Professional Documents
Culture Documents
007-Installation of Cooling Tower
007-Installation of Cooling Tower
007-Installation of Cooling Tower
PROJECT HPGRDC
EMPLOYER HPCL
PMC EIL
VKBS EIL
Signature:
Date:
INDEX
1. PURPOSE
2. REFERENCE
3. TOOLS & EQUIPMENTS
4. METHOD
1) STORAGE
2) PREPARATION
3) SAFETY REQUIREMENTS
4) INSTALLATION METHOD
5. RECORDS
1.0 Purpose
Purpose of this method statement is to outline the method of carrying out installation of Cooling Tower.
2.0 References
Cooling Tower
Tool Box with tools
Impact drill machine
Electric drill machine
Grinding machine
Chain pulley
Mobile scaffolding
Stage platform
Hydra crane
4.0 Method
1) Storage
On arrival at site, receiving and unloading of Cooling Tower parts shall be done as per manufacturer’s
recommendation. Manufacturer’s hoisting provisions like lifting legs etc. shall be used for hoisting and
unloading. Unloading equipment like cranes, fork lift, and trolleys shall be used if required.
Joint visual inspections shall be carried out on arrival of Cooling Tower with transporter, supplier and
any physical damages shall be reported immediately to manufacturer.
Check the Cooling tower for receipt of accessories like vibration pads / isolators, motors, fills, FRP
sections for any damages.
Check the cooling tower for correct model and type on delivery to site.
2) Preparation
Check the cooling tower’s plinth size, location and height according to equipment foundation layout
drawings.
Check and verify the correctness in type, Size and quantity of vibration isolators.
Check for clearance for delivery routes of cooling towers from ground level to where the towers are to be
erected.
3) Safety Requirements
Only qualified lifting supervisor, signaller and rigger shall be in command and control the lifting
activities.
4) Installation method
Check for Cooling Tower orientation and alignment where concrete plinth dimensions provided is in
accordance with the approved shop drawing.
Mark, drill and install anchor bolts for vibration isolators to correct position
Check that size and hole positions of vibration isolators are correct.
Place Cooling Tower Base Channel onto Vibration Isolators and ensure that the orientation are as per
approved shop drawing.
Lift Cooling Tower Bottom Module onto the Base Channel and fix by Bolts / Nuts.
Lift Cooling Tower Upper Module onto the bottom module connect both modules by bolts & nuts.
Lift the fan deck and discharge cowl onto the upper module.
Connect all piping system and other necessary components as per manufacture’s recommendations.
Connect electrical supply wiring and other field control wiring system.
Cover the Cooling Tower with protective sheet. For prevention of damaged to corners especially when
Cooling Tower is located at the common material / equipment delivery route, plywood covers are ideal
for protection.
Check and adjust the level of Cooling Tower after water filling.
5.0 Records