Professional Documents
Culture Documents
A Proposed Three Storey Multi Purpose Building at Brgy. Bolo Roxas City Capiz1
A Proposed Three Storey Multi Purpose Building at Brgy. Bolo Roxas City Capiz1
JUNE 2023
Republic of the Philippines
CAPIZ STATE UNIVERSITY
Main Campus, Fuentes Drive, Roxas City Capiz
APPROVAL SHEET
Advisory Committee:
Recommending Approval:
Approved by:
i
Republic of the Philippines
CAPIZ STATE UNIVERSITY
Main Campus, Fuentes Drive, Roxas City Capiz
ACCEPTANCE SHEET
MA. ADELINE D. DIAZ, CE, MEE JOEL C. VILLARUZ, CE, MEE, PhD
Member Member
MA CORAZON A. BARCENAS, CE, ME, LPT
Chairman
Accepted as a partial fulfillment of the requirements for
the Degree of Bachelor of Science in Civil Engineering.
ii
ACKNOWLEDGEMENT
iii
the structure-design process that improved the
courage.
J. A. A.
N. A. D.
D. D. F.
J. M. P.
iv
DEDICATION
possible.
v
ABSTRACT
vi
reinforcements used were found to be 2 to 3 pieces, 2 to
mm with a 12 mm diameter.
16mm and 10mm for the main bars and temperature bars,
pesos.
vii
TABLE OF CONTENTS
PRELIMINARIES PAGE
Title Page
Approval Sheet i
Acceptance Sheet ii
Acknowledgement iii
Dedication v
Abstract vi
Table of Contents viii
List of Tables x
List of Figures xii
List of Appendices xv
I INTRODUCTION 1
Conceptual Review 16
Foreign and Local Studies 29
III METHODOLOGY 44
Site Investigation 44
Preparation of Working Plans 46
Structural Load Analysis Procedures 47
Structural Design Analysis Procedures 53
Project Cost 65
Duration of the Project 65
viii
PRESENTATION, ANALYSIS AND INTERPRETATION
IV 67
OF DATA
REFERENCES 182
APPENDICES 183
CURRICULUM VITAE
ix
LIST OF TABLES
TABLE PAGE
x
Summary Loads for Beams & Column
4.9 114
(Frame-9)
Summary Loads for Beams & Column
4.10 118
(Frame-10)
Summary Loads for Beams & Column
4.11 122
(Frame-11)
Summary Loads for Beams & Column
4.12 126
(Frame-12)
Summary Loads for Beams & Column
4.13 131
(Frame-13)
Summary Loads for Beams & Column
4.14 136
(Frame-14)
Summary Loads for Beams & Column
4.15 141
(Frame-15)
Summary Loads for Beams & Column
4.16 144
(Frame-16)
4.17 Schedule of Ground Floor Slabs 148
4.18 Schedule of Ground Floor Column 148
4.19 Schedule of Stair 149
4.20 Schedule of Ramps 149
4.21 Schedule of Second Floor Beam 153
4.22 Schedule of Second Floor Column 154
4.23 Schedule of Second Floor Slab 154
4.24 Schedule of Third Floor Beam 158
4.25 Schedule of Third Floor Column 158
4.26 Schedule of Third Floor Slab 159
4.27 Schedule of Roof Slab Beam 162
4.28 Schedule of Roof Slab 162
4.29 Bill of Materials and Estimate 169
4.30 Summary of Project Cost and Estimate 173
xi
LIST OF FIGURES
FIGURE PAGE
xii
4.20 Frame 4 Vertical Load Analysis 93
4.21 Frame 5 Lateral Load Analysis 96
4.22 Frame 5 Vertical Load Analysis 97
4.23 Frame 6 Lateral Load Analysis 100
4.24 Frame 5 Vertical Load Analysis 101
4.25 Frame 7 Lateral Load Analysis 104
4.26 Frame 7 Vertical Load Analysis 105
4.27 Frame 8 Lateral Load Analysis 108
4.28 Frame 8 Vertical Load Analysis 109
4.29 Frame 9 Lateral Load Analysis 112
4.30 Frame 9 Vertical Load Analysis 113
4.31 Frame 10 Vertical Load Analysis 116
4.32 Frame 10 Lateral Load Analysis 117
4.33 Frame 11 Lateral Load Analysis 120
4.34 Frame 11 Vertical Load Analysis 121
4.35 Frame 12 Lateral Load Analysis 125
