IRM-SOW-FEED00014XX-001
Revision A
24 Feb 24
- Ensure all construction works are conducted as per the Safety provisions in Clause 12 and
result in Zero Harm at Work
- All the materials and manpower required to complete this work will be referred to in
Clause 14 under Mechanical of Price Schedule.
- Works excluded from this Scope of Work are referenced to the Clauses 5 and 8.
1. XXX
XXX1
o XXX
4.3.1 Engineering
- Ensure all the Electrical designs meet AS Standards as per Clauses 6 and 7 and the Project
Owner’s requirements.
- Ensure all works are carried out to meet high quality outcomes and complete with Quality
Controls as per Clause 13.
- Works excluded from this Scope of Work are referenced to in Clauses 5 and 8.
4.3.2 Construction
- Ensure all construction works are conducted as per the Safety provisions in Clause 12 and
result in Zero Harm at Work
- All the materials and manpower required to complete this work will be referred to in
Clause 14 under Electrical of Price Schedule.
- Works excluded from this Scope of Work are referenced to the Clauses 5 and 8.
1. XXX
XXX1
o XXX
Page 5 of 27
Scope of Work for Proposal Doc No. IRM-SOW-FEED00014XX-001
Revision A
24 Feb 24
- After construction is completed, a final inspection will be conducted to ensure all works
have been undertaken in accordance with Scope of Works and Design. The Inspection will
be carried out by both parties (IRM and Project Owner)
- The acceptance of works will be confirmed once the final inspection has been signed off
by both parties. Handover documentation will then be submitted to Project Owner for
approval.
5 Work Excluded
The following work is excluded from this Scope. This work is deemed to be the responsibility of the
Project Owner. In the event that the Project Owner requires this work to be included in the Scope it
will constitute a change and will follow the change procedures.
The scope of the Project Owner for supply and install are as follows.
- Area Clearance and move material out of the working area, By Project Owner
- Refer to the cost estimate, all items need to complete by project owner
- XXX
- Provide security during construction to protect from theft (especially cable) (if not relate
to electrical work should be remove from proposal). If security breaches occur that result
in loss of materials or equipment, replacement and/or repair will be at the cost of the
Project Owner. (need security stand by XX months during construction)
- No additional works will be undertaken until the required Change Notice (CN) is approved
by the relevant GM.
6 General Notes
IRM hereby quote for the complete supply of the equipment/materials as contained in Section 14 -
Schedule of rates, including the furnishing of all labour, supervision, materials, equipment, tools,
supplies and services required to execute the works.
The equipment/materials shall be supplied strictly in accordance with the documents listed herein
Schedule 1 - Applicable Documents.
Page 6 of 27