STL 23054 Sunit Brewery Pending Points Tank Wise

SL No Tank NO Description Material Status Activity Discipline Priority Completion Date Remarks

1 UT-12 Tank Top Platform & Interconnection (Handrail Fixing) Delivered @ site Mechanical P-1
2 UT-12 Tank Top Platform & Interconnection (Painting) Delivered @ site Mechanical P-1

3 UT-12 Tank Top Platform Gratings Fixing Delivered @ site Mechanical P-1

4 UT-12 Glycol Supply Line insulation Cladding sheet not available Insulation P-2

5 UT-12 Glycol Return Line insulation Cladding sheet not available Insulation P-2

6 UT-12 Name Plate & Sticker Fixing Delivered @ site Mechanical P-1
7 UT-12 Tank bottom pipe Joint Cleaning Mechanical P-1

8 UT-12 Tank Cladding bottom reducer painting White paint yet to arrange. Insulation P-3

9 UT-12 Puff cleaning Insulation P-1


10 UT-12 Tank Cladding 5th layer black painting Delivered @ site Insulation P-1

11 UT-11 Tank Top Platform & Interconnection (Handrail Fixing) Delivered @ site Mechanical P-1
12 UT-11 Tank Top Platform & Interconnection (Painting) Delivered @ site Mechanical P-1

13 UT-11 Tank Top Platform Gratings Fixing Delivered @ site Mechanical P-1

14 UT-11 Glycol Supply Line insulation Cladding sheet not available Insulation P-2
15 UT-11 Glycol Return Line insulation Cladding sheet not available Insulation P-2

16 UT-11 Name Plate & Sticker Fixing Delivered @ site Mechanical P-1

17 UT-11 Tank bottom pipe Joint Cleaning Mechanical P-1

18 UT-11 Tank Cladding bottom reducer painting White paint yet to arrange. Insulation P-3
19 UT-9 Tank Top Platform & Interconnection (Handrail Fixing) Delivered @ site Mechanical P-1

20 UT-9 Tank Top Platform & Interconnection (Painting) Delivered @ site Mechanical P-1
21 UT-9 Tank Top Platform Gratings Fixing Delivered @ site Mechanical P-1
22 UT-9 Glycol Supply Line insulation Cladding sheet not available Insulation P-3

23 UT-9 Glycol Return Line insulation Cladding sheet not available Insulation P-3
24 UT-9 Name Plate & Sticker Fixing Delivered @ site Mechanical P-2
25 UT-9 Tank bottom pipe Joint Cleaning Mechanical P-2
26 UT-9 Tank Cladding & Puff filling Delivered @ site Insulation P-1
27 UT-9 Tank Cladding bottom reducer painting White paint yet to arrange. Insulation P-3

28 UT-9 Puff cleaning Insulation P-3


29 UT-9 Tank Cladding 5th layer black painting Delivered @ site Insulation P-2
30 UT-9 TT & LT field cable laying Delivered @ site Electrical P-1
31 UT-9 TT & LT field & panel termination Delivered @ site Electrical P-1
32 UT-9 Functioning with Scada (automation) Delivered @ site Electrical P-1

33 UT-21 Tank Top Platform & Interconnection (Handrail Fixing) Delivered @ site Mechanical P-1
34 UT-21 Tank Top Platform & Interconnection (Painting) Delivered @ site Mechanical P-1

35 UT-21 Tank Top Platform Gratings Fixing Delivered @ site Mechanical P-1
36 UT-21 Glycol Return line fit-up & welding Delivered @ site Mechanical P-2
37 UT-21 Cone glycol line valve fixing Delivered @ site Mechanical P-2

38 UT-21 Sight Glass fixing in Wort IN + Out line Delivered @ site Mechanical P-2

39 UT-21 Glycol Supply Line insulation Cladding sheet not available Insulation P-3

40 UT-21 Glycol Return Line insulation Cladding sheet not available Insulation P-3
41 UT-21 Name Plate & Sticker Fixing Delivered @ site Mechanical P-1

42 UT-21 Tank bottom pipe Joint Cleaning Mechanical P-1


43 UT-21 Scaffolding of tank Available @ site Insulation P-1
Delivered @ site, 40 Nos GI sheet has to
44 UT-21 Tank Cladding & Puff filling Insulation P-2
arranged
45 UT-21 Tank Cladding bottom reducer painting White paint yet to arrange. Insulation P-3
46 UT-21 Puff cleaning Insulation P-3

47 UT-21 Tank Cladding 5th layer black painting Delivered @ site Insulation P-3
48 UT-21 TT & LT field cable laying Delivered @ site Electrical P-1

49 UT-21 TT & LT field & panel termination Delivered @ site Electrical P-1

50 UT-21 Functioning with Scada (automation) Delivered @ site Electrical P-1