Sunshine Project Changes Made by Client Date 16-May-24
Sunshine Project Changes Made by Client Date 16-May-24
Internal partition revised 6 times 12-May-23, 22-May-23, 13-June-23, 11-Dec-23, 15-Jan-24 and 19-Jan-24
Wall has to dismentle and relocated 11-Dec-23 Done with the job
Mini Chemical Store Once again constructed wall dismantled 19-Jan-24 Done with the job
Constructed drain removed from floor 19-Jan-24 Done with the job
Pattern stations Dismantling of wall including coping beam 8-Nov-23 Done with the job
Laser Hall Designer office walls demolished and installed 11-Dec-23 Executed
purlins unistalled
Resin Dip Area Constructed room demolished 1-Apr-24 Done with the job
Centre lift grid I/5 Lift wall (Kitchen side) cladded with 5-Sep-23 Done with the job
brickwork 4.5" thick
All Areas Plaster work on jambs 22-May-23 Done with the job
of Int/Ext Doors and Windows
3mm Bitumen membrane Under all internal Windows. 22-May-23 Done with the job As per KASWA dwg
North elevation Grid S-T/1 Louvers replaced with windows and we have to 11-Jan-24 Done with the job
resize the constructed openings of windows.
1 Mill Building
5 spans of brickwork above bracing beam 11-Jan-24 Done with the job
dismantled and installed with glazing.
Louvers replaced with windows and we have to 11-Jan-24 Done with the job
resize the constructed openings of windows.
South Elevation Grid A-T/8
Once again 3-4 inches on all side of openings of 20-Apr-24 Done with the job
exhaust fans extended.
All exhaust fan openings are being packed by 6-May-24 Done with the job
BMC.
Internal partition revised 5 times 26-Mar-23, 22-June-23, 6-July-23, 24-Aug-23 and 5-Dec-23
Constructed CLC wall dismantled and relocated to 25-Oct-23 Done with the job
increase passage's width
Pocket Setter J-K/4
Width of door increased from
26-Sep-23 Installed
3'-10" to 5'-4"
Internal
Internal
Grid j/4 infront Wall dismantled infront of centre stair 25-Oct-23 Done with the job
of centre stair
Lifts All walls cladded with CLC masonry 27-Sep-23 Done with the job
External West Elevation Removal of CC Jali 12-Oct-23 Done with the job
Grid A-B/1-8,J-K/1-8 AND S-T/1-8 Dry wall thinkness increased from 6" to 9.5" (as Sample completed
per site)
Grid A-B/1-8,J-K/1-8 AND S-T/1-8 Cementitious coating instead of paint Not started
Internal partition revised 5 times 14-Oct-23, 27-Oct-23, 8-Dec-23, 29-Dec-23 and 23-Jan-24
SF Internal 3mm Bitumen membrane Under all internal Windows. 21-Oct-23 Done with the job As per KASWA dwg
GRID A-T/1-8 Dry wall thinkness increased from 6" to 9.5" (as 21-Oct-23 Done with the job
per site)
PD washing area Addition of branch drains 2-Nov-23 Done with the job
South Elevation Grid A-T/8 Extension of constructed 4 exhaust openings as 8-May-24 Done with the job
per drawing
Internal
Ground Floor
Internal Addition of two new openings on wall for MEP
10 Sft 25-Oct-23 Job Completed
work, after the completion of brick masonry.
Ground Floor
LT Room
Addition of MS angle 1.5x1.5x3/16" and FRP
2-Nov-23 Job Completed
grating with chequered sheet
Workshop area Internal GF 6 M3 (2'x2') openings added on constructed wall 29-Nov-23 Job Completed
Chiller's foundations
Rooftop Mumty, two single glazed windows added 6-Feb-24 Job Completed
External
Pump Room Louver replaced with 4'x4' window 29-Apr-24 Job Completed
Boiler area Internal Addition of Nosing on pads with MS angle 1-Dec-23 Job Completed
2"x2"x3/16"
3 UB-1
3 UB-1
GF Office Block
External Shade added on 2 sides and RCC parapet wall 14-Feb-24 Job Completed
5 ETP
Internal Floor Pads 1-Feb-24 Job Completed
5 ETP
GF Internal Right Side Gate offices Tile replaced with grano 26-Apr-24 Job Completed
6 Gate offices
6 Gate offices
E-Bricks
B/wall Zone 2
HDP, backfilling Provision of Ghassu to client 20-Nov-23 Done with the job
7 Infrastructure External
Dismantling of Catch basins and kerb stones
along the constructed drain. Besides, to
increase road level for the slope towards Done with the job
constructed drain, we have to lay more bajjar
Road 8 (8+3.5= 11.5 inche)
Road 10 width increased from 3'-6" to 4'-11". Laid Done with the job
kerbstone in 200 Rft length removed.
F/ Boundary wall New B/wall pulled 15ft away from old B/wall, Done with the job
filling required
ELV and Electrical provisions On Compacted bajjar, we have to excavate for 12-Feb-24 Done with the job
provisions
Temp. route for irrigation RCC pipe (18" dia and 160 Rft) with RCC concrete
27-12-23 In Progress
channel casing