4.36 Frame 12 Vertical Load Analysis 125
4.37 Frame 13 Lateral Load Analysis 130
4.38 Frame 13 Vertical Load Analysis 130
4.39 Frame 14 Lateral Load Analysis 135
4.40 Frame 14 Vertical Load Analysis 135
4.41 Frame 15 Lateral Load Analysis 139
4.42 Frame 15 Vertical Load Analysis 140
4.43 Frame 16 Lateral Load Analysis 142
4.44 Frame 16 Vertical Load Analysis 143
4.45 Foundation Plan 146
4.46 First Floor Framing Plan (Slab) 147
4.47 Second Floor Framing Plan (Beam) 151
4.48 Second Floor Framing Plan (Slab) 152
4.49 Third Floor Framing Plan (Beam) 156
4.50 Third Floor Framing Plan (Slab) 157
4.51 Rooftop Framing Plan (Beam) 161
4.52 Rooftop Framing Plan (Slab) 162
4.53 Detailed Design of Beam (RB-1) 164
4.54 Detailed Design of Slab (S-1) 165
4.55 Detailed Design of Column (C-1) 166
Elevation of Column-Footing (F1-C1,
4.56 166
C3, C5)
xiii
4.57 Typical Raft Footing 167
4.58 Raft Footing Detailed Section 168
4.59 Network Diagram 174
4.60 S-Curve 175
xiv
LIST OF APPENDICES
Appendix PAGE
A Gantt Chart 189
B Project Description 190
C Working Plans 191
D Structural Load Analysis 224
E Structural Design Analysis 247
F Project Cost and Estimate 280
xv
CHAPTER I
INTRODUCTION
venue for social and public events. This will also serve
1
2
events.
project.
guidelines.
following:
8
A. Residents
danger.
daily basis.
Definition of Terms
and seminars.
(DOH).
(Vocabulary, 2023).
human negligence.
globe.
(Erochko, 2020).
support responses.
13
the dead load, which includes its own weight, the weight
(www.boeingconsult.com).
structure (campus.extension.org).
(NBCP, 2010).
15
present study.
1. Evacuation Center
16
17
2011).
square mile.
2015.
C. Emergency Shelters
EXTENDED DISPLACEMENT
DISASTER EVENT
(>72 hours)
(<72 hours)
1.5 s.qm covered area per 3.5 s.qm covered area per
person person
per day.
Location
Areas required
2. Registration Area
3. Mud/disinfecting area
4. Storage Area
issues).
6. Eating area
people
16. Laundry
18. Crèche
2. Government Programs
therapeutic environment.
3. Training Center
Philippines)
Case Study
A. Foreign Studies
Findings
center.
strikes.
B. Local Studies
Background
communities?
(flooding, landslide,
relief response
community center
initiatives.
34
Design Specifications
emergency:
customs.
kph.
building.
presence.
supplies.
storage.
37
Use or Occupancy
Institutional
Space Requirements
meters.
39
WALKWAYS + PASSAGES
RAMPS
device
preferred
5. Policy Content
Office;
for PWDs
facilities
facilities
METHODOLOGY
Site Investigation
42
43
LIVE DEAD
USE OR LOAD COMPONENTS LOAD
OCCUPANCY (KPa) (KPa)
ROOFING
THEATER, 7.2 STONE CONCRETE 0.023
ASSEMBLY AREAS ELECTRICAL AND MECHANICAL 0.20
AND AUDITORIUM DUCT ALLOWANCE
3RD FLOOR
THEATER, 7.2 STONE CONCRETE 0.023
ASSEMBLY AREAS ELECTRICAL AND MECHANICAL 0.20
AND AUDITORIUM DUCT ALLOWANCE
SOLID FLAT TILE 1.10
2ND FLOOR
THEATER, 7.2 STONE CONCRETE 0.023
ASSEMBLY AREAS ELECTRICAL AND MECHANICAL 0.20
AND AUDITORIUM DUCT ALLOWANCE
SOLID FLAT TILE 1.10
44
GROUND FLOOR
THEATER, 7.2 STONE CONCRETE 0.023
ASSEMBLY AREAS ELECTRICAL AND MECHANICAL 0.20
AND AUDITORIUM DUCT ALLOWANCE
SOLID FLAT TILE 1.10
WHEELCHAIR RAMP 4.8
TABLE 3.1. (National Structural Code of the Philippines-
2015)
Wind Load
through time.
Section 207.5.11.1.
46
determined.
determined.
rotation.
at that joint.
in step 9.
