Professional Documents
Culture Documents
Highway and Railroad Engineering by Yours Truly
Highway and Railroad Engineering by Yours Truly
Highway and Railroad Engineering by Yours Truly
MODULE 1
1.0 Transportation\
Introduction: Highways, railroads and different kind of transportation have all played a major
role in the development of the society ever since. Til today, these modes of transportation have
all continued to provide and be a critical aspect of a developing civilization.
Production/supply and
demand
Social Effects
- the reason why early civilizations have progressed because their population have
always settled in places along rivers, where their mode of transportation of their goods
was through small boats. Now populations have always settled along the river shores,
road sides and near railway stations. the various social effects of transportation may be
further elaborated with the ff;
sectionalism and
transportation : present
conditions of
transportation have
greatly improved and
reduced sectionalism in
different countries.
concentration of
population into urban
areas : since
transportation has greatly
improved the economic
conditions of different
countries, people from the
rural areas has also
migrated to urban cities.
This concentration of
people in one area needs
to have an adequate
mass transportation
facilities to satisfy the
needs of the people that
needs to go from point to
point everyday.
aspect of safety, law
and
order : transportation
facilities are needed and
are of great importance
when it comes to rushing
aids in times of
emergencies. To maintain
law and order, an efficient
system of transportation
is important , especially
when it comes to
defending a country's
interest and security from
external aggression from
different countries.
Summary:
Tresaguet Construction
Not until the eighteenth century did any early civilizations have created a new road
construction method, Pierre Tresaguet developed an improved method of construction
in France. He developed several methods of construction. The main feature of his
proposal was that the thickness of the roads need not to be over 30 cm. The typical
cross section of Tresaguet Construction :
o
subgrade is prepared and a layer of large
foundation stones were laid on edge by hand.
At the two edges of pavement large stones
were embedded edgewise to serve as
submerged curb stones.
the corners of these heavy foundation stones
were hammered and then the interstices filled
with smaller stones. Broken stones were
packed to a thickness of about 8 cm and
compacted.
Top wearing course was made of smaller
stones and compacted to a thickness of about
5 cm at the edges and gradually increased
towards the center, giving a cross slope of 1 in
45 to the surface.
The shoulders were also provided cross slope
to drain the surface water to the side drain
Metcalf Construction
John Metcalf (1717-1810) was engaged on road construction works in England during
the same period as Tresaguet when he was working in France. He was responsible for
the construction of the 290 km of road in the northern region of England.
Telford Construction
Thomas Telford began his work in the early 19th century. He was the founder of the
Institution of Civil Engineers at London. He believed in using heavy foundation stones
below the top surface and above soil subgrade. The construction steps are:
o
A level subgrade is prepared to the designed
width of about 9 meters.
Large foundation stones of thickness 17-22 cm
were laid with hand with their largest face
down so as to be in stable position. Stones
with 17 cm thickness were laid at the edges
and increases towards the center at 22 cm.
The interstices between the foundation stones
were filled with smaller stone and chipping and
properly beaten down.
The central portion of about 5.5 meter width
was covered with two layers of angular broken
stones to compacted thickness of 10 and 5
cm.
A certain width of the pavement towards the
edges was constructed by compacted broken
stones, 15cm thick, sometimes in lime mortar
instead of using the curb stones.
A binding layer of wearing course 4 cm thick
was constructed on top using gravel.
Macadam Construction
John Macadam put forward an entirely new method of road construction. He was the
Surveyor General of Roads in England and his new concept of road construction
became known by the year 1827. He recognized the importance of subgrade drainage
and compaction. He also suggested that heavy foundation stones are not at all
necessary to be placed at the bottom layer of construction. The most important
modifications made in Macadam's methods with respect to the older methods are:
o
the importance of subgrade drainage and
compaction were recognized and so the
subgrade was compacted and was prepared
with a cross slope of 1 in 36.
