MS08 - Retaining Wall - Section 1
MS08 - Retaining Wall - Section 1
Ghana Limited
P W GHANA
Civil Engineering and Mining Contractors
Site Offices
Tema Port Stacking & Marshalling Area B
Ghana
THE METHOD STATEMENT MUST BE EXPLAINED TO THE SITE OPERATIVES BY THE SITE SUPERVISOR/SECTION MANAGER PRIOR TO COMMENCEMENT: EACH SECTION MUST BE
SIGNED OFF BY THE SUPERVISOR ON COMPLETION OF THE WORK SECTION: THE SIGNED METHOD STATEMENT MUST BE RETURNED TO THE PROJECT MANAGER ON COMPLETION
1.00 Preamble 1. The retaining wall will be constructed in sections of 10m with the concrete pours
alternating.
2.00 Setting Out 2. Qualified and competent Engineering staff will set out the works in accordance PPE to be worn as per the PW SPS.
with the approved drawings. Hand tools to be checked for defects prior to use.
3.00 Excavation 1. An excavator will excavate to level taking care not to over excavate, level will be PPE to be worn as per the PW SPS.
controlled by boning a traveler through the profiles. Hand tools to be checked for defects prior to use.
2. Excavated material will be loaded into tippers and transported to the reusable or Plant operators must have valid PW driving permit.
waste stockpile. Adequate signage/warning tapes will be provided to
3. Suitability of material will be determined by the materials Engineer. warn other personnel of the excavation.
If the excavation exceeds 1.200m deep, the sides will
be benched out.
4.00 Blinding 4. Minimum 50mm blinding concrete will be placed to levels given by the PPE to be worn as per the PW SPS.
Engineering staff. Hand tools to be checked for defects prior to use.
Plant operators must have valid PW driving permit.
Only the foreman mason or another designated person
should direct the truck whilst reversing or discharging
5.00 Steel fixing 1. Steel reinforcement will be pre-cut and bent for the base slab and wall starter PPE to be worn as per the PW SPS.
bars, this will be transported mechanically to the excavation and placed on Hand tools to be checked for defects prior to use.
timber supports to protect it.
2. Steel fixers will place the reinforcing bars in the correct pattern and tie them
together as stated on the approved reinforcement drawings.
3. A minimum of 50mm cover will be ensured using concrete spacers on the
blinding and formworks.
6.00 Formwork 1. Formwork for the base slab, either site fabricated or proprietary type, will be PPE to be worn as per the PW SPS.
transported to a point close to the edge of the excavation and placed on timber Hand tools to be checked for defects prior to use.
battens to avoid contamination
2. The formwork will be placed and adequately braced in position.
3. Rails will be fixed to hold a 100mm kicker in place to form the base of the walls
pour.
4. The Site Engineer will then check the horizontal alignment of the kicker.
5. The PW pre-pour inspection will be carried out and the findings recorded, at
which time the Supervisor will have any defects found remedied.
7.00 Inspection At this point, the Resident Engineer should inspect and approve the Base
(HOLD POINT) Reinforcement, having been notified at least 24 hours earlier that the reinforcement
P.W. Ghana Limited
P W GHANA
Civil Engineering and Mining Contractors
Site Offices
Tema Port Stacking & Marshalling Area B
Ghana
THE METHOD STATEMENT MUST BE EXPLAINED TO THE SITE OPERATIVES BY THE SITE SUPERVISOR/SECTION MANAGER PRIOR TO COMMENCEMENT: EACH SECTION MUST BE
SIGNED OFF BY THE SUPERVISOR ON COMPLETION OF THE WORK SECTION: THE SIGNED METHOD STATEMENT MUST BE RETURNED TO THE PROJECT MANAGER ON COMPLETION
THE METHOD STATEMENT MUST BE EXPLAINED TO THE SITE OPERATIVES BY THE SITE SUPERVISOR/SECTION MANAGER PRIOR TO COMMENCEMENT: EACH SECTION MUST BE
SIGNED OFF BY THE SUPERVISOR ON COMPLETION OF THE WORK SECTION: THE SIGNED METHOD STATEMENT MUST BE RETURNED TO THE PROJECT MANAGER ON COMPLETION