LNDCH4 Exploratory Well - Weekly Progress Report #26

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Geophysical Investigation for

Groundwater Detection and Drilling of Well at Wales, W.B.D.

WEEKLY PROGRESS REPORT No. 26


In association with
February 21, 2024– February 27, 2024

1.0 PROJECT SUMMARY

Geophysical investigation for groundwater detection and drilling of wells at Wales


Works Description
Development Zone, WBD

Employer LNDCH4

Employer’s
Mr. Bernardo Perez (Construction Manager)
Representative

Contractor C.B. & Associates Inc. (CBA) in association with H&S Water and Waste Water
Supplies and Consultancy Services

Contract Start Date June 25, 2023

Contract Completion Date December 25, 2023

Revised Completion Date February 22, 2024

Contract Duration Months (6) Months

Contract Price US$576,437

30% Mobilization Advance

Payment Schedule 50% upon completion of fieldwork

20% upon submission of the Geophysical Investigation report

Disbursement Mobilization Advance (30%) US$172,931.10

% of Pre-construction Activities Completed 100%

% of Exploratory Well Construction 58%

Page 1 of 6
Geophysical Investigation for
Groundwater Detection and Drilling of Well at Wales, W.B.D.

WEEKLY PROGRESS REPORT No. 26


In association with
February 21, 2024– February 27, 2024

2.0 PROGRESS OF WORKS

The following table summarizes the progress of works to date (February 27, 2023).

ACTIVITY % COMPLETE REMARKS DELIVERY DATE OWNER


Pre- Construction Activities 100%
Acquisition of drilling casings and screens from Screens have arrived in Guyana. To
1 100% October 31, 2023
overseas be delivered to site.
Application process is complete.
2 Application for Permits 100%
Approvals given.
Approved. October 30, 2023
3 Permit Approval 100%
Approved. October 30, 2023
4 Preparation and approval of Plans 100% Approved.
5 Offsite Preparation for Site Facilities 100% Completed.
6 On-site Preparation by Client 100% Completed. September 27, 2023
7 On-site preparation by Contractor 100% Completed. October 23, 2023 CBA/HSWWW

Exploratory Well Construction 58%


Phase 1 100%
The rig arrived in Georgetown on
8 Arrival of Drill Rig 100% CBA/HSWWW
November 20, 2023.
9 Mobilization of drilling machine to site and rig set up 100% CBA/HSWWW
10 Drill Pilot Hole to 600ft depth 100%
Sample collection activity completed,
11 Collect samples for sieve analysis 100%
laboratory testing currently ongoing.

Page 2 of 6
Geophysical Investigation for
Groundwater Detection and Drilling of Well at Wales, W.B.D.

WEEKLY PROGRESS REPORT No. 24


In association with
February 14, 2024– February 20, 2024

ACTIVITY % COMPLETE REMARKS DELIVERY DATE OWNER


The geophysical logging was
12 Conduct geophysical log 100%
completed on January 26, 2024.
13 Ream pilot hole to accommodate conductor 100%
14 Ream to accommodate actual well casing 100%
15 Sieve analysis testing and results 100%
16 Perform Definitive Well design 100%
Fabrication of adaptors and modification to well
17 100%
screens
18 Install well casings and complete well drilling 100%
Phase 2 8%
19 Backwashing of Well 50%
20 Comprehensive Development of Well 30%
21 Complete development of well 0
22 Construct well head and assembly 0
23 Test exploratory well 0
24 Water sampling and water quality testing 0
25 Obtain laboratory report 0
26 Preparation of Geophysical Investigation Report 0
27 Submission of Geophysical Investigation Report 0
28 Demobilise from Site 0

Page 3 of 6
Geophysical Investigation for
Groundwater Detection and Drilling of Well at Wales, W.B.D.

WEEKLY PROGRESS REPORT No. 26


In association with
February 21, 2024– February 27, 2024

3.0 CONSTRAINTS

On February 21, 2024, we successfully obtained water from a canal located west of the site. Our water tanker was filled,
and we initiated the process of flushing the well. However, it is important to note that the condition of the access road
leading to this canal is continuously deteriorating due to regular use by sand trucks. This degradation of the road is
particularly concerning, especially when our filled water tanker navigates through it.

Given the precarious condition of the road and the risk of potential accidents such as tanker toppling, we have taken
proactive measures to minimize the number of times the truck needs to traverse the access road. One such measure
involves recycling the water used for the flushing process as much as possible. By recycling the water, we aim to reduce
the frequency of tanker movements along the deteriorating road, thereby mitigating the associated risks and ensuring the
safety of our operations.

5.0 PLANS FOR THE COMING WEEK

The following lists the activities planned for the coming week:

1. Continuation of backwashing of well and further well development

Page 4 of 6
Geophysical Investigation for
Groundwater Detection and Drilling of Well at Wales, W.B.D.

WEEKLY PROGRESS REPORT No. 24


In association with
February 14, 2024– February 20, 2024

6.0 PROGRESS PHOTOGRAPHS

Figure 1: Installation of pipes for backwashing the well - Feb. 22, 2024

Figure 2: Preparation of area near canal by LNDCH4 where water will be sourced - Feb. 22, 2024

Page 5 of 6
Geophysical Investigation for
Groundwater Detection and Drilling of Well at Wales, W.B.D.

WEEKLY PROGRESS REPORT No. 24


In association with
February 14, 2024– February 20, 2024

Figure 3: Piping system set up to flush the well

Figure 4: Discharge from the well during the backwashing process

Page 6 of 6