SL No Tank NO Description Material Status Activity Discipline Priority Completion Date Remarks
1 UT-12 Tank Top Platform & Interconnection (Handrail Fixing) Delivered @ site Mechanical P-1
2 UT-12 Tank Top Platform & Interconnection (Painting) Delivered @ site Mechanical P-1
3 UT-12 Tank Top Platform Gratings Fixing Delivered @ site Mechanical P-1
4 UT-12 Glycol Supply Line insulation Cladding sheet not available Insulation P-2
5 UT-12 Glycol Return Line insulation Cladding sheet not available Insulation P-2
6 UT-12 Name Plate & Sticker Fixing Delivered @ site Mechanical P-1
7 UT-12 Tank bottom pipe Joint Cleaning Mechanical P-1
8 UT-12 Tank Cladding bottom reducer painting White paint yet to arrange. Insulation P-3
11 UT-11 Tank Top Platform & Interconnection (Handrail Fixing) Delivered @ site Mechanical P-1
12 UT-11 Tank Top Platform & Interconnection (Painting) Delivered @ site Mechanical P-1
13 UT-11 Tank Top Platform Gratings Fixing Delivered @ site Mechanical P-1
14 UT-11 Glycol Supply Line insulation Cladding sheet not available Insulation P-2
15 UT-11 Glycol Return Line insulation Cladding sheet not available Insulation P-2
16 UT-11 Name Plate & Sticker Fixing Delivered @ site Mechanical P-1
18 UT-11 Tank Cladding bottom reducer painting White paint yet to arrange. Insulation P-3
19 UT-9 Tank Top Platform & Interconnection (Handrail Fixing) Delivered @ site Mechanical P-1
20 UT-9 Tank Top Platform & Interconnection (Painting) Delivered @ site Mechanical P-1
21 UT-9 Tank Top Platform Gratings Fixing Delivered @ site Mechanical P-1
22 UT-9 Glycol Supply Line insulation Cladding sheet not available Insulation P-3
23 UT-9 Glycol Return Line insulation Cladding sheet not available Insulation P-3
24 UT-9 Name Plate & Sticker Fixing Delivered @ site Mechanical P-2
25 UT-9 Tank bottom pipe Joint Cleaning Mechanical P-2
26 UT-9 Tank Cladding & Puff filling Delivered @ site Insulation P-1
27 UT-9 Tank Cladding bottom reducer painting White paint yet to arrange. Insulation P-3
33 UT-21 Tank Top Platform & Interconnection (Handrail Fixing) Delivered @ site Mechanical P-1
34 UT-21 Tank Top Platform & Interconnection (Painting) Delivered @ site Mechanical P-1
35 UT-21 Tank Top Platform Gratings Fixing Delivered @ site Mechanical P-1
36 UT-21 Glycol Return line fit-up & welding Delivered @ site Mechanical P-2
37 UT-21 Cone glycol line valve fixing Delivered @ site Mechanical P-2
38 UT-21 Sight Glass fixing in Wort IN + Out line Delivered @ site Mechanical P-2
39 UT-21 Glycol Supply Line insulation Cladding sheet not available Insulation P-3
40 UT-21 Glycol Return Line insulation Cladding sheet not available Insulation P-3
41 UT-21 Name Plate & Sticker Fixing Delivered @ site Mechanical P-1
47 UT-21 Tank Cladding 5th layer black painting Delivered @ site Insulation P-3
48 UT-21 TT & LT field cable laying Delivered @ site Electrical P-1
49 UT-21 TT & LT field & panel termination Delivered @ site Electrical P-1