Professional Documents
Culture Documents
Adr 1
Adr 1
On
1|Page
ACKNOWLEDGMENT
I would like to express my gratitude and appreciation to all those who gave me
the possibility to complete this project. Special thanks to my supervisor Ms.
Neha Bharti for giving me this golden opportunity to work on ADR project and
whose help, stimulating suggestions and encouragement helped me in all time
of fabrication process and in writing this report. I also sincerely thank her for
the time she spent in proofreading and correcting my many mistakes.
2|Page
DECLARATION
I hereby declare that my Project titled ADR is a bona- fide record of the project
work which I have submitted to School of Law and Constitutional Studies,
Shobhit University in partial fulfilment of credit requirements for the degree of
B.A.LL. B is my authentic work. This project has not been copied, duplicated or
plagiarised from any other paper, journal, document or book and has not been
submitted to any educational institute or otherwise for the award of any
certificate, diploma, degree or recognition.
3|Page
CONTENTS
1. Introduction
2. Need of the Mediation Act
3. Core provisions of the Mediation Bill
a) Scope of the mediation bill
b) Pre-litigation Mediation
c) Subject matter of disputes
d) Interim Reliefs
e) Period of Mediation
f) Enforceability of Mediated Settlement Agreements (MSA)
g) Procedure to challenge the MSA
h) Online Mediation
i) Confidentiality
j) Mediation Council of India
k) Institutional mediation
4. History of mediation act in india
a) Commercial Courts Act, 2015
b) Commercial Courts (Pre-Institution Mediation and Settlement) Rules,
2018
c) The New Delhi International Arbitration Centre Act, 2019
d) The Arbitration and Conciliation (Amendment) Act, 2019
5. Effects of mediation act on “ADR” system
a) Promotion of Mediation
b) Pre-Institution Mediation
c) Reducing Court Backlogs
d) Increased Awareness and Acceptance
e) Enhanced Credibility of Mediation
f) Establishment of Mediation Infrastructure
g) Establishment of Mediation Infrastructure
h) Continuous Development and Improvement
4|Page
1. INTRODUCTION
In December 2021, the Mediation Bill of 2021 was introduced in the Rajya
Sabha, followed by a referral to the Standing Committee on Personnel, Public
Grievances, Law & Justice. On July 13, 2022, the committee issued its 117th
Report, which included specific recommendations for the Bill. Some of these
recommendations gained approval from the Union Cabinet. Consequently,
the Mediation Bill of 2023, commonly referred to as the 'Mediation Bill,'
successfully passed both the Rajya Sabha on August 2, 2023, and the Lok
Sabha on August 7, 2023. Upon receiving Presidential assent, it will formally
become the 'Mediation Act of 2023.'
The Concept of Mediation is ancient and deeply rooted in our country. It has
been practised in the form of the Panchayat system for centuries, in which
respected elders of the village worked as mediators between the parties and
helped to resolve their disputes.
5|Page
There has been a significant demand for the introduction of a dedicated
mediation law, aimed at establishing a formal framework for the mediation
process and eliminating discrepancies found in various existing statutes, such
as the Code of Civil Procedure 1908, the Industrial Disputes Act 1947, and
the Commercial Courts Act 2015, among others. Additionally, it became
imperative to enact legislation that could effectively address both domestic
and international mediation matters. Furthermore, India signed the Singapore
Convention on Mediation ("Singapore Convention") on August 7, 2019,
which has standardized and unified rules for mediation in international
commercial disputes; however, the ratification of the Singapore Convention
is still pending.
Given the identified gaps in the existing legal framework, the proposed
Mediation Bill of 2021 seeks to regulate various aspects of mediation within
the Indian legal system.
c) The New Delhi International Arbitration Centre Act, 2019: This Act
emphasized the promotion of arbitration, mediation, and other alternative
dispute resolution mechanisms. It aimed to establish an institution for the
conduct of arbitration, mediation, and conciliation proceedings.
Furthermore, various courts across India have been actively promoting and
incorporating mediation into their dispute resolution mechanisms. Mediation
centers have been established in many states to facilitate the mediation process.
It's important to note that the landscape of mediation laws in India continues to
evolve, and there might be further developments or amendments in legislation
to further strengthen and promote the use of mediation as an effective tool for
dispute resolution in the country.
Overall, the Mediation Act and related legislative measures have significantly
influenced the ADR landscape in India by promoting mediation as an effective,
efficient, and viable alternative to traditional litigation, thereby contributing to
the swift resolution of disputes and reducing the burden on the courts.
