PROPOSAL
IRM-SOW-FEED0001303-001
Page 1 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
Table of Contents
Page 2 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
1. Project Description
This Scope of Work is for the Replacement Elution Oil heater Project. The Project Owner is the Fixed
Plant Maintenance Department, located at Ban Houayxai Mine Site in Laos PDR and will be hereafter
called the “Project Owner”.
The scope contained within this document will be managed by the Infrastructure and Road
Maintenance Department on behalf of the Project Owner from start of the project until handover and
acceptance.
2. General
Without the ability to heat eluate, there can be no dore recovery from the loaded carbon. To safely
and reliably continue the gold recovery process, it is crucial that critical equipment such as the elution
oil heater, is comprehensively supported with OEM parts, technical knowledge and service visits. At
present the BHX site teams are dependent on on-site ingenuity, remote support from one distant
manufacturer and their one contracted service technician.
The proposed elution heater will come with improvements in fuel burning technology which will
reduce the diesel usage per carbon strip.
The scope of work includes design, supply of materials, fabrication, installation and transportation of
Civil, Mechanical and Electrical work for the Replacement Elution Oil heater Project includes as follows
Page 3 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
4.1.1 Engineering
- Ensure all the Civil designs meet AS Standards as per Clauses 6 and 7 and the Project
Owner’s requirements.
- Ensure all works are carried out to meet high quality outcomes and complete with Quality
Controls as per Clause 13.
- Works excluded from this Scope of Work are referenced to in Clauses 5 and 8.
4.1.2 Construction
- Ensure all construction works are conducted as per the Safety provisions in Clause 12 and
result in Zero Harm at Work
- All the materials and manpower required to complete this work will be referred to in
Clause 14 under Civil of Price Schedule.
- Works excluded from this Scope of Work are referenced to the Clauses 5 and 8.
Page 4 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
Page 5 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
Formworks
o Waterproof plywood 18mm thick, 1.2x2.4m
o Rectangular Tube 100x50x2.3mm, length 6Mtr (SS400 or ASTM, TIS)
Steel & Rebar
o Supply and install rebar DB12 SD40 x 10Mtr per length
o Supply wire rod (Bar tie 1mm)
Concrete works
o Supply and install concrete 25MPa
Accessories
o Plastic Chamfer Edge - Plain, (20x20mmx2.5m), 1 Pack = 40 Ea (Shared with slab)
o Self-Drilling Screw Washer Face Hexagon Head Zinc Yellow Plated + Neo Washer,
(Gauge-TPI x Length) 12-14 x 50mm, (250Ea / box)
o Plastic Chamfer Edge - Plain, (20x20mmx2.5m), 1 Pack = 40 Ea (Shared with slab)
o Galvanized L-bolt M24 (refer photo, D = 24mm, L = 8000mm, C = 200mm, T =
150mm) with 2 x Hex. nut and 2 x washers
4.2.1 Engineering
- Ensure all the Mechanical designs meet AS Standards as per Clauses 6 and 7 and the
Project Owner’s requirements.
- Ensure all works are carried out to meet high quality outcomes and complete with Quality
Controls as per Clause 13.
- Works excluded from this Scope of Work are referenced to in Clauses 5 and 8.
4.2.2 Construction
- Ensure all construction works are conducted as per the Safety provisions in Clause 12 and
result in Zero Harm at Work
- All the materials and manpower required to complete this work will be referred to in
Clause 14 under Mechanical of Price Schedule.
- Works excluded from this Scope of Work are referenced to the Clauses 5 and 8.
Page 6 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
2. Installation work
New Elution Oil Heater
o 3200KW THERMAL OIL HEATER with accessories, Provide by Project Owner,
equipment already onsite
3. Piping work
Piping
o DN150 (6") PIPE, SEAMLESS, ASME B36.10 Sched.40, ASTM A53, Gr.B ERW,
bevelled ends. 6000mm Lg
o DN100 (4") PIPE, SEAMLESS, ASME B36.10 Sched.40, ASTM A53, Gr.B ERW,
bevelled ends.6000mm Lg
o DN80 (3") PIPE, SEAMLESS, ASME B36.10 Sched.40, ASTM A53, Gr.B ERW,
bevelled ends.6000mm Lg
o DN50 (2") PIPE, SEAMLESS, ASME B36.10 Sched.40, ASTM A53, Gr.B ERW,
bevelled ends.6000mm Lg
o DN40 (1-1/2") PIPE, SEAMLESS, ASME B36.10 Sched.40, ASTM A53, Gr.B ERW,
bevelled ends.6000mm Lg
o DN25 (1") PIPE, SEAMLESS, ASME B36.10 Sched.80, ASTM A53, Gr.B ERW,
bevelled ends.6000mm Lg DN25 (1") PIPE, SEAMLESS, ASME B36.10 Sched.80,
ASTM A53, Gr.B ERW, bevelled ends.6000mm Lg
o DN15 (1/2") PIPE, ASME B36.10 sched.80 ASTM A53 Gr.B ERW, threaded ends to
NPT, 6m/Ea
Fitting
o REDUCER,DN150x DN100 (6" x 4"), Butt weld to ASME B16.9. ASTM A234 WPB.