Design of Footing.
that the beam will carry obtained from the vertical and
where:
3. Assume ρ.Ρ =
Beam. Wt
N = ; (actual) As = N(Ao)
11. Check for actual ρ and compare to the ρmin and ρmax:
(actual) ρ =
support:
Vu = Vmax – wud
proceed to step 5
where: ф = 0.75
5. Spacing of stirrups s=
1. Determine the value of the dead load and live load that
0.59ω)
(Coefficient Method)
obtained from
56
8. Calculation of Moment
Ma = Caneg(wu)(LS)2 ; Mb = Cbneg(wu)(LL)2
LL
LL
0.59ω)
11. Check for ρmin= and use the proper value for ρ.
stairs
2013).
Design of Stairs
will carry.
0.59ω)
59
stairs
Ag = ; h =
formula: eactual =
eccentricity
eccentricity
following:
x̅ = 𝐵/2; Ȳ = 𝐿/2
𝑄2𝑋′ 2 + 𝑄3𝑋′ 3 + ⋯ 𝑥 = 𝑋 ′ − 𝑋̅
61
𝑒𝑦 = 𝑌 ′ − Ȳ
equation:
Where: A = BL
𝑄4.
𝑄2 + 𝑄3 + 𝑄4 )]/2
𝐹 = 𝑄(𝑎𝑣) 𝑄1 + 𝑄2 + 𝑄3 + 𝑄4 = 𝑄𝑖(𝑎𝑣) 𝑄
Project Cost
B. Fajardo (2000).
Allocating Duration of
the Activity
bustle.
65
66
70
Figure 4.6. Third Floorplan
71
Figure 4.8. Roof Floorplan
Figure 4.7. Rooftop Floorplan
72
Figure 4.8. Front Elevation
73
Figure 4.9.Rear Elevation
74
Figure 4.10.Right Side Elevation
75
Figure 4.11.Left Side Elevation
76
Structural Load Analysis
Frames
77
78
load, and live load that act through the wall of the
the total load prior to the beam and column (see table
4.1).
79
80
COLUMN
AI 7.67 2.71 5.42 0.00 65.59 99.86 0.00 7.67 68.30 105.27
IQ 2.54 1.52 2.29 0.00 136.91 66.09 0.00 2.54 138.44 68.38
QY 0.51 0.51 0.76 0.00 108.42 32.32 0.00 0.51 108.92 33.09
BJ 3.84 5.42 10.83 0.00 110.52 0.00 0.00 3.84 115.94 10.83
JR 1.27 3.05 4.57 0.00 140.52 0.00 0.00 1.27 143.56 4.57
RZ 0.25 1.02 1.52 0.00 88.73 0.00 0.00 0.25 89.74 1.52
CK -3.84 5.42 10.83 0.00 107.22 0.00 0.00 -3.84 112.64 10.83
KS -1.27 3.05 4.57 0.00 39.93 0.00 0.00 -1.27 42.97 4.57
SA' -0.25 1.02 1.52 0.00 77.60 0.00 0.00 -0.25 78.62 1.52
DL 0.00 5.42 10.83 0.00 161.98 0.00 0.00 0.00 167.40 10.83
LT 0.00 3.05 4.57 0.00 128.27 0.00 0.00 0.00 131.32 4.57
TB' 0.00 1.02 1.52 0.00 130.76 0.00 0.00 0.00 131.78 1.52
EM 3.84 5.42 10.83 0.00 166.25 0.00 0.00 3.84 171.66 10.83
MU 1.27 3.05 4.57 0.00 104.98 0.00 0.00 1.27 108.02 4.57
UC' 0.25 1.02 1.52 0.00 126.85 0.00 0.00 0.25 127.87 1.52
FN -3.84 5.42 10.83 0.00 47.24 0.00 0.00 -3.84 52.65 10.83
NV -1.27 3.05 4.57 0.00 77.60 0.00 0.00 -1.27 80.65 4.57
VD' -0.25 1.02 1.52 0.00 161.98 0.00 0.00 -0.25 163.00 1.52
GO 0.00 5.42 10.83 0.00 128.27 0.00 0.00 0.00 133.69 10.83
OW 0.00 3.05 4.57 0.00 130.76 0.00 0.00 0.00 133.81 4.57
WE' 0.00 1.02 1.52 0.00 166.25 0.00 0.00 0.00 167.26 1.52
HP -7.67 2.71 5.42 0.00 104.98 -114.17 0.00 -7.67 107.68 -108.76
PX -2.54 1.52 2.29 0.00 126.85 -75.57 0.00 -2.54 128.38 -73.28
XF' -0.51 0.51 0.76 0.00 47.24 -36.96 0.00 -0.51 47.75 -36.20
81
82
load, and live load that act through the wall of the
84
COLUMN
AI 5.42 15.35 10.83 0.00 480.63 236.86 0.00 5.42 495.98 247.69
IQ 3.05 5.08 4.57 0.00 316.52 155.98 0.00 3.05 321.59 160.55
QY 1.02 1.02 1.52 0.00 152.40 75.11 0.00 1.02 153.42 76.63
