willing to share their knowledge and
expertise and were patient in answering my questions and helping me to understand
the company and industry.
In addition to my colleagues, the staff at the Company were always helpful and
efficient in assisting me with any needs or questions I had. I am grateful for the
opportunity to work with such a dedicated and professional team.
I am deeply grateful to Mr. Hardik Panchal as my mentors and Haresh Vala,
Mayan dholu, and Akshar Panchal as advisors during this internship, for their
invaluable advice and guidance. Their industry experience and expertise helped me
to better understand the company and the industry also allowed me to make the most
of my internship.
Throughout the internship, Mr. Hardik Panchal provided me with valuable insights
and guidance that helped me to navigate my tasks and responsibilities. They were
always available to answer my questions and provide support, and their wisdom and
expertise helped me to grow as a professional. I am thankful for their time and
support, and for sharing their valuable insights with me.
This internship report serves the purpose of recording the details of my industrial
training which was conducted in fives combustion system pvt. Ltd. Which is a big
name in combustion burner industries. This report will cover the details of my
internship in the control and instrumentation department for a duration of three
months which began from 23 January 2023 till 23 April 2016 at fives company
which is located at Vadodara.
Fives group has about 8000 employees throughout 30 countries also it is 200 years
old company.
Fives designs and supplies machines, process equipment and production lines for
various industries: steel, aerospace and special machining, aluminum, the
automotive and manufacturing industries, cement, energy, logistics and glass.
Based on a portfolio of proprietary technologies, Fives products and solutions
anticipate the needs of industrial companies in terms of profitability, performance,
quality, safety and environmental protection.
To optimize synergies and propose a more legible offer of its organization and
services, the Group is organized around three Major Activities - High Precision
Machines, Process Technologies, and Smart Automation Solutions.
Fives Combustion Systems, formerly known as Coen Bharat Limited and CBL
Combustion Systems, was founded in 1981 to answer a significant demand for
efficient industrial combustion equipment and burner systems in the country.
In 2012, Fives Combustion Systems joined the Fives group and is today the leading
actor in the cement and pelletizing industries in India. It is part of Fives’ Energy |
Combustion activity with other great names in combustion including Fives Pillared
(Mineral & Energy), Fives ITAS (Oil & Gas) and Fives North American
Combustion (Aluminum & Steel)
We have the full infrastructure to design, engineer, manufacture, supply, and
commission Pillard and North American combustion equipment and burner systems
in a wide range of solid, liquid, and gaseous fuels.
We have 4 main branches for combustion works in the world.
1) fives combustion system (India)
2) fives north America combustion (north America)
3) fives itas (Italy)
4) fives Pillard(France)
Our 3,800 m2 workshop follows the highest standards for quality and safety in
compliance with the European, North American, and Middle East markets.
It is the industry that make all industries upgrade to next level combustion process
and used to simplify control system and other combustion processes to get desire
temperature according to applications and try to get the same at minimum fuel and
energy resources. The main part of this industry is ‘good combustion’ so this word
is making this industry to must desire application of every industry.
(4) GRC low NOx burner Uses as load burner. Main aim to control
emission within limit
(5) GRC induct burner Continuous oil / gas firing HRSG burner .
(6) induct burner (duct burner ) Continuous gas firing HRSG burner .
(7) low btu burner (KFT/ bio To utilize low energy fuel for considerable
flam/scroll) energy output
(8) HGG For generating hot gas used for drying out
process also used in steel plant.
(9) kiln burner ( cement & Continuous firing burner in cement kiln and
minerals ) used in boiler.
(10)coal fired HGG(vertical) For cement plant and WHRB
(14) FNA small burners Various application like conveyor belt or level
base burning system.
(15) indurating Furnace Used for producing iron ore pellets.
Fuel gas
By-pass stack
Steam turbine generator
HRSG
Gas turbine generator
TEG FIRING
FRESH AIR FIRING (auxiliary mode)
The working process of burner starts from mode selection, first we must select
control mode from there we have to control whole bms system. User must select one
mode out of ‘bms mode , local mode dcs mode’ according to selection user can
control whole process by this location.
Then interlock check is the most important part , it’s part of bms system so we
described it farther. If all kinds of interlock are healthy then manually, we must
check leakage problem. If it’s ok, then we can press the push button of purge start.
In control of the burner system a logic system is there in that we must give the set
point of purge and all others. According to the logic purge is start. This logic and all
are part of the bms system, so we learn it in brief in farther discussions . After 5 min
purge is done and then ignition command is given by the controller, so ignitor is on
and gives pilot flame.
And then according to plc logic the ssov and other valve is open for pass the fuel to
the burner. The ignitor lights up the burner when the actual fuel meets the pilot
aflame. We can take feedback from the scanner to show whether the burner is start
or not.
After main burner light up, we can modulate the burners temperature by giving air
by blower And some other conditions according to our temperature requirement.
The terms I use in this description like purge , interlock , pilot and for combustion
there are many things that are important like logic , control system, control panels
fuel , oil and gas skids , instruments , bms system , ignitors , air blowers, scanners
engineering documents , drawings etc. These are all terms you learn in this report
after that you learn the actual processes of burner.
Mode selection :
Operators may choose from either of the three available modes (‘ local mode, Bms
mode, dcs mode’ ) and its respective interlocks will then be monitored by BMS.
Interlocks :
A device, or an arrangement of devices, in which the operation of one part or one
mechanism of the device or arrangement controls the operation of another part of
another mechanism.
Leak test :
Leak Test is carried out to ensure tightness for main line safety shut off valves. This
is carried out in two stages, one with pressurized condition (for 2nd Block Valve) and
another in zero pressure condition (for 1st Block Valve)
Purge :
A flow of air or an inert medium at a rate that will effectively remove any gaseous
or suspended combustibles and replace them with the purging medium.
Ignition :
For ignition ignitor is used it is A permanently installed device that provides proven
ignition energy to light off the main burner.
Logic System :
The decision making and translation elements of the burner management system. A
logic system provides outputs in a particular sequence in response to external inputs
and internal logic.
Fuel Trip :
The automatic shutoff of a specific fuel as the result of an interlock or operator action
The burner management system essentially is an on/off control system that permits
firing of a boiler at any load when safe conditions exist. If an unsafe condition
occurs, the BMS automatically shuts off fuel or causes the boiler to go to a safe state.
The code authority that covers practices in this area is the National Fire Protection
Association (NFPA). The published documents are the 85 series.
❖ System interlock:
It is interlock that must be always healthy like in example of car there are some
things that must be important to drive the car (like air in tire).
In burner also some things are most important for combustion and its always need
to check up weather burner is in running condition or not. So that kinds of interlocks
called system interlock. Here some interlocks are described.
• tank level should be not low.
• PHF unit any pump should be running (if there is PHF unit available).
• Burner mode selection
• Coffee pot or hoisting damper is in open position (in hgg burner).
• Fuel selection.
• Emergency stop should not be pressed.
• Instrument and automizing air pressure should not be low then given set point.
• Combustion and dilution air fan running
• Input and output check. (Not fail)
• Coffee pot or hoisting damper open position
This all interlock should be healthy in every condition of burner. If any interlock is
in unhealthy condition, it will terminate running sequence, operator has to check and
resolve it before starting sequence.