o REDUCER,DN150x DN80 (6" x 3"), Butt weld to ASME B16.9. ASTM A234 WPB.
o REDUCER,DN100x DN80 (4" x 3"), Butt weld to ASME B16.9. ASTM A234 WPB.
o REDUCER,DN100x DN50 (4" x 2"), Butt weld to ASME B16.9. ASTM A234 WPB.
o REDUCER,DN80x DN40 (3" x 1 1/2"), Butt weld to ASME B16.9. ASTM A234 WPB.
o ELBOW 90DEG,DN150 (6") LR, Butt weld to ASME B16.9. ASTM A234 WPB.
o ELBOW 45DEG,DN150 (6") LR, Butt weld to ASME B16.9. ASTM A234 WPB.
o ELBOW 90DEG,DN50 (2") LR, Butt weld to ASME B16.9. ASTM A234 WPB..
o ELBOW 45DEG,DN50 (2") LR, Butt weld to ASME B16.9. ASTM A234 WPB.
o ELBOW 90DEG,DN40 (1 1/(2") LR, Butt weld to ASME B16.9. ASTM A234 WPB.
o ELBOW 90DEG,DN25 (1") ASME B16.11, 3000 PSI ASTM A105. Threaded to NPT.
Page 7 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
o ELBOW 45DEG,DN40 (1 1/2") ASME B16.11, 3000 PSI ASTM A105. Threaded to
NPT.
o ELBOW 45DEG,DN25 (1") ASME B16.11, 3000 PSI ASTM A105. Threaded to NPT.
o HALF COUPLING ,DN15 (1/2"), ASME B16.11, 3000 PSI ASTM A105. Threaded to
NPT.
o HALF COUPLING ,DN25 (1"), ASME B16.11, 3000 PSI ASTM A105. Threaded to NPT.
o HALF COUPLING ,DN40 (1 1/2"), ASME B16.11, 3000 PSI ASTM A105. Threaded to
NPT.
o UNION,DN25 (1"), ASME B16.11, 3000 PSI ASTM A105. Threaded to NPT.
o TEE,EQUAL ,DN100 (4"), ASME B16.9. ASTM A234 WPB.
o TEE,EQUAL ,DN40 (1-1/2")ASME B16.9. ASTM A234 WPB.
Flange
o DN150 (6") FLANGE,Carbon steel slip-on flanges to ASME B16.5 R.F. CL 150, ASTM
A105
o DN100 (4") FLANGE,Carbon steel slip-on flanges to ASME B16.5 R.F. CL 150, ASTM
A105
o DN80 (3") FLANGE,Carbon steel slip-on flanges to ASME B16.5 R.F. CL 150, ASTM
A105
o DN50(2") FLANGE,Carbon steel slip-on flanges to ASME B16.5 R.F. CL 150, ASTM
A105
o DN40(1-1/2") FLANGE,Carbon steel slip-on flanges to ASME B16.5 R.F. CL 150,
ASTM A106
o DN40(1-1/2") BLIND FLANGE,Carbon steel slip-on flanges to ASME B16.5 R.F. CL
150, ASTM A106
o DN25(1") FLANGE,Carbon steel slip-on flanges to ASME B16.5 R.F. CL 150, ASTM
A106
o DN15(1/2") FLANGE,Carbon steel slip-on flanges to ASME B16.5 R.F. CL 150, ASTM
A106
o DN150 (6") FLANGE, DIN EN 1092-2 PN16
o DN100 (4") FLANGE, DIN EN 1092-2 PN16
o DN80 (3") FLANGE, DIN EN 1092-2 PN16
Gasket
o DN150 (6") 1.5 mm thick, Klingersil C4430 or approved equivalent
o DN100 (4") 1.5 mm thick, Klingersil C4430 or approved equivalent
o DN80 (3") 1.5 mm thick, Klingersil C4430 or approved equivalent
o DN50 (2") 1.5 mm thick, Klingersil C4430 or approved equivalent
o DN40 (1-1/2") 1.5 mm thick, Klingersil C4430 or approved equivalent
o DN25 (1") 1.5 mm thick, Klingersil C4430 or approved equivalent
o DN15 (1/2") 1.5 mm thick, Klingersil C4430 or approved equivalent
Stud Bolts
o 3/4" (M20) x 120mm Alloy steel stud bolts ASTM A193 Gr.B7 with 1 flat,1spring
washer,2 heavy hexagon nuts ASTM A194 Br. 2H.
o 5/8" (M16) x 100mm Alloy steel stud bolts ASTM A193 Gr.B7 with 1 flat,1spring
washer,2 heavy hexagon nuts ASTM A194 Br. 2H.