Macadam was also the first person to suggest
that heavy foundation stones are not at all
necessary to be placed at the bottom layer.
though the total thickness of construction was
less than the previous methods, this technique
could serve the purpose in better way, due to
better load dispersion characteristics of
compacted broken stone aggregates of
smaller sizes.
The size of broken stones for the top layer was
decided based on the stability under animal
drawn vehicles.
Macadam's method is the first method based on scientific thinking. It was realized that
stresses due to the wheel loads of traffic decreases on the lower part of the pavement.
This method became very popular far and wide.
Visual Presentation of 3 Most Popular Roads after the Roman Empire
Classification of Roads
Types of Roads
-classified depending on whether they can be used all throughout the year;
all-weather roads
fair weather roads
all weather roads are roads that are fairly manageable to use during all weather, except
at major river crossing where interruption to traffic is permissible upon certain extent;
fair weather roads are roads where the traffic maybe interrupted during monsoon
season at causeways where streams may overflow.
-classified based on the type of carriage or the road pavement, the roads are classified
as;
-roads may also be classified based on their use, as classified by the DPWH for roads
in the Philippines
Road Patterns
- different road patterns may be classified to:
o
(a) rectangular or block pattern
(b) radial or star and block pattern
(c) radial or star and circular pattern
(d) radial or star and grid pattern
(e) hexagonal pattern
(f) minimum travel pattern
these patterns are shown below:
Planning Surveys
Highway planning includes the assessment for the length requirement for an area
(maybe a district, city, or the whole country) and preparation of master plan. In doing
these phases, one must carry out field surveys and collect data. The field surveys
required to collect the data may be called as planning surveys.
The planning surveys consist of the following fact finding surveys:
o
economic studies - population, trend of its growth,
agricultural and industrial listing, income per capita,
banking, post office, etc.,
financial studies - source of income, revenue from
taxation on road transport
traffic or road use studies - traffic volume, traffic flow
patterns, mass transportation facilities, accidents, growth
of vehicular traffic, passenger trips
engineering studies - road location and alignment,
classification; type of roads in use, soil and topography
studies
Highway Alignment
The position or the layout of the center line of the highway on the ground is called
alignment. Horizontal alignment includes the straight path, horizontal deviations and the
curves. Changes in gradient and vertical curves are under vertical alignment. It is
important that the roads must be properly aligned and adheres to road standards for the
failure to do these would result to increase in; construction cost, maintenance cost,
vehicle operation cost, accident rate.
Requirements for and Ideal Alignment
short
easy
safe, and
economical
obligatory points
traffic
geometric design
economics
other considerations; special considerations while
aligning roads on hilly areas
stability
drainage
geometric standard of hill roads
resisting length
https://www.ancient-origins.net/history/built-last-craftsmanship-enabled-roman-roads-
withstand-passage-time-007523 roman roads
Summary:
a) rectangular or block pattern
(b) radial or star and block pattern
(c) radial or star and circular pattern
(d) radial or star and grid pattern
(e) hexagonal pattern
(f) minimum travel pattern
3.0 Types of Road Failures
Introduction to the Topic:
Road maintenance is one of the important components of the entire road
system. The maintenance operations involve the assessment of road conditions,
identifying the problems and coming up with the solutions step by step to conduct the
maintenance of the road. Even well built highways needs maintenance from time to
time, this is due to several factors and conditions that the road experiences throughout
the year. These problems includes various types of failures in pavements ranging from
minor and localized failure to major and general failures.
Pavement Failures
Failures in Flexible Pavements
Any settlement in each of the layer of the pavement could lead to whole pavement
failure. This demands that each one of the layers should be carefully designed and laid.
o Failure in Subgrade - one of the prime cause of flexible pavement
failure, it is the excessive deformation of the subgrade soil.