11 | P a g e
Conclusion
The mediation principles embedded in current Acts barring a few like the
Commercial Courts Act 2015, etc have become somewhat outdated in the
context of our contemporary times. The Mediation Act, serving as a
comprehensive framework, will not only modernize these existing practices but
also establish a unified and harmonized approach, aligning them with the
demands of today. The age-old saying, "the proof of the pudding is in the
eating," underscores that the real evaluation occurs during actual
implementation. Any shortcomings or deficiencies in the Mediation Act will
become apparent only when it is applied in practice.
12 | P a g e
(PROCEEDINGS ON ADR SYSTEM)
[PROCEEDING 1]
Steel Authority Of India Limited V. Indian Council Of Arbitration
ISSUES
1. The primary issue revolved around the appointment of arbitrators. SAIL
contested the legitimacy and fairness of the process conducted by the Indian
Council of Arbitration for appointing arbitrators to resolve a dispute. This
raised questions about the adherence to the agreed-upon arbitration
procedures and the fairness of the appointment process.
2. The case have centered on whether the Indian Council of Arbitration
complied with the terms and conditions outlined in the arbitration agreement
between SAIL and ICA. The dispute might have been about the interpretation
of the agreement and whether the actions of the Indian Council of Arbitration
were in accordance with the agreed-upon arbitration mechanisms.
3. There have been arguments regarding the jurisdictional authority of the
Indian Council of Arbitration to oversee the arbitration process between
SAIL and ICA. This could include discussions about the scope of authority
granted to the arbitration body as per the arbitration agreement and relevant
legal provisions.
FACTS
1. SAIL awarded TPL, along with a Dutch company, a contract for setting up a
blast furnace at one of its steel plants.
2. The contract contained an arbitration clause for resolving any disputes
arising from it.
3. A dispute arose later, and SAIL invoked arbitration under the International
Chamber of Commerce (ICC) Rules.
4. TPL challenged the arbitral tribunal's jurisdiction, arguing that the dispute
was not international commercial arbitration due to the involvement of
SAIL, a public sector undertaking under the Indian government.
13 | P a g e
ARGUMENTS
(SAIL's Arguments)
JUDGEMENT
14 | P a g e
Section 37 of the Act, to the extent it is relevant, provides for an appeal from an
order of the Arbitral Tribunal accepting the plea referred to in sub-section (2) of
sub-section (3) of Section 16. No appeal, however, is provided, in case such a
plea is rejected. Section 5 of the Act provides that notwithstanding anything
contained in another law for the time being in force, in matter governed by Part-
I of the Act, no judicial authority shall interfere, except where so provided in the
said Part.
(2.) The following two issues of law arise for consideration in these two
petitions:-
(i) Whether the Arbitral Tribunal is mandatorily required to take a decision on
the plea referred to in sub-section (3) of the Act before it proceeds further in the
matter or it can decide such a plea at a later stage while making the arbitral
award;
(il) If the Arbitral Tribunal decides to go ahead with the arbitral proceedings,
without taking a decision on such a plea or if it rejects the said plea whether
such an order of the Tribunal can be interfered with in exercise of writ
jurisdiction under Article 226/227 of the Constitution.
(3.)In W.P.(C) No. 6328 of 2013, the petitioner before this Court, in response to
the statement of claim and also by filing a separate application under Section 16
of the Act, challenged the very initiation of arbitration proceedings on the
ground that there was no arbitration agreement between it and respondent No. 2-
Seaspray Shipping Co. Ltd. It was also pleaded in the said application that
disputes, if any, could not be classified as maritime dispute attracting
applicability of clause 60 of the agreement between the parties and the
agreement dated 04.12.2007 does not fulfill the ingredients of an arbitration
agreement, as prescribed in Section 7 of the Act. The aforesaid application,
however, was not decided by the Arbitral Tribunal which was of the view that on
the first date of hearing, the claims should be decided and adjudicated. This was
followed by three more applications before the Arbitral Tribunal seeking a
decision of the issue of jurisdiction, competence and validity of the Arbitral
Tribunal. The Arbitral Tribunal, however, decided to proceed with the matter,
without giving decision on the applications filed by the petitioners. Being
aggrieved from the order of the Tribunal dated 05.07.2013, deciding to proceed
with the matter, the petitioner is before this Court seeking quashing of the
aforesaid order, besides a direction terminating the mandate of the
Arbitral Tribunal.
15 | P a g e
[PROCEEDING 2]
Lion Engineering Consultants Vs. Respondent: State Of M.P. And
Ors.
