SunShine Project

Changes Made by Client


Date 16-May-24
Change
Sr # Building Name Level Internal/External Area/Grid Description Measurements Status Remarks
requested on

Internal partition revised 6 times 12-May-23, 22-May-23, 13-June-23, 11-Dec-23, 15-Jan-24 and 19-Jan-24

1 MS Sliding Door added 8-Jul-23 Installed

2 windows added 8-Jul-23 Installed


Ozone Area
1 Door added on constructed wall 19-Jan-24 Wall dismantled, door installed

1 internal partition of glazing is added 29-Jan-24 Installed

1 Door (MS,Alum and Glass) added 10-Oct-23 Installed

Quality Room 1 window replaced with Door 10-Oct-23 Installed

Removal of Z purlins 23-Apr-24 Uninstalled

1 Window added 20-Sep-23 Deleted from scope

Wall has to dismentle and relocated 11-Dec-23 Done with the job

Mini Chemical Store Once again constructed wall dismantled 19-Jan-24 Done with the job

2 windows added 19-Jan-24 Installed

Constructed drain removed from floor 19-Jan-24 Done with the job

Pattern stations Dismantling of wall including coping beam 8-Nov-23 Done with the job

Laser Hall Designer office walls demolished and installed 11-Dec-23 Executed
purlins unistalled
Resin Dip Area Constructed room demolished 1-Apr-24 Done with the job

Centre lift grid I/5 Lift wall (Kitchen side) cladded with 5-Sep-23 Done with the job
brickwork 4.5" thick

On 11-Nov-23, client has


Front wall of double cell lift cladded with 4.5"
Internal decided to keep the wall with
thick brickwork upto lintel level. Later on, to 20-Oct-23 Done with the job
concrete finish instead of
dismantle the wall was decided.
brick cladding.
Double Cell lift

Constructed openings as per dwg, resized (Width


14-Mar-24 Done with the job
increased)

location of lift changed, for this drill and grout


Lobby Lift 22-May-23 Job Completed
(with epoxy chemical) activity was performed.

Internal process drains were completed after that


89 Rft installed SS angle
Washing Area grid A-K/1-4 it was advised to give RCC slab at some points on 12-Aug-23 Done with the job
2"x2"x3/16" had to remove.
drains instead of FRP grating.
GF
GF

Width had to increase coz 9"


MS double leaf door at Grid M/1 Width increased from 8ft to 8.75ft Installed kola adjacent to columns can
not take the heavy load of MS
Door.

All Areas Plaster work on jambs 22-May-23 Done with the job
of Int/Ext Doors and Windows

Management Washroom Plaster work 22-May-23 Done with the job

Corridor and offices Paint work on brick walls 22-May-23 In Progress

3mm Bitumen membrane Under all internal Windows. 22-May-23 Done with the job As per KASWA dwg

Brickwork, Glazing, false ceiling framing and paint


Office block 3 Grid Q-R/5-6 work completed, but now, this have to be 11-Dec-23 Executed As per revised drawing
removed/dismantled

Brickwork, Glazing, false ceiling framing and paint


Office block 2 Grid O-P/5 work completed, now have to be 11-Dec-23 Executed As per revised drawing
removed/dismantled

louver of LT room has been replaced with window 29-Nov-23 Installed

North elevation Grid S-T/1 Louvers replaced with windows and we have to 11-Jan-24 Done with the job
1 Mill Building resize the constructed openings of windows.

5 spans of brickwork above bracing beam 11-Jan-24 Done with the job
dismantled and installed with glazing.

South side cavity wall, openings have been


completed including jambs and marble sills but in
External 17-Oct-23 Done with the job
revised dwg 3x windows have been removed and
size of 5 openings of windows have been reduced.

Louvers replaced with windows and we have to 11-Jan-24 Done with the job
resize the constructed openings of windows.
South Elevation Grid A-T/8

Once again 3-4 inches on all side of openings of 20-Apr-24 Done with the job
exhaust fans extended.

All exhaust fan openings are being packed by 6-May-24 Done with the job
BMC.