BJ 10.83 7.67 21.67 0.00 1003.24 0.00 0.00 10.83 1010.91 21.67
JR 6.09 2.54 9.14 0.00 660.68 0.00 0.00 6.09 663.22 9.14
RZ 2.03 0.51 3.05 0.00 318.12 0.00 0.00 2.03 318.63 3.05
CK 10.83 -7.67 21.67 0.00 794.43 0.00 0.00 10.83 786.76 21.67
KS 6.09 -2.54 9.14 0.00 523.17 0.00 0.00 6.09 520.63 9.14
SA' 2.03 -0.51 3.05 0.00 251.91 0.00 0.00 2.03 251.40 3.05
DL 10.83 0.00 21.67 0.00 782.54 0.00 0.00 10.83 782.54 21.67
LT 6.09 0.00 9.14 0.00 515.34 0.00 0.00 6.09 515.34 9.14
TB' 2.03 0.00 3.05 0.00 248.14 0.00 0.00 2.03 248.14 3.05
EM 10.83 7.67 21.67 0.00 1029.65 0.00 0.00 10.83 1037.32 21.67
MU 6.09 2.54 9.14 0.00 678.07 0.00 0.00 6.09 680.61 9.14
UC' 2.03 0.51 3.05 0.00 326.49 0.00 0.00 2.03 327.00 3.05
FN 10.83 -7.67 21.67 0.00 785.53 0.00 0.00 10.83 777.85 21.67
NV 6.09 -2.54 9.14 0.00 517.31 0.00 0.00 6.09 514.77 9.14
VD' 2.03 -0.51 3.05 0.00 249.08 0.00 0.00 2.03 248.58 3.05
GO 10.83 0.00 21.67 0.00 785.66 0.00 0.00 10.83 785.66 21.67
OW 6.09 0.00 9.14 0.00 517.39 0.00 0.00 6.09 517.39 9.14
WE' 2.03 0.00 3.05 0.00 249.13 0.00 0.00 2.03 249.13 3.05
HP 5.42 -15.35 10.83 0.00 514.65 -270.82 0.00 5.42 499.30 -259.98
PX 3.05 -5.08 4.57 0.00 338.92 -178.34 0.00 3.05 333.84 -173.77
XF' 1.02 -1.02 1.52 0.00 163.19 -85.87 0.00 1.02 162.17 -84.35
85
86
load, and live load that act through the wall of the
the total load prior to beam and column (see table 4.3).
88
COLUMN
AI 2.26 6.40 4.51 0.00 410.33 202.21 0.00 2.26 416.73 206.73
IQ 1.27 2.12 1.90 0.00 270.30 133.21 0.00 1.27 272.42 135.11
QY 0.42 0.42 0.63 0.00 130.27 64.20 0.00 0.42 130.69 64.83
BJ 4.51 3.20 9.03 0.00 856.50 0.00 0.00 4.51 859.70 9.03
JR 2.54 1.06 3.81 0.00 564.21 0.00 0.00 2.54 565.27 3.81
RZ 0.85 0.21 1.27 0.00 271.92 0.00 0.00 0.85 272.13 1.27
CK 4.51 -3.20 9.03 0.00 678.24 0.00 0.00 4.51 675.04 9.03
KS 2.54 -1.06 3.81 0.00 446.78 0.00 0.00 2.54 445.72 3.81
SA' 0.85 -0.21 1.27 0.00 215.33 0.00 0.00 0.85 215.11 1.27
DL 4.51 0.00 9.03 0.00 668.09 0.00 0.00 4.51 668.09 9.03
LT 2.54 0.00 3.81 0.00 440.09 0.00 0.00 2.54 440.09 3.81
TB' 0.85 0.00 1.27 0.00 212.10 0.00 0.00 0.85 212.10 1.27
EM 4.51 3.20 9.03 0.00 879.05 0.00 0.00 4.51 882.25 9.03
MU 2.54 1.06 3.81 0.00 579.07 0.00 0.00 2.54 580.12 3.81
UC' 0.85 0.21 1.27 0.00 279.08 0.00 0.00 0.85 279.29 1.27
FN 4.51 -3.20 9.03 0.00 670.64 0.00 0.00 4.51 667.44 9.03
NV 2.54 -1.06 3.81 0.00 441.77 0.00 0.00 2.54 440.72 3.81
VD' 0.85 -0.21 1.27 0.00 212.91 0.00 0.00 0.85 212.70 1.27
GO 4.51 0.00 9.03 0.00 670.75 0.00 0.00 4.51 670.75 9.03
OW 2.54 0.00 3.81 0.00 441.85 0.00 0.00 2.54 441.85 3.81
WE' 0.85 0.00 1.27 0.00 212.95 0.00 0.00 0.85 212.95 1.27
HP 2.26 -6.40 4.51 0.00 439.37 -231.21 0.00 2.26 432.98 -226.69
PX 1.27 -2.12 1.90 0.00 289.43 -152.30 0.00 1.27 287.32 -150.40
XF' 0.42 -0.42 0.63 0.00 139.49 -73.40 0.00 0.42 139.07 -72.77
89
90
load, and live load that act through the wall of the
the total load prior to the beam and column (see table
4.4).