Page 8 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
o 5/8" (M16) x 170mm Alloy steel stud bolts ASTM A193 Gr.B7 with 1 flat,1spring
washer,2 heavy hexagon nuts ASTM A194 Br. 2H.
o 5/8" (M16) x 90mm Alloy steel stud bolts ASTM A193 Gr.B7 with 1 flat,1spring
washer,2 heavy hexagon nuts ASTM A194 Br. 2H.
o 1/2" (M14) x 80mm Alloy steel stud bolts ASTM A193 Gr.B7 with 1 flat,1spring
washer,2 heavy hexagon nuts ASTM A194 Br. 2H.
o 1/2" (M14) x 70mm Alloy steel stud bolts ASTM A193 Gr.B7 with 1 flat,1spring
washer,2 heavy hexagon nuts ASTM A194 Br. 2H.
Valve and Flexible
o DN150 (6") STAINLESS STEEL FLEXIBLE HOSE, SF67X6, FLANGE PN16, TYPE NW
(L=620mm)
o DN150 (6") STAINLESS STEEL FLEXIBLE HOSE, SF67X3, FLANGE ANSI150, TYPE NW
(L=240mm)
o DN80 (3") CHECK VALVE, Dual Plate, Wafer Type to Suit Flanges to ASME
B16.5,CL150, Body ASTM A351 CF8M, Plates 316 Stainless Steel, 1000 kPa at 185
Deg C
o DN50 (2") CHECK VALVE, SWING, FLGD RF, CL150, CS, BOLTED BONNET, Body
ASTM A216 Gr WCB, Disc ASTM A216 Gr WCB + 13% chrome faced, Seat Ring
ASTM A105N + stellite faced, Gasket Corrugated soft iron, Max duty 1900 kPag @
80 Deg C
o DN40 (1 1/2") BALL VALVE, Flanged to ASME B16.5, CL150,Stainless steel, bolted
to body
o DN25 (1") BALL VALVE, Flanged to ASME B16.5, CL150,Stainless steel, bolted to
body
o DN150 (6") GLOBE VALVE, Flanged to ASME B16.5, CL150, R..,Stainless steel,
bolted to body, O S & Y, rising stem,316 SS trim, renewable stellite (hard facing
alloy) faced seat and plug, 1000 kPag @ 150 Deg C
o DN15 PRESSURE GAUGE RANGE 0-20 BARG., DIAL ∅4".
o VALVE,SAFETY,28-PU-020,25MM, (used existing)
Flue Pipe
o DN600 (24") PIPE, ASME B36.10 Sched.10, ASTM A53 Gr.B ERW, bevelled ends.
6000mm Lg
o DN600 (24") ELBOW, 45Degree, Butt weld to ASME B16.9. ASTM A234 WPB.
o FLUE FLANGE MS 700 O/D x 600 I/D x 10thk
o FLUE SLEAVE, I/D 560 x 6Thk x 150mm Lg SABS.719-B, Shared
Pipe Support
o BEAM,STRUCTURAL,CS,250x250x14MM,6M LG
o PLATE,METAL,1200x20MM,2400MM LG,SS400
o PLATE,SHELL O/D 615 x 635 I/D x 10Thk (used existing)
o CHANNEL,STRUCTURAL,200x80x11x7.5MM,6M LG,STEEL
o BEAM,STRUCTURAL,H SECT,STEEL,MED GALV,100x100x6x8MM,6M LG
o ELECTRODE,WELD,LB-52,3.2x350MM,CAR/20KG
Page 9 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
Painting
o HEMPATHANE TOPCOAT 55210-11150, RAL7035, Light Grey, 20 Ltr
o PAINT,55210-37240,HEMPATHANE TOPCOAT,BLUE,RAL5015,20L
o HEMPADUR QUATTRO 17634-50630, RAL3009 Oxide Red,18 Ltr
o Thinner paint, Code 08080 (use for Topcoat paint)
o Thinner paint, Code 08450 (use for HEMPADUR QUATTRO)
Accessories
o ELECTRODE, WELDING, RB 52U, 2.6x350MM
Test and Commissioning
o Punch list
o Test and Commissioning, by Project owner
4.3.1 Engineering
- Ensure all the Electrical designs meet AS Standards as per Clauses 6 and 7 and the Project
Owner’s requirements.
- Ensure all works are carried out to meet high quality outcomes and complete with Quality
Controls as per Clause 13.
- Works excluded from this Scope of Work are referenced to in Clauses 5 and 8.
4.3.2 Construction
- Ensure all construction works are conducted as per the Safety provisions in Clause 12 and
result in Zero Harm at Work
- All the materials and manpower required to complete this work will be referred to in
Clause 14 under Electrical of Price Schedule.
- Works excluded from this Scope of Work are referenced to the Clauses 5 and 8.
