Roll No. Total No.

of Pages : 03
Total No. of Questions : 09
B.Tech. (CE) (Sem.–6)
ENGINEERING ECONOMICS ESTIMATION AND COSTING
Subject Code : BTCE-601-18
M.Code : 79393
Date of Examination : 12-12-2022
Time : 3 Hrs. Max. Marks : 60

INST RUCT IONS T O CANDIDAT ES :


1. SECTION-A is COMPULSORY cons is ting of TEN questions carrying TWO marks
each.
2. SECTION-B c ontains FIVE questions c arrying FIVE marks eac h and s tudents
have to atte mpt any FOUR ques tions.
3. SECTION-C contains THREE questions carrying TEN marks e ach and s tudents
have to atte mpt any TWO questions.

SECTION-A

1. Write briefly :

a) Write any four objectives of Rate analysis

b) Write a short note on Approximate estimate

c) Define depreciation what are the various methods used in depreciation calculation

d) Give a short note on sunken cost

e) Differentiate between macroeconomic and microeconomic

f) What are the duties of quantity surveyor?

g) Discuss various methods used to compare GDP of different countries

h) Explain various determinants of supply

i) What are the various representative factors for investment analysis?

j) What is product life cycle?

1 | M-79393 (S2)- 56
SECTION-B

2. Analyse the rate for construction of random rubble stone masonry in foundation and
plinth in cement mortar 1:6. Unit 1 m3

3. What is contract explain various types of contracts.

4. What do you meant by out-turn work with suitable example, explain approximate
quantity of different work done by an average artisan per day.

5. Define the term cost. What are various types of cost?

6. A R.C.C beam 400 mm × 800 mm and length 5200 mm is reinforced with 5 no. 20 mm
diameter of M.S. bars placed in one row. Three main bars are bent-up. Two i.e., anchor
bars of 10 mm diameter are provided at the top. 6 mm diameter stirrups are provided at
200 c/c. The all-round clear cover is 40 mm. Find out the total quantity of steel (plain)
bars. Prepare the table of bar bending schedule.

SECTION-C

7. Estimate the cost of earthwork for a portion of a road for 400 meters length from the
following data:

Station Distance in metre R.L of Ground


25 1000 51.00
26 1040 50.90
27 1080 50.50
28 1120 50.80
29 1160 50.60
30 1200 50.70
31 1240 51.20
32 1280 51.40
33 1320 51.30
34 1360 51.00
35 1400 50.60

R.L of formation at 25th station is 52.00. Downward gradient of 1 in 200 is provided


throughout the section. Draw longitudinal section of the road. Formation width of the
road in 10 meters. Side slopes are 2:1 in banking and 1.5:1 in cutting.

2 | M-79393 (S2)- 56
8. Discuss in detail

a) Workman's compensation act

b) Minimum wage act.

c) Easement Rights.

9. Estimate the quantities of the following items of a residential building from the given
drawing in Figure 1

a) Lime concrete in foundation

b) First class brickwork in 1:5 cement sand mortar in foundation and plinth

c) 2.5 cm Damp proof course

d) First class brickwork in lime mortar in superstructure Doors:

Dl - 120 cm ×210 cm

D2 - 100 cm ×200 cm

D3 - 75 cm ×180 cm

Windows:

Wl - 100cm×150 cm

W2 - 100 cm×200 cm

W3 - 75cm×120 cm

C.W - 75×60 cm

3 | M-79393 (S2)- 56
NOTE : Disclosure of Identity by writing Mobile No. or Making of passing request on any
page of Answer Sheet will lead to UMC against the Student.