ISSUE
Matter arising out of a dispute in the execution of works contract was referred to
Arbitrator by High Court. The arbitrator made his Award in favor of Appellant.
It was challenged under Section 34 of Act by Respondent. The Respondent
sought to amend its objections after three years which was rejected by Trial
Court. High Court had allowed said amendment. Hence, the present appeal was
filed by the Appellant.
FACTS
1. The challenge focused specifically on a delay by the State of M.P. in seeking
amendment of its objections to the arbitration award.
2. The District Court rejected the amended objections due to the delay, but the
High Court later allowed them.
3. Lion Engineering Consultants appealed the High Court's decision to the
Supreme Court, questioning the validity of allowing belated amendments
and raising broader legal issues surrounding arbitration procedures.
ARGUMENT
1. In M/s Lion Engineering Consultants v. State of Madhya Pradesh &
Ors., the respondent had filed a petition under Section 34 of the Arbitration
and Conciliation Act, 1996 (‘Arbitration Act’) against an award passed in
favour of the appellant.
2. The respondent sought to belatedly amend this petition, which was rejected
by the trial court, but was allowed by the High Court of Madhya Pradesh. The
petitioner approached the Supreme Court contending, inter alia, that the
amendment should not have been permitted as it introduced new grounds at
the stage of the petition under Section 34 of the Arbitration Act, which had
not been raised under Section 16 of the Arbitration Act before the tribunal.
3. The appellant relied on MSP Infrastructure Ltd. v. MPRDC Ltd. (‘MSP
Infrastructure’).
4. The Supreme Court overruled the MSP Infrastructure judgement to hold that
there is no bar to the plea of jurisdiction being raised by way of an objection
under Section 34 of the Arbitration Act, even if no such objection was raised
under Section 16, as both stages are independent of one another.
16 | P a g e
5. The MSP Infrastructure judgement had also held that public policy of India
means the policy of the Union i.e., central law and not State law.
6. The Supreme Court overruled the same to hold that ‘public policy of India’
refers to law in force in India, whether State law or central law.
JUDGEMENT
The court finds merit in the contentions raised on behalf of the State. The court
proceeds on the footing that the amendment being beyond limitation is not to be
allowed as the amendment is not pressed. The court does not see any bar to the
plea of jurisdiction being raised by way of an objection under Section 34 of the
Act even if no such objection was raised under Section 16.
It is not possible to accept this submission. Firstly, there is nothing to warrant
the inference that all objections to the jurisdiction of the tribunal can’t be raised
under Section 16 and that the tribunal doesn’t have the power to rule upon its
jurisdiction. Secondly, Parliament has employed a different phraseology in
clause (b) of Section 34. That phraseology being “the subject-matter of the
dispute isn’t capable of settlement by arbitration”. This phrase does not
necessarily refer to an objection to “jurisdiction” as the term is well known. It
refers to the situation where the dispute referred for arbitration, because of its
subject-matter isn’t capable of settlement by arbitration.
The newly added ground that the tribunal under the Arbitration Act, 1996 had
no jurisdiction to decide the dispute in question because the jurisdiction lay with
the tribunal under the M.P. Act of 1983, was a question which can be agitated
under sub-clause (ii) of clause (b) of sub-section (2) of Section 34 of the
Arbitration Act, 1996.
Therefore, it is contended that the amendment had been rightly allowed and it
cannot be said that what was raised was only a question which pertained to
jurisdiction and ought to have been raised under Section 16 of the Act, but in
fact, there was a question which should also be raised under Section 34 before
the Court, has been done by the respondent. Thus, the submission must be
rejected.
Furthermore, it was provided that the contention should have been raised under
the topic that the arbitral award conflicts with the public policy of India. In
other words, it was submitted that it is the public policy of India that arbitrations
should be held under the appropriate law. It was contended that unless the
arbitration was held under the State law i.e. the M.P. Act that it would be a
violation of the public policy of India.
17 | P a g e
In our considered view, the public policy of India alludes to law enforcement in
India either State law or Central law. Accordingly, we overrule the observations
to the contrary in the above paras of the judgment in MSP Infrastructure Ltd.
The impugned order is set aside.
18 | P a g e
[PROCEEDING 3 ]
R.V. Solutions Pvt. Ltd. Vs. Ajay Kumar Dixit & Ors. 2019
ISSUE
The central issue in the case of R.V. Solutions Pvt. Ltd. v. Ajay Kumar
Dixit & Ors. 2019 revolved around whether a dispute concerning allegations of
breach of employment contracts, including resignation without notice,
misappropriation of confidential information, and joining a competitor, should
be referred to arbitration as per the clauses within those contracts, or whether it
should be decided by the court directly.