1. Dismantle Work
Dismantle Electrical Device
o Dismantle existing electrical cable for oil heater
o Dismantle existing electrical cable for oil motor
o Dismantle existing instrument cable
Page 10 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
Page 11 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
Page 12 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
o Crimping type copper tubular cable terminal ends-non insulated, for cable 16
mm2.- stud hole 10.5 mm., 1 Hole
o Terminal crimp pin, bootlace 1.5mm2, BLP150, Colours : Red (100Ea/Pack)
o Terminal crimp pin, bootlace 2.5mm2, BLP250, Colours : Grey (100Ea/Pack)
Cable gland
o Cable Gland M50, Nickel plated brass, for non-armoured cable, Brand Hawke with
Shround black, (for cable O.D. 34.5-43.5mm.)
o CABLE GLAND,TYPE OSNJ A2F,22.1-26MM OD CABLE,M32B,BRASS ,NP,IP67
o CABLE GLAND,TYPE OSNJ A2F,16.1-18MM OD CABLE,M25B,BRASS NP,IP67
Cable ladder
o Cable ladder type "RI" Rail In Series, Size 300Wx100Hx3000L, Rung spacing
300mm nominal, with splice plate, bolt/nut, clamp lock and Cover peaked straight
plate (HDG.)
o Cable ladder, Flat Bend 90° With Flange, Size 300Wx100H, Radius 300, with splice
plate, bolt/nut, clamp lock and Cover plate (HDG.)
o Cable ladder, Internal Riser 90° With Flange, Size 300Wx100H, Radius 300, with
splice plate, bolt/nut, clamp lock and Cover plate (HDG.)
o Cable ladder, External Riser 90° With Flange, Size 300Wx100H, Radius 300, with
splice plate, bolt/nut, clamp lock and Cover plate (HDG.)
o Hinged horizontal splice plate, Size 100H (HDG.)
o Hinged Vertical splice plate, Size 100H (HDG.)
o Z-Hold Down Clamp Model LHGZHCH100 (HDG)
o Channel (P1000-HDG) size 41x41x2.5tx6000L mm.
o Hex Head Bolt M8 x 25 mm.
o Channel Nut with spring (Spring Nut for P1000) M8
o Flat Plate Fitting (P1062) for bolt M8 (HDG)
o Ladder cover clip, size 100H (HDG.)
o Fabricate cable ladder support
Sign
o "Engraved Aluminum Tags size 100Wx150Lx2tmm, Engraved
o ( DANGER ELECTRICAL HAZARD AUTHORIZED PERSONNAL ONLY )"
o "Engraved Aluminum Tags size 100Wx150Lx2tmm, Engraved
o ( CAUTION 400 VOLTS )"
Equipment and Accessories
o Plastic cable tie 4.8Wx250L mm, Specification : Natural nylon, Service
temperature range : -10 °C to 85 °C, Color : Black, (100 Each./Pack)
o Self drilling screw pan head philips drive zinc yellow plated size 8-18x16mm. (Size
: Gauge-T.P.I. x Length) (500pcs./ Box)
o Electrical insulation tape 3M, Black (Super 33+ Vinyl Electrical Tape)
o ACS rod Threaded Rod Galvanised, M12 x 3000L mm
o Hexagon Nuts M12 with Flat Washers and Spring Washers 100 set / Box
o NUT,GANG CH,P1008+HHCSM1030,M10,COMPLETE WITH M10x30MM
SETSCREW
Page 13 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
3. Grounding System
Grounding
o Ground Cable Insulation (Green/Yellow) 1Cx120 mm2
o Copper C-clamp, Model: CCC120-120, Run main 120 tap 120-25 mm2.
o Crimping type copper tubular cable terminal ends-non insulated, for cable 120
mm2.- stud hole 13 mm., 1 Hole
o Bolt M12 x 40 304 Stainless Steel c/w 304 SS Nut, 2 x 304 SS Washer, and 304 SS
Spring Washer
o Vinyl wire end caps, for cable 120 mm2, Colours : Green
o Ground cable termination
Page 14 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
5 Work Excluded
The following work is excluded from this Scope. This work is deemed to be the responsibility of the
Project Owner. In the event that the Project Owner requires this work to be included in the Scope it
will constitute a change and will follow the change procedures.
The scope of the Project Owner for supply and install are as follows.
- Area Clearance, By Owner
- New Elution Oil heater, Provide by Owner
- De-commissioning existing oil heater and commissioning new elution oil heater, by Project
Owner
- Supply new elution heater oil pump
- EWP, Request from BHX Mobile Maintenance
- Crane 80t include driver, Request from Fixed Plant Maintenance
- Provide security during construction to protect from theft (especially cable). If security
breaches occur that result in loss of materials or equipment, replacement and/or repair
will be at the cost of the Project Owner. (need security stand by 1 month during
construction)
- No additional works will be undertaken until the required Change Notice (CN) is approved
by the relevant GM.
6 General Notes
IRM hereby quote for the complete supply of the equipment/materials as contained in Section 14 -
Schedule of rates , including the furnishing of all labour, supervision, materials, equipment, tools,
supplies and services required to execute the works.
The equipment/materials shall be supplied strictly in accordance with the documents listed herein
Schedule 1 - Applicable Documents.
Page 15 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
All CNs will require approval in accordance with the delegated authority procedure. This must be
signed and approved by the relevant persons prior to projects undertaking any extra works.
11 Templates
IRM shall submit the following documents to Project Owner within 7 days after receipt of CEA.
- Construction schedule.
- Construction drawing (IFC)
12 Safety Provision
This Scope of Works includes a provision for safety. To meet PBM standards and procedures, this
scope of work must adhere to PBM safe work procedures. IRM’s Safety department will guide all
personnel in these requirements.