92
COLUMN
AI 3.16 8.95 6.32 0.00 74.98 37.88 0.00 3.16 83.93 44.20
IQ 1.78 2.96 2.67 0.00 49.94 25.37 0.00 1.78 52.90 28.03
QY 0.59 0.59 0.89 0.00 24.90 12.85 0.00 0.59 25.49 13.74
BJ 6.32 4.48 12.64 0.00 145.33 0.00 0.00 6.32 149.81 12.64
JR 3.56 1.48 5.33 0.00 95.09 0.00 0.00 3.56 96.57 5.33
RZ 1.19 0.30 1.78 0.00 44.85 0.00 0.00 1.19 45.14 1.78
CK 6.32 -4.48 12.64 0.00 243.26 0.00 0.00 6.32 238.78 12.64
KS 3.56 -1.48 5.33 0.00 167.58 0.00 0.00 3.56 166.09 5.33
SA' 1.19 -0.30 1.78 0.00 91.89 0.00 0.00 1.19 91.60 1.78
DL 6.32 0.00 12.64 0.00 473.13 0.00 0.00 6.32 473.13 12.64
LT 3.56 0.00 5.33 0.00 298.47 0.00 0.00 3.56 298.47 5.33
TB' 1.19 0.00 1.78 0.00 123.82 0.00 0.00 1.19 123.82 1.78
EM 6.32 4.48 12.64 0.00 519.29 0.00 0.00 6.32 523.76 12.64
MU 3.56 1.48 5.33 0.00 313.89 0.00 0.00 3.56 315.37 5.33
UC' 1.19 0.30 1.78 0.00 108.50 0.00 0.00 1.19 108.79 1.78
FN 6.32 -4.48 12.64 0.00 470.57 0.00 0.00 6.32 466.09 12.64
NV 3.56 -1.48 5.33 0.00 296.51 0.00 0.00 3.56 295.02 5.33
VD' 1.19 -0.30 1.78 0.00 122.45 0.00 0.00 1.19 122.15 1.78
GO 6.32 0.00 12.64 0.00 235.66 0.00 0.00 6.32 235.66 12.64
OW 3.56 0.00 5.33 0.00 162.32 0.00 0.00 3.56 162.32 5.33
WE' 1.19 0.00 1.78 0.00 88.99 0.00 0.00 1.19 88.99 1.78
HP 3.16 -8.95 6.32 0.00 78.30 -41.19 0.00 3.16 69.35 -34.87
PX 1.78 -2.96 2.67 0.00 51.22 -26.65 0.00 1.78 48.26 -23.98
XF' 0.59 -0.59 0.89 0.00 24.14 -12.10 0.00 0.59 23.55 -11.21
93
94
load, and live load that act through the wall of the
the total load prior to the beam and column (see table
4.5).
