Professional Documents
Culture Documents
002-Installation of Insulation of CHWP Above Ground
002-Installation of Insulation of CHWP Above Ground
PROJECT HPGRDC
EMPLOYER HPCL
PMC EIL
VKBS EIL
Signature:
Date:
INDEX
1. PURPOSE
2. MATERIAL
3. REFERENCES
4. PROCEDURE
4.1. STORAGE
4.2. PREPARATION
5. RECORDS
1. PURPOSE
2. MATERIAL
4. Calipers
5. Scissors
4. REFERENCES
5. PROCEDURE
A. STORAGE
Insulation material shall be stored in proper storage place and shall be stacked
one above other in neatly manner as per material safety data sheet.
B. PREPARTION
Before starting the works ensure the piping installation is complete and
inspection, pressure testing for the same is completed and approved to start
the insulation works.
Ensure all service clearances are available prior to start and same documents
to be attached for PMC clearance.
All work permits are needs to be obtained from the PMC and client.
All pipes shall be brushed and cleaned properly. All pipes shall be primer
coated before starting the insulation.
different sizes.
32 to 40 40
50 to 80 45
100 to 250 50
C. INSULATION APPLICATION
When the adhesive is tack dry, place the insulation on the pipe surface and
then apply pressure firmly on insulation to achieve good bonding and to avoid
air bubbles.
All valves, fittings, joints, strainers etc. shall be insulated to the same
thickness as specified for the main run of the piping.
6. RECORDS
************************