IRM will carry out Safety Management planning specifically to manage this scope of work before any
works commence. IRM’s supervision and key stakeholders are to attend a Risk Assessment Workshop
held at the IRM offices before commencement of the project. The resultant risk management plan
must form part of the activities safe work procedures for this scope of work.
IRM work tasks will provide a JSA (Job Safety Analysis) for every activity before any works commence.
This includes risk management of any activity greater than 1.8 metres high and is considered to be
working at heights as per the PBM cardinal rules and procedures.
IRM’s vehicles will obtain a current BHX monthly or weekly safety inspection as required and show
the current ‘sticker’ on the windscreen after inspections from the BHX Mobile Mechanical Workshop.
IRM will utilise the BHX Clinic/emergency response team for all First aid and medical incidents.
Page 16 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
All persons working on the site will require current and valid inductions prior to starting work on the
BHX plant site.
All personnel will require to be inducted for the General induction and BHX Mining area before access.
Supervisors required will be familiar with BHX site emergency contact details, phone numbers or radio
protocol as per the inductions onsite
Page 17 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
14 Schedule of Rates
OVERALL ESTIMATED INDICATIVE COST
Page 18 of 22
Doc. No. IRM-EST-FEED0001253-001
WBS Code Discipline Type Description Material Equipment Labour Overhead Total
FEED $ - $ - $ - $ - $ -
- FEED Civil/Structure/Architectural $ - $ -
- FEED Mechanical/HVAC $ - $ -
- FEED Electrical $ - $ -
Engineering $ - $ - $ - $ - $ -
- Engineering Civil/Structure/Architectural $ - $ -
- Engineering Mechanical/HVAC $ - $ -
- Engineering Electrical $ - $ -
Handover $ - $ - $ - $ - $ -
- Handover Civil/Structure/Architectural $ - $ -
- Handover Mechanical/HVAC $ - $ -
- Handover Electrical $ - $ -
4,119.29 - - 4,119.29
Mechanical work
- 33,397.58 - 33,397.58
Electrical work
- - 32,326.19 32,326.19
Construction Support
- - - -
Total (USD) 5,121.54 47,564.48 36,396.54 89,082.55
IRM Overhead Cost (Recharge) 153.65 1,426.93 1,091.90 2,672.48
Contingency 7% 358.51 3,329.51 2,547.76 6,235.78
Grand Total (USD) 5,633.69 52,320.93 40,036.19 97,990.81
Doc. No. IRM-EST-FEED0001303-C-001
Material Cost (USD) Equipment Cost (USD) Man Hour Cost (USD)
WBS Item Description Unit
Mat Qty Unit Cost Mat Cost EQ.Qty Duration Unit Cost EQ Cost MH Qty Unit Cost MH Cost
Subtotal - Engineering $ - $ - 90 $ -
PROCUREMENT / CONSTRUCTION
1 Extend Concrete support for elution tank $ 720.92 152.0 $ 501.60
1.1 Preparation works $ - 84.0 $ 277.20
01 Setting-out area and levelling m2 5 $ - $ - 12.0 $ 3.30 $ 39.60
02 Scrabble existing concrete slab m2 3 $ - $ - 36.0 $ 3.30 $ 118.80
Drilling holes Diameter 16mm,250mm Length on existing concrete for rebar DB12
03 Hole 32 $ - $ - 36.0 $ 3.30 $ 118.80
installation
Material Cost (USD) Equipment Cost (USD) Man Hour Cost (USD)
WBS Item Description Unit
Mat Qty Unit Cost Mat Cost EQ.Qty Duration Unit Cost EQ Cost MH Qty Unit Cost MH Cost
Drilling holes Diameter 16mm,250mm Length on existing concrete for rebar DB12
03 Hole 4 $ - $ - 12.0 $ 3.30 $ 39.60
installation
Material Cost (USD) Equipment Cost (USD) Man Hour Cost (USD)
WBS Item Description Unit
Mat Qty Unit Cost Mat Cost EQ.Qty Duration Unit Cost EQ Cost MH Qty Unit Cost MH Cost