96
COLUMN
AF 7.90 33.58 15.80 0.00 181.63 42.01 0.00 7.90 215.20 57.81
FK 4.44 11.11 6.67 0.00 110.57 25.57 0.00 4.44 121.68 32.24
KP 1.48 2.22 2.22 0.00 39.51 9.14 0.00 1.48 41.73 11.36
BG 15.80 -11.19 31.60 0.00 636.31 0.00 0.00 15.80 625.12 31.60
GL 8.89 -3.70 13.33 0.00 387.36 0.00 0.00 8.89 383.65 13.33
LQ 2.96 -0.74 4.44 0.00 138.41 0.00 0.00 2.96 137.67 4.44
CH 15.80 0.00 31.60 0.00 736.39 0.00 0.00 15.80 736.39 31.60
HM 8.89 0.00 13.33 0.00 448.28 0.00 0.00 8.89 448.28 13.33
MR 2.96 0.00 4.44 0.00 160.18 0.00 0.00 2.96 160.18 4.44
DI 15.80 11.19 31.60 0.00 636.31 0.00 0.00 15.80 647.50 31.60
IN 8.89 3.70 13.33 0.00 387.36 0.00 0.00 8.89 391.06 13.33
NS 2.96 0.74 4.44 0.00 138.41 0.00 0.00 2.96 139.15 4.44
EJ 7.90 -33.58 15.80 0.00 181.63 -42.01 0.00 7.90 148.05 -26.21
JO 4.44 -11.11 6.67 0.00 110.57 -25.57 0.00 4.44 99.46 -18.91
OT 1.48 -2.22 2.22 0.00 39.51 -9.14 0.00 1.48 37.28 -6.92
97
98
load, and live load that act through the wall of the
the total load prior to the beam and column (see table
4.6).
100
COLUMN
IQ 0.59 0.59 0.89 0.00 91.89 25.02 0.00 1.98 95.71 28.97
AI 1.98 3.82 3.95 0.00 473.13 12.51 0.00 0.59 473.72 13.40
BJ 3.95 1.91 7.90 0.00 298.47 0.00 0.00 3.95 300.38 7.90
JR 1.19 0.30 1.78 0.00 123.82 0.00 0.00 1.19 124.12 1.78
CK 3.95 -1.91 7.90 0.00 519.29 0.00 0.00 3.95 517.38 7.90
KS 1.19 -0.30 1.78 0.00 313.89 0.00 0.00 1.19 313.60 1.78
DL 3.95 0.00 7.90 0.00 108.50 0.00 0.00 3.95 108.50 7.90
LT 1.19 0.00 1.78 0.00 470.57 0.00 0.00 1.19 470.57 1.78
EM 3.95 1.91 7.90 0.00 296.51 0.00 0.00 3.95 298.41 7.90
MU 1.19 0.30 1.78 0.00 122.45 0.00 0.00 1.19 122.74 1.78
FN 3.95 -1.91 7.90 0.00 235.66 0.00 0.00 3.95 233.75 7.90
NV 1.19 -0.30 1.78 0.00 162.32 0.00 0.00 1.19 162.03 1.78
GO 3.95 0.00 7.90 0.00 88.99 0.00 0.00 3.95 88.99 7.90
OW 1.19 0.00 1.78 0.00 78.30 0.00 0.00 1.19 78.30 -23.25
HP 1.98 -3.82 3.95 0.00 51.22 -25.02 0.00 1.98 47.40 -8.56
PX 0.59 -0.59 0.89 0.00 24.14 -12.51 0.00 0.59 23.55 -11.62
101
102
load, and live load that act through the wall of the
the total load prior to the beam and column (see table
4.7).
104
COLUMN
AI 2.26 4.36 4.51 0.00 334.04 69.01 0.00 2.26 112.03 73.52
IQ 0.68 0.68 1.02 0.00 107.66 34.50 0.00 0.68 334.72 35.52
BJ 4.51 2.18 9.03 0.00 220.05 0.00 0.00 4.51 222.23 9.03
JR 1.35 0.34 2.03 0.00 106.05 0.00 0.00 1.35 106.39 2.03
CK 4.51 -2.18 9.03 0.00 439.53 0.00 0.00 4.51 437.34 9.03
KS 1.35 -0.34 2.03 0.00 289.53 0.00 0.00 1.35 289.19 2.03
DL 4.51 0.00 9.03 0.00 139.54 0.00 0.00 4.51 139.54 9.03
LT 1.35 0.00 2.03 0.00 335.32 0.00 0.00 1.35 335.32 2.03
EM 4.51 2.18 9.03 0.00 220.89 0.00 0.00 4.51 223.07 9.03
MU 1.35 0.34 2.03 0.00 106.46 0.00 0.00 1.35 106.79 2.03
FN 4.51 -2.18 9.03 0.00 335.37 0.00 0.00 4.51 333.19 9.03
NV 1.35 -0.34 2.03 0.00 220.92 0.00 0.00 1.35 220.58 2.03
GO 4.51 0.00 9.03 0.00 106.47 0.00 0.00 4.51 106.47 9.03
OW 1.35 0.00 2.03 0.00 219.69 0.00 0.00 1.35 219.69 -66.98
HP 2.26 -4.36 4.51 0.00 144.72 -69.01 0.00 2.26 140.35 29.99
PX 0.68 -0.68 1.02 0.00 69.75 -34.50 0.00 0.68 69.07 -33.49
105
106
load, and live load that act through the wall of the
the total load prior to beam and column (see table 4.8).