Internal partition revised 5 times 26-Mar-23, 22-June-23, 6-July-23, 24-Aug-23 and 5-Dec-23

Constructed CLC wall dismantled and relocated to


25-Oct-23 Done with the job
increase passage's width
Pocket Setter J-K/4
Width of door increased from
26-Sep-23 Installed
3'-10" to 5'-4"
Internal
Internal
Grid j/4 infront Wall dismantled infront of centre stair 25-Oct-23 Done with the job
of centre stair

Lifts All walls cladded with CLC masonry 27-Sep-23 Done with the job

All Areas Plaster work on jambs Done with the job


of Int/Ext Doors and Windows
FF
3mm Bitumen membrane Under all internal Windows. Laid As per KASWA dwg

External West Elevation Removal of CC Jali 12-Oct-23 Done with the job

Grid A-B/1-8,J-K/1-8 AND S-T/1-8 Dry wall thinkness increased from 6" to 9.5" (as Sample completed
per site)
Grid A-B/1-8,J-K/1-8 AND S-T/1-8 Cementitious coating instead of paint Not started

EPS panels and concrete are used to raise the


Worker and Management washrooms (Raised Done with the job
floor level. Initially sewerage system was below
floor)
the slab.
Internal
Dry wall work is on hold except washroom Approx 400 Rft framing has been completed and 21-Dec-23
area. have to remove.
Dismantling of CLC walls including coping Due to revised plan 5-Dec-23 Done with the job
beam
Addition of Windows/Doors Due to revised plan 5-Dec-23 Done with the job
Dismantling of Granolethic flooring of thread Due to revised plan 5-Dec-23 Done with the job
Store

Internal partition revised 5 times 14-Oct-23, 27-Oct-23, 8-Dec-23, 29-Dec-23 and 23-Jan-24

Lifts All walls cladded with CLC masonry 27-Sep-23 In Progress

All Areas Plaster work on jambs 21-Oct-23 Completed


of Int/Ext Doors and Windows

SF Internal 3mm Bitumen membrane Under all internal Windows. 21-Oct-23 Done with the job As per KASWA dwg

GRID A-T/1-8 Dry wall thinkness increased from 6" to 9.5" (as 21-Oct-23 Done with the job
per site)

PD washing area Addition of branch drains 2-Nov-23 Done with the job

South Elevation Grid A-T/8 Extension of constructed 4 exhaust openings as 8-May-24 Done with the job
per drawing

MS Doors of lifts Pending


Rooftop External All Lifts
Lift walls cladded with 4.5" Brickwork 25-Oct-23 Completed

Cavity wall added with common wall


Upper Mezzanine ,Cavity wall
Upper Mezzanine of Engg offices and Power house. (Addition of 25-Oct-23 Done with the job
grid C-G/16
jambolan and 4.5" thick brickwork

Addition of Nosing on pads with MS angle


10-Oct-23 Done with the job
2"x2"x3/16"
Power House
Diesel slab and addition of FRP with chequered
15-Oct-23 Completed
sheet infront of Fire exit door

Internal

Ground Floor
Internal Addition of two new openings on wall for MEP
10 Sft 25-Oct-23 Job Completed
work, after the completion of brick masonry.
Ground Floor
LT Room
Addition of MS angle 1.5x1.5x3/16" and FRP
2-Nov-23 Job Completed
grating with chequered sheet

Initially there was FRP grating on trenches but


Power House decision was made to give RCC slab instead of 230 Rft 28-Sep-23 Job Completed
11-16/C-E grating. So installed MS angle 2"x2"x3/16" had to
be removed.

Workshop area Internal GF 6 M3 (2'x2') openings added on constructed wall 29-Nov-23 Job Completed

2 UB-2 Addition of Nosing on pads with MS angle 20-Nov-23 Job Completed


2"x2"x3/16"

Chiller's foundations

Acid Resisting tile 8-Dec-23 Not executed

Rooftop Mumty, two single glazed windows added 6-Feb-24 Job Completed

External

Workshope 1 Columns dismantled, for installation of IT tower. Job Completed

9 columns dismantled and 1 added for new


Powerhouse construction. All columns poured with 4000 PSI 15-Apr-24 Job Completed
concrete

Pump Room Louver replaced with 4'x4' window 29-Apr-24 Job Completed

Boiler area Internal Addition of Nosing on pads with MS angle 1-Dec-23 Job Completed
2"x2"x3/16"

3 UB-1
3 UB-1

Toilet Block FF External 3 window (6'x2.5' added) 7-Feb-24 Job Completed

Dismantling work of Exisiting drain


(3.67'x2.67'x140') coz it is passing through admin 650 Cft quality of existing
4 Admin Block Substructure External Re-routing of existing RCC Drain 26-Oct-23 Job Completed
block, for the new drain UPVC dia 12", 150 Rft drain dismantled
has been constructed.