Subtotal - Comercial $ - 12 $ -
CONSTRUCTION MANAGEMENT
01 Site supervisor Hrs 48 $ - $ -
02 QA/QC Hrs 6 $ - $ -
03 Superintendent Hrs 6 $ - $ -
04 Safety officer Hrs 12 $ - $ -
05 Project Manager review and approval Hrs 6 $ - $ -
SUBTOTAL - HANDOVER $ - $ - 16 $ -
TOTAL CIVIL WORKS COSTING (USD) $ 3,267.54 $ - $ 1,854.00
IRM Overhead Cost (Recharge) $ 153.65
CONTINGENCY $ 358.51
GRAND TOTAL (USD) $ 5,633.69
Doc. No. IRM-EST-FEED0001303-M-001
Material Cost (USD) Equipment Cost (USD) Man Hour Cost (USD)
WBS Item Description Unit
Mat Qty Unit Cost Mat Cost EQ.Qty Duration Unit Cost EQ Cost MH Qty Unit Cost MH Cost
ENGINEERING & DESIGN
FEED
1 Engineer
- Project study Hrs 10 $ - $ -
- Concept drawings Hrs 50 $ - $ -
- Project scoping and estimate Hrs 10 $ - $ -
2 Project control
- Procurement Hrs 4 $ - $ -
- Scheduling/planning Hrs 4 $ - $ -
- QS/Cost Control Hrs 4 $ - $ -
- Project scoping and estimate Hrs 4 $ - $ -
3 Management
- Project scoping review and approval Hrs 2 $ - $ -
Subtotal - FEED $ - $ - 88 $ -
Engineering
01 Construction Drawings (Plan, Detail and section) Hrs 40 $ - $ -
02 Bill of quantity or Material Take off Hrs 10 $ - $ -
03 Finalize vendor drawing Hrs 0 $ - $ -
04 As built drawings Hrs 20 $ - $ -
Subtotal - Engineering $ - $ - 70 $ -
PROCUREMENT / CONSTRUCTION
1 Dismantle Work $ - 420.00 $ 3,570.00
1.1 Old Oil Heat Systems and Accessories $ - 420.0 $ 3,570.00
01 Preparation area Ea 1 $ - $ - 60.0 $ 8.50 $ 510.00
02 De-commissioning oil heater, by project owner, IRM support man-power only Ea 1 $ - $ - 60.0 $ 8.50 $ 510.00
03 Disconnect elution oil heater piping and pipe support Ea 1 $ - $ - 60.0 $ 8.50 $ 510.00
04 Remove and reinstall existing roof of oil heater Ea 1 $ - $ - 60.0 $ 8.50 $ 510.00
05 Remove and reinstall fire water pipe Ea 1 $ - $ - 30.0 $ 8.50 $ 255.00
06 Remove existing oil heater Lot 1 $ - $ - 60.0 $ 8.50 $ 510.00
07 Remove and re-install Deaerator tank Lot 1 $ - $ - 60.0 $ 8.50 $ 510.00
08 Remove existing oil pump and re-install new pump Lot 1 $ - $ - 30.0 $ 8.50 $ 255.00
Material Cost (USD) Equipment Cost (USD) Man Hour Cost (USD)
WBS Item Description Unit
Mat Qty Unit Cost Mat Cost EQ.Qty Duration Unit Cost EQ Cost MH Qty Unit Cost MH Cost
DN15 (1/2") PIPE, ASME B36.10 sched.80 ASTM A53 Gr.B ERW, threaded
07 Ea 1 $ 33.33 $ 33.33 8.0 $ 8.50 $ 68.00
ends to NPT, 6m/Ea
07 ELBOW 45DEG,DN150 (6") LR, Butt weld to ASME B16.9. ASTM A234 WPB. Ea 2 $ 25.33 $ 50.67 2.0 $ 8.50 $ 17.00
08 ELBOW 90DEG,DN50 (2") LR, Butt weld to ASME B16.9. ASTM A234 WPB.. Ea 2 $ 3.33 $ 6.67 2.0 $ 8.50 $ 17.00
09 ELBOW 45DEG,DN50 (2") LR, Butt weld to ASME B16.9. ASTM A234 WPB. Ea 6 $ 2.83 $ 17.00 6.0 $ 8.50 $ 51.00
ELBOW 90DEG,DN40 (1 1/(2") LR, Butt weld to ASME B16.9. ASTM A234
10 Ea 6 $ 2.50 $ 15.00 6.0 $ 8.50 $ 51.00
WPB.
ELBOW 90DEG,DN25 (1") ASME B16.11, 3000 PSI ASTM A105. Threaded to
11 Ea 5 $ 11.67 $ 58.33 4.0 $ 8.50 $ 34.00
NPT.
ELBOW 45DEG,DN40 (1 1/2") ASME B16.11, 3000 PSI ASTM A105.
12 Ea 6 $ 12.67 $ 76.00 4.0 $ 8.50 $ 34.00
Threaded to NPT.
ELBOW 45DEG,DN25 (1") ASME B16.11, 3000 PSI ASTM A105. Threaded to
13 Ea 3 $ 11.67 $ 35.00 6.0 $ 8.50 $ 51.00
NPT.
HALF COUPLING ,DN15 (1/2"), ASME B16.11, 3000 PSI ASTM A105.
14 Ea 2 $ 4.17 $ 8.33 2.0 $ 8.50 $ 17.00
Threaded to NPT.
HALF COUPLING ,DN25 (1"), ASME B16.11, 3000 PSI ASTM A105. Threaded
15 Ea 3 $ 10.00 $ 30.00 2.0 $ 8.50 $ 17.00
to NPT.
HALF COUPLING ,DN40 (1 1/2"), ASME B16.11, 3000 PSI ASTM A105.
16 Ea 3 $ 13.33 $ 40.00 2.0 $ 8.50 $ 17.00
Threaded to NPT.