Failure in Sub-base or base course - caused by inadequate stability or strength, loss of binding
in the pavement material, loss of base course materials, use of low quality materials
Failure in wearing course - a typical failure in roads where the topmost layer shows sign of wear
due to the vehicles traversing the road.
Routine maintenance
Periodic maintenance
Special repairs
Routine and periodic maintenance are needed in any type of highways/roads, for these
roads are highly susceptible to wear due to continuous use of vehicles and weather
conditions. Special repairs and strengthening of pavement with overlays are needed to
prevent further pavement failures.
Routine Maintenance
o upkeep of carriageway
o maintenance of shoulders and subgrade
o maintenance of side drains and other ancillary works
o patch repairs of pot holes and localized failures
These cracks should be sealed off before the cracks get worse and further develop to
larger cracks. This is done by filling the cracks with bituminous sealing compound
heated to liquid consistency. The sealer is placed about 3 mm above the level ground
and a layer of sand is spread over it to protect it temporarily.
In the event that these cracks have worsened, additional measures should be done in
order to maintain the road functionality. The maintenance work in such a case involves
first remedy of the basic cause of the problem and then re-casting the failed slabs.
Flexible or rigid overlay may be needed in failure of slabs that came from structural
distress, this is needed before the cracks develop to other slabs too. It is however not
worth while to provide an overlay over a badly cracked slab due to uneven settlement of
the cracked and broken slabs, removal of the broken concrete slab may be necessary
and reconstruction of new pavement.
Maintenance of Joints
Joint filler material at the expansion joints may get damaged or deteriorate over time,
thus repair is needed. The repair consists of removal of sealer and deteriorated filler
and sealer materials from the expansion joints cleaning up, replacement with new filler
board and sealing the top joints with suitable sealer material.
Strengthening of Existing Pavements
For the successful maintenance of pavements it is essential that they have adequate
stability to withstand the design traffic under prevailing climatic and subgrade
conditions. Due to additional wheel loads that pavements may experience over time,
overlays are important to provide additional strength to the concrete.
Types of Overlay
o Flexible overlay over flexible pavement
o cement concrete or rigid overlay over flexible pavements
o flexible overlays over cement concrete
o cement concrete or rigid overlay over rigid pavements
Summary
1. ) Classification of maintenance
o
Routine maintenance/repairs
Periodic maintenance
Special repairs
2. ) Failures in Flexible Pavements
o
Failure in Subgrade
Failure in Sub-base or base course
Failure in wearing course
3. )Typical Flexible Pavement Failures
o
Alligator (map) Cracking
Consolidation of Pavement Layers
Shear Failure and Cracking
Longitudinal Cracking
Frost Heaves
Lack of Binding with Lower Layer
Reflection Cracking
4. ) Failure in Cement Concrete Pavements
o
disintegration of cement concrete
formation of cracking
spalling of joints
poor riding surface
slippery surface
formation of shrinkage cracks
ingress of surface water and further progressive failures
cracking of slab corners
cracking of pavements longitudinally
settlement of slabs
widening of joints
mud pumping
5. ) Typical Rigid Pavement Failures
o
Scaling of Cement Concrete
Shrinkage Cracks
Spalling of Joints
Warping Cracks
Mud Pumping
Structural Cracks
4.0 Geometric Design of
Highways
Introduction to the Topic:
Geometrics are of great importance in designing an efficient and safe road
environment. Planning initially all the geometric design of the road is necessary for a
less expensive construction of the highways and railways. Geometric design of
highways and railways deal with the cross section elements, sight distance
considerations, horizontal alignment details, vertical alignment details and intersection
elements. Highway geometrics are greatly influenced by the topography, locality, and
traffic characteristics and the requirements of design speed.
1. ) Design Speed - this is the most important factor that controls the geometric
design elements of highways. Design speed is taken into account in the
overall requirements of the highway. Different speed standards/limits are
placed depending on the use of the highway. This is further modified taking
into consideration the topography of the area. Almost every geometric design
depends on the assigned design speed of the highway, from the cross
section element, to the radius of the curve of super-elevation, etc.