108
COLUMN
AI 1.69 3.27 3.39 0.00 329.91 161.75 0.00 0.51 108.92 162.51
IQ 0.51 0.51 0.76 0.00 108.42 80.88 0.00 1.69 333.19 84.26
BJ 3.39 1.64 6.77 0.00 218.35 0.00 0.00 3.39 219.99 6.77
JR 1.02 0.25 1.52 0.00 106.79 0.00 0.00 1.02 107.05 1.52
CK 3.39 -1.64 6.77 0.00 434.09 0.00 0.00 3.39 432.46 6.77
KS 1.02 -0.25 1.52 0.00 287.31 0.00 0.00 1.02 287.05 1.52
DL 3.39 0.00 6.77 0.00 140.52 0.00 0.00 3.39 140.52 6.77
LT 1.02 0.00 1.52 0.00 331.17 0.00 0.00 1.02 331.17 1.52
EM 3.39 1.64 6.77 0.00 219.19 0.00 0.00 3.39 220.82 6.77
MU 1.02 0.25 1.52 0.00 107.20 0.00 0.00 1.02 107.46 1.52
FN 3.39 -1.64 6.77 0.00 331.23 0.00 0.00 3.39 329.59 6.77
NV 1.02 -0.25 1.52 0.00 219.22 0.00 0.00 1.02 218.97 1.52
GO 3.39 0.00 6.77 0.00 107.22 0.00 0.00 3.39 107.22 6.77
OW 1.02 0.00 1.52 0.00 216.97 0.00 0.00 1.02 216.97 163.28
HP 1.69 -3.27 3.39 0.00 143.60 -161.75 0.00 1.69 140.33 84.26
PX 0.51 -0.51 0.76 0.00 70.23 -80.88 0.00 0.51 69.73 81.64
109
110
load, and live load that act through the wall of the
the total load prior to the beam and column (see table
4.9).
112
COLUMN
IQ 0.51 0.51 0.76 0.00 108.42 67.53 0.00 0.51 108.92 68.30
AI 1.69 3.27 3.39 0.00 329.91 33.77 0.00 1.69 333.19 37.15
BJ 3.39 1.64 6.77 0.00 218.35 0.00 0.00 3.39 219.99 6.77
JR 1.02 0.25 1.52 0.00 106.79 0.00 0.00 1.02 107.05 1.52
CK 3.39 -1.64 6.77 0.00 434.09 0.00 0.00 3.39 432.46 6.77
KS 1.02 -0.25 1.52 0.00 287.31 0.00 0.00 1.02 287.05 1.52
DL 3.39 0.00 6.77 0.00 140.52 0.00 0.00 3.39 140.52 6.77
LT 1.02 0.00 1.52 0.00 331.17 0.00 0.00 1.02 331.17 1.52
EM 3.39 1.64 6.77 0.00 219.19 0.00 0.00 3.39 220.82 6.77
MU 1.02 0.25 1.52 0.00 107.20 0.00 0.00 1.02 107.46 1.52
FN 3.39 -1.64 6.77 0.00 331.23 0.00 0.00 3.39 329.59 6.77
NV 1.02 -0.25 1.52 0.00 219.22 0.00 0.00 1.02 218.97 1.52
GO 3.39 0.00 6.77 0.00 107.22 0.00 0.00 3.39 107.22 6.77
OW 1.02 0.00 1.52 0.00 216.97 0.00 0.00 1.02 216.97 69.06
HP 1.69 -3.27 3.39 0.00 143.60 -67.53 0.00 1.69 140.33 37.15
PX 0.51 -0.51 0.76 0.00 70.23 -33.77 0.00 0.51 69.73 34.53
113
114
load, and live load that act through the wall of the
the total load prior to beam and column (see table 4.10).