17 UNION,DN25 (1"), ASME B16.11, 3000 PSI ASTM A105. Threaded to NPT. Ea 5 $ 14.67 $ 73.33 2.0 $ 8.50 $ 17.00
18 TEE,EQUAL ,DN100 (4"), ASME B16.9. ASTM A234 WPB. Ea 1 $ 25.00 $ 25.00 2.0 $ 8.50 $ 17.00
19 TEE,EQUAL ,DN40 (1-1/2")ASME B16.9. ASTM A234 WPB. Ea 1 $ 10.00 $ 10.00 2.0 $ 8.50 $ 17.00
Material Cost (USD) Equipment Cost (USD) Man Hour Cost (USD)
WBS Item Description Unit
Mat Qty Unit Cost Mat Cost EQ.Qty Duration Unit Cost EQ Cost MH Qty Unit Cost MH Cost
10 DN100 (4") FLANGE, DIN EN 1092-2 PN16 Ea 2 $ 25.17 $ 50.33 4.0 $ 8.50 $ 34.00
11 DN80 (3") FLANGE, DIN EN 1092-2 PN16 Ea 2 $ 18.00 $ 36.00 4.0 $ 8.50 $ 34.00
Material Cost (USD) Equipment Cost (USD) Man Hour Cost (USD)
WBS Item Description Unit
Mat Qty Unit Cost Mat Cost EQ.Qty Duration Unit Cost EQ Cost MH Qty Unit Cost MH Cost
Material Cost (USD) Equipment Cost (USD) Man Hour Cost (USD)
WBS Item Description Unit
Mat Qty Unit Cost Mat Cost EQ.Qty Duration Unit Cost EQ Cost MH Qty Unit Cost MH Cost
SUBTOTAL - HANDOVER $ - $ - 16 $ -
TOTAL MECHANICAL COSTING (USD) $ 27,474.48 $ 6,650.00 $ 13,440.00
IRM Overhead Cost (Recharge) $ 1,426.93
CONTINGENCY $ 3,329.51
GRAND TOTAL (USD) $ 52,320.93
Doc. No. IRM-EST-FEED0001303-E-001
Material Cost (USD) Equipment Cost (USD) Man Hour Cost (USD)
WBS Item Descriptions Unit
Mat Qty Unit Cost Mat Cost EQ.Qty Duration Unit Cost EQ Cost MH Qty Unit Cost MH Cost
ENGINEERING & DESIGN
FEED
1 Engineer
- Project study Hrs 5.0 $ - $ -
- Concept drawings Hrs 10.0 $ - $ -
- Project scoping and estimate Hrs 8.0 $ - $ -
2 Project control
- Procurement Hrs 2.0 $ - $ -
- Scheduling/planning Hrs 2.0 $ - $ -
- QS/Cost Control Hrs 2.0 $ - $ -
- Project scoping and estimate Hrs 2.0 $ - $ -
3 Management
- Project scoping review and approval Hrs 2.0 $ - $ -
Material Cost (USD) Equipment Cost (USD) Man Hour Cost (USD)
WBS Item Descriptions Unit
Mat Qty Unit Cost Mat Cost EQ.Qty Duration Unit Cost EQ Cost MH Qty Unit Cost MH Cost
CABLE,ELEC,C99620774011,CONTROL,0.6/1KV,20C+E,1.5MM2,COPPER,CVV
01 Mtr 200 $ 5.14 $ 1,028.00 50.0 $ 5.80 $ 290.00
INSULN,70DEG C,PVCSHEATH
CABLE,SPECIAL,P5508ESCS,INSTRUMENT,1.5MM2,8PR,INDIVIDUAL & O/A
02 Ea 200 $ 8.22 $ 1,644.00 50.0 $ 5.80 $ 290.00
SCREENED
WIRE,ELEC,3801031,FLEXIBLE,0.6/1KV,1.5MM2,BLACK,V90HTINSULN,1C,RO
03 Roll 1 $ 101.50 $ 101.50 0.0 $ 5.80 $ -
LL/100M
WIRE,ELEC,3801034,FLEXIBLE,0.6/1KV,1.5MM2,RED,V90HT
04 Roll 1 $ 76.66 $ 76.66 0.0 $ 5.80 $ -
INSULN,1C,ROLL/100M
WIRE,ELEC,TRETA8.0015.01.VT,FLEXIBLE,1.5MM2,VIOLET (RAL
05 4001),V90HT Roll 1 $ 40.36 $ 40.36 0.0 $ 5.80 $ -
SOFTINSULN,1C,ROLL/100M
WIRE,ELEC,TRETA8.0015.01.OE,FLEXIBLE,1.5MM2,ORANGE (RAL
06 2003),V90HT Roll 1 $ 39.74 $ 39.74 0.0 $ 5.80 $ -
SOFTINSULN,1C,ROLL/100M
07 Cable termination Hrs 100.0 $ 6.80 $ 680.00
Material Cost (USD) Equipment Cost (USD) Man Hour Cost (USD)
WBS Item Descriptions Unit
Mat Qty Unit Cost Mat Cost EQ.Qty Duration Unit Cost EQ Cost MH Qty Unit Cost MH Cost
Marking strip-printed for NSYTRV terminal, black marking on white background,
08 Pack 4 $ 25.00 $ 100.00 0.0 $ 5.80 $ -
printed characters 1 to 10, 10Ea/pack Model: NSYTRAB510
Marking strip-printed for NSYTRV terminal, black marking on white background,
09 Pack 4 $ 25.00 $ 100.00 0.0 $ 5.80 $ -
printed characters 11 to 20, 10Ea/pack Model: NSYTRAB520
Marking strip-printed for NSYTRV terminal, black marking on white background,
10 Pack 4 $ 25.00 $ 100.00 0.0 $ 5.80 $ -
printed characters 21 to 30, 10Ea/pack Model: NSYTRAB530
Marking strip-printed for NSYTRV terminal, black marking on white background,
11 Pack 4 $ 25.00 $ 100.00 0.0 $ 5.80 $ -
printed characters 31 to 40, 10Ea/pack Model: NSYTRAB540
Marking strip-printed for NSYTRV terminal, black marking on white background,
12 Pack 4 $ 25.00 $ 100.00 0.0 $ 5.80 $ -
printed characters 41 to 50, 10Ea/pack Model: NSYTRAB550
Material Cost (USD) Equipment Cost (USD) Man Hour Cost (USD)
WBS Item Descriptions Unit
Mat Qty Unit Cost Mat Cost EQ.Qty Duration Unit Cost EQ Cost MH Qty Unit Cost MH Cost
Cable ladder, Internal Riser 90° With Flange, Size 300Wx100H, Radius 300, with
05 Set 2 $ 75.09 $ 150.18 12.0 $ 9.80 $ 117.60
splice plate, bolt/nut, clamp lock and Cover plate (HDG.)