2. ) Topography - or terrain, is of significance factor in designing the geometric
elements of a highway. This is classified based on the general slope across
the alignment.
3. ) Traffic Factors - the factors associated with the traffic that affect geometric
design of roads are the vehicular characteristics and of course the road
users.
4. ) Design hourly volume and capacity - traffic flow/volume fluctuates over
time, this is where off-peak and peak hours are considered. Designing a
highway based only on the peak volume of vehicles during peak hours will
make the design uneconomical. Therefore a reasonable value of traffic
volume is considered, called design hourly volume.
5. ) Environmental and other factors - factors such as aesthetics,
landscaping, air pollution, noise pollution and other local conditions should be
given due consideration in the design of highways.
Pavement Width
This depends on the width of traffic lane and the number of lanes on the road. The width
is determined on the basis of the ruling standard width of the vehicle and minimum side
clearance for safety. Having a larger width of a road also affects the maximum speed of
the vehicles.
IRC Specification for Carriageway width
Kerbs (Curbs)
Kerbs indicates the boundary between the pavement and shoulder. It is desirable to
provide kerbs on urban roads
\
Road Margins
There are various elements that are included in the road margins; shoulder, parking
lane, frontage road, driveway, cycle track, footpath, guard rail and embankment slope.
o
Shoulders are provided along the road edge
to provide as an emergency lane for the
vehicles to be taken out of the main road way.
Parking lanes are provided in urban roads to
allow kerb parking. As far as possible, only
parallel parking should be allowed as it is safer
from moving vehicles.
Frontage roads are provided to give access
to properties along an important highways.
Driveways connect commercial
establishments like fuel stations, etc.
Cycle tracks are provided in urban areas with
a high volume of cyclists.
Foot path or side walks are provided in urban
areas to protect pedestrians from vehicles.
Guard rails are provided at the edge on a fill
so that vehicles are prevented from running off
the embankment.
Sight Distance
Defined as the distance the driver sees along the road surface from a specified height
above the road. It is important to consider sight distance in the geometric design of the
highway, as the feasibility to see ahead is important for safe vehicle operation.
Three sight distance situations are considered in the design:
o
stopping sight distance
safe overtaking or passing sight distance
safe sight distance for entering into
uncontrolled intersections
The SSD can be calculated by adding the lag distance or the time before the driver
applies the brakes (reaction time) multiplied by the speed of the vehicle, and the
distance travelled after the application of the brakes, which is given by the equation:
L =v^2/2gf
Stopping distance:
= vt + v^2/2gf
Stopping distance at slopes
= vt + v^2/2g(f + - .01n)
The overtaking sight distance is the minimum distance open to the vision of the driver of
a vehicle intending to overtake the slow vehicle ahead safely against the traffic in the
opposite direction.
Velocities of the overtaking vehicle, overtaken vehicle and of the vehicle coming in the
opposite direction
Spacing between vehicles, which in-turn depends on the speed
Skill and reaction time of the drive
Rate of acceleration of overtaking vehicle
Gradient of the road
P = Wv^2/ gR
W - weight of the vehicle
R - radius of the circular curve
v - speed of vehicle in m/s
g - gravity, 9.81 m/s2
Centrifugal force has 2 effects, to force vehicle to skid out of the lane, and/or to overturn
the vehicle. This will be further illustrated in the discussion.
Super-elevation
In order to counteract the force exerted by the centrifugal force and prevent skidding
and overturning of the vehicle on curves, a super elevation may be required in order to
add a certain measure in addition to the frictional force. This is the super-elevation. This
is done by raising the outer edge of a curve, providing a transverse slope throughout the
length of the horizontal curve. Superelevation is also known
as cant or banking. Expressed as 'e', it is the ratio of the height of the outer edge with
respect to the horizontal width.