FACTS
1. Three of the ex-employees had arbitration clauses in their employment
contracts mandating arbitration for contract-related disputes.
2. R.V. Solutions argued that the arbitration clause didn't apply to Rishabh
Enterprises and the claims against it.
3. The dispute centered on whether the entire case, including claims against
Rishabh Enterprises, should be referred to arbitration as per the clauses or
decided by the court.
ARGUMENT
1. R.V. Solutions alleged that the ex-employees, including Dixit, breached their
employment contracts by:
a. Resigning without proper notice or justification
b. Taking away confidential information
c. Joining a competitor company (Rishabh Enterprises)
2. R.V. Solutions sought:
a. A permanent injunction restraining the defendants from working
with any R.V. Solutions employee or using confidential
information.
b. Damages of Rs. 1.1 crore.
4. Central Issue:
a. Whether the dispute should be referred to arbitration as per the
clause, or decided by the court.
19 | P a g e
5. Arguments for Arbitration:
a. Defendants:
i. The arbitration clause is valid and binding.
ii. The dispute arises directly from the employment contracts.
iii. Referring the case to arbitration would be faster and more
cost-effective.
b. R.V. Solutions:
i. The arbitration clause only applies to the ex-employees, not
Rishabh Enterprises.
ii. The claims against Rishabh Enterprises are independent of
the employment contracts and cannot be arbitrated.
iii. There is no commonality of subject matter between the
claims against the ex-employees and Rishabh Enterprises.
JUDGEMENT
The Delhi High Court held that a non-signatory or third party could be
subjected to Arbitration without its consent, only in exceptional cases. There
needs to be either a direct relationship to the signatory party of the Arbitration
Agreement, or commonality of the subject matter, or composite transactions in
the agreement between the parties.
20 | P a g e
[PROCEEDING 4]
Parsoli Motor Works (P) Ltd. v. BMW India P Ltd. 2018
ISSUE
The central issue in the case of Parsoli Motor Works (P) Ltd. v. BMW India P
Ltd. (2018) revolved around the termination of their dealership agreement and
whether it constituted an unfair or illegal practice by BMW India.
FACTS
1. The Competition Commission of India (CCI) initially ruled in favor of
Parsoli Motor Works, finding that BMW India had abused its dominant
position and imposed a fine.
2. BMW India appealed the decision to the National Company Law Appellate
Tribunal (NCLAT), which upheld the CCI's findings and the imposed fine.
ARGUMENT
1. Abuse of Dominant Position:
a. BMW India holds a dominant position in the Gujarat luxury car
market, giving them significant control over dealerships.
b. The abrupt termination of their dealership agreement, with only 21
days' notice, was an unfair exercise of this power.
c. Parsoli Motor Works was a successful and well-performing
dealership, contributing significantly to BMW India's sales in
Gujarat.
d. The non-renewal without any valid reason or opportunity for
improvement was clearly aimed at eliminating competition and
maintaining BMW India's market dominance.
2. Unreasonable Termination:
a. The non-exclusive agreement does not imply unlimited discretion
to terminate without due process.
b. The long-standing and successful partnership established a
legitimate expectation of continued collaboration.
c. The short notice period caused severe financial hardship and
disrupted their business operations, leaving them unprepared for
closure.
d. This constituted a breach of good faith and fair dealing expected in
such long-term business relationships.
21 | P a g e
3. Legality of Termination:
a. The lack of any documented performance issues or contractual
violations before the termination raises suspicion about BMW
India's motives.
b. Alleged performance shortcomings, if any, were likely used as a
pretext to mask the anti-competitive intent behind the termination.
c. The burden of proof lies with BMW India to demonstrate
legitimate business reasons for not renewing the agreement.
4. Business Restructuring:
a. The claimed business restructuring plan lacked transparency and
clear criteria for dealership selection.
b. Parsoli Motor Works was not provided with any specific
explanation for their exclusion, suggesting arbitrariness and
potential bias.
c. The timing of the non-renewal coinciding with the restructuring
plan raises further doubts about its genuine nature.
JUDGEMENT
The Delhi High Court held that injunctions that cannot be granted under Section
41 of the Specific Relief Act, cannot be granted under Section 9 of Arbitration
Act, 1996 either.
22 | P a g e