Cable ladder, External Riser 90° With Flange, Size 300Wx100H, Radius 300, with
06 Set 2 $ 77.69 $ 155.38 12.0 $ 10.80 $ 129.60
splice plate, bolt/nut, clamp lock and Cover plate (HDG.)
07 Hinged horizontal splice plate, Size 100H (HDG.) Ea 20 $ 6.32 $ 126.40 0.0 $ 11.80 $ -
08 Hinged Vertical splice plate, Size 100H (HDG.) Ea 20 $ 6.34 $ 126.80 0.0 $ 12.80 $ -
09 Z-Hold Down Clamp Model LHGZHCH100 (HDG) Ea 40 $ 6.33 $ 253.20 0.0 $ 13.80 $ -
10 Channel (P1000-HDG) size 41x41x2.5tx6000L mm. Ea 10 $ 45.18 $ 451.80 64.0 $ 14.80 $ 947.20
11 Hex Head Bolt M8 x 25 mm. Ea 100 $ 0.95 $ 95.00 0.0 $ 15.80 $ -
12 Channel Nut with spring (Spring Nut for P1000) M8 Ea 100 $ 1.74 $ 174.00 0.0 $ 16.80 $ -
13 Flat Plate Fitting (P1062) for bolt M8 (HDG) Ea 100 $ 2.85 $ 285.00 0.0 $ 17.80 $ -
14 Ladder cover clip, size 100H (HDG.) Ea 100 $ 1.27 $ 127.00 0.0 $ 18.80 $ -
15 Fabricate cable ladder support Lot 1 $ - $ - 100.0 $ 19.80 $ 1,980.00
Material Cost (USD) Equipment Cost (USD) Man Hour Cost (USD)
WBS Item Descriptions Unit
Mat Qty Unit Cost Mat Cost EQ.Qty Duration Unit Cost EQ Cost MH Qty Unit Cost MH Cost
02 Copper C-clamp, Model: CCC120-120, Run main 120 tap 120-25 mm2. Ea 10 $ 8.59 $ 85.90 0.0 $ 5.80 $ -
Crimping type copper tubular cable terminal ends-non insulated, for cable 120
03 Ea 20 $ 3.00 $ 60.00 0.0 $ 5.80 $ -
mm2.- stud hole 13 mm., 1 Hole
Bolt M12 x 40 304 Stainless Steel c/w 304 SS Nut, 2 x 304 SS Washer, and 304
04 Set 20 $ 3.00 $ 60.00 0.0 $ 5.80 $ -
SS Spring Washer
05 Vinyl wire end caps, for cable 120 mm2, Colours : Green Ea 20 $ 0.50 $ 10.00 0.0 $ 5.80 $ -
06 Ground cable termination Hrs $ - $ - 10.0 $ 5.80 $ 58.00
Material Cost (USD) Equipment Cost (USD) Man Hour Cost (USD)
WBS Item Descriptions Unit
Mat Qty Unit Cost Mat Cost EQ.Qty Duration Unit Cost EQ Cost MH Qty Unit Cost MH Cost
CONTINGENCY $ 2,547.76
GRAND TOTAL OF ELECTRICAL WORKS (USD) $ 40,036.19
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
MECHANICAL
1 BHX-260-06-121-002 ISOMECTRIC
2 BHX-260-00-121-002 GENERAL ARRAMGEMENT
3 BHX-260-05-122-006 ELEVATIONS
ELECTRICAL
N/A
Page 19 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
Page 20 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
APPENDICES “A”
Page 21 of 22
Phu Bia Mining Limited Scope of Work for Proposal Doc No. IRM-SOW-FEED0001303-001
Infrastructure and Road Maintenance Revision A
9 Mar 23
Page 22 of 22