Height of walls increased by 4" of equalization


External tank 16-Jun-23 Job Completed
Sump added in Raft of aeration tank

Layout completed on 26-Dec-23 and there was


Internal error in the dwg. Later on it was cleared. But we Job Completed
have to dismantle substructure wall.

Substructure wall (common wall of control panel


internal and lab office) is still upto floor coz layout revised 13-Feb-24 Job Completed
and wall on it replaced with glazing (window and
door).

GF Office Block
External Shade added on 2 sides and RCC parapet wall 14-Feb-24 Job Completed

Internal Floor drains added 1-Feb-24 Job Completed

5 ETP
Internal Floor Pads 1-Feb-24 Job Completed
5 ETP

Internal Openings 17-Feb-24 Job Completed

1 window added on constructed wall on 13-Jan-


24, 5 on 27-Jan-24 and finally 3 window locked on Job Completed
13-Feb-24 to be provided.

GF External Blower Room


Above equalisation tank

3ft wide shade and RCC parapet added. After


completion of FW as per previous dwg (without 19-Feb-24 Job Completed
shade)

Initially it was decided to not provide beam under


Tank External Aeration Tank walkway but on later stage this was again decided Job Completed
to provide beam.

Steel and formwork completed on 14-Dec-23 and


Tank Inner tank Sedimentation Tank dwg revised on 19-Dec-23. Missing details cleared 25-Dec-23 Job Completed
on

Substructure wall (common wall of toilet and


store) is till SOG coz layout revised. Later on 28-Mar-24 Job Completed
Superstructure wall of toilet and store deleted
from scope

GF Internal Left side Gate offices

Tile replaced with grano 26-Apr-24 Job Completed

GF Internal Right Side Gate offices Tile replaced with grano 26-Apr-24 Job Completed
6 Gate offices
6 Gate offices

Clear height increased from 20' to 21' 24-Apr-24 Pending

GF External Main Gate

2 windows added on common wall 24-Apr-24 Pending

For bike parking area, gate added


Dismantling of E-Brick B/wall and 45 Rft B/wall will be dismantled, 19-Oct-23 Done with the job
currently that part is completed till E-bricks

E-Bricks
B/wall Zone 2

Removal of Razor wire, E-bricks and dismantling


Dismantling of E-Brick B/wall of 3x H columns, pedestal columns and 25-Nov-23 Done with the job
brickwork, for installation of turbine

E-Bricks RCC columns & retaining wall height increased


Height of B/wall increased by 6" 8-Mar-23 Done with the job
B/wall All zones by 6"

Difference is bed level of B/wall along agriculture


E-Brick B/wall Along agriculture land land and neighbour's existing wall, -9ft and -6'-3"
from ERL respectively.

HDP, backfilling Provision of Ghassu to client 20-Nov-23 Done with the job

Ghassu, bajjar, RCC concrete and installation


Foundation work for HT
of embeded parts along E-brick boundary wall Done with the job
cable and gas pipeline
(From compressor room to Lesco Room)

Re-Shifting of 1 concrete batching plant Done with the job

Bike Parking area

2ft Earthfilling 18-Dec-24 Done with the job

7 Infrastructure External
Dismantling of Catch basins and kerb stones
along the constructed drain. Besides, to
increase road level for the slope towards Done with the job
constructed drain, we have to lay more bajjar
Road 8 (8+3.5= 11.5 inche)

Width increased from 15ft to 30ft Done with the job


Road 1 and 7 Uprooting of trees Done with the job

On road 9 and 3 Addition of SWD Done with the job

Road 10 width increased from 3'-6" to 4'-11". Laid Done with the job
kerbstone in 200 Rft length removed.

Road 1 Laid kerbstone in 100 Rft removed due to Pending


revised dwg (4ft to 6ft)

F/ Boundary wall New B/wall pulled 15ft away from old B/wall, Done with the job
filling required

ELV and Electrical provisions On Compacted bajjar, we have to excavate for 12-Feb-24 Done with the job
provisions

Temp. route for irrigation RCC pipe (18" dia and 160 Rft) with RCC concrete
27-12-23 In Progress
channel casing