116
COLUMN
AF 2.37 3.36 4.74 0.00 239.68 240.59 0.00 2.37 243.03 245.33
FK 1.33 1.11 2.00 0.00 154.66 155.25 0.00 1.33 155.77 157.25
KP 0.44 0.22 0.67 0.00 69.65 69.91 0.00 0.44 69.87 70.58
BG 4.74 0.00 9.48 0.00 473.80 0.00 0.00 4.74 473.80 9.48
GL 2.67 0.00 4.00 0.00 305.76 0.00 0.00 2.67 305.76 4.00
LQ 0.89 0.00 1.33 0.00 137.71 0.00 0.00 0.89 137.71 1.33
CH 4.74 0.00 9.48 0.00 490.48 0.00 0.00 4.74 490.48 9.48
HM 2.67 0.00 4.00 0.00 316.49 0.00 0.00 2.67 316.49 4.00
MR 0.89 0.00 1.33 0.00 142.49 0.00 0.00 0.89 142.49 1.33
DI 4.74 6.72 9.48 0.00 365.42 0.00 0.00 4.74 372.14 9.48
IN 2.67 2.22 4.00 0.00 237.34 0.00 0.00 2.67 239.56 4.00
NS 0.89 0.44 1.33 0.00 109.27 0.00 0.00 0.89 109.71 1.33
EJ 2.37 -10.07 4.74 0.00 5.87 59.58 0.00 2.37 -4.20 64.32
JO 1.33 -3.33 2.00 0.00 4.66 37.89 0.00 1.33 1.33 39.89
OT 0.44 -0.67 0.67 0.00 3.45 16.21 0.00 0.44 2.79 16.88
117
118
load, and live load that act through the wall of the
the total load prior to the beam and column (see table
4.11).
120
COLUMN
AF 4.74 6.72 9.48 0.00 498.03 499.90 0.00 4.74 504.74 509.38
FK 2.67 2.22 4.00 0.00 328.04 329.28 0.00 2.67 330.26 333.28
KP 0.89 0.44 1.33 0.00 158.06 158.65 0.00 0.89 158.50 159.99
BG 9.48 0.00 18.96 0.00 984.67 0.00 0.00 9.48 984.67 18.96
GL 5.33 0.00 8.00 0.00 648.59 0.00 0.00 5.33 648.59 8.00
LQ 1.78 0.00 2.67 0.00 312.50 0.00 0.00 1.78 312.50 2.67
CH 9.48 0.00 18.96 0.00 1018.88 0.00 0.00 9.48 1018.88 18.96
HM 5.33 0.00 8.00 0.00 671.12 0.00 0.00 5.33 671.12 8.00
MR 1.78 0.00 2.67 0.00 323.36 0.00 0.00 1.78 323.36 2.67
DI 9.48 13.43 18.96 0.00 781.28 0.00 0.00 9.48 794.71 18.96
IN 5.33 4.44 8.00 0.00 514.62 0.00 0.00 5.33 519.06 8.00
NS 1.78 0.89 2.67 0.00 247.96 0.00 0.00 1.78 248.84 2.67
EJ 4.74 -20.15 9.48 0.00 24.69 115.90 0.00 4.74 4.55 125.38
JO 2.67 -6.67 4.00 0.00 16.26 76.34 0.00 2.67 9.60 80.34
OT 0.89 -1.33 1.33 0.00 7.84 36.78 0.00 0.89 6.50 38.12
121
122
load, and live load that act through the wall of the
the total load prior to the beam and column (see table
4.12).
Figure 4.35. Frame 12 Lateral Load Analysis
123
Table 4.12. Summary Loads for Beams & Column (Frame-12)
FRAME
12 Lateral Loads Vertical Loads Total Loads
Member Shear Axial Moment Shear Axial Moment M.Midspan Shear Axial Moment
BEAM
K'L' 0.14 -3.59 -0.41 341.15 0.00 266.71 246.86 341.29 -3.59 266.29
L'M' 0.14 -3.04 -0.41 336.20 0.00 259.38 239.39 336.34 -3.04 258.97
M'N' 0.14 -2.49 -0.41 353.68 0.00 281.76 270.22 353.82 -2.49 281.35
N'O' 0.41 -1.94 -0.41 199.10 0.00 199.26 -24.34 199.51 -1.94 198.85
O'P' 0.17 -1.38 -0.41 90.45 0.00 27.69 74.18 90.62 -1.38 27.27
P'Q' 0.17 -0.83 -0.41 103.07 0.00 77.39 54.89 103.24 -0.83 76.97
Q'R' 0.17 -0.28 -0.41 99.53 0.00 63.99 59.35 99.69 -0.28 63.58
YZ 0.35 -5.23 -1.04 341.24 0.00 286.68 227.15 341.59 -5.23 285.63
ZA' 0.35 -4.94 -1.04 335.93 0.00 278.82 219.14 336.28 -4.94 277.78
A'B' 0.35 -4.65 -1.04 354.69 0.00 302.84 252.29 355.04 -4.65 301.79
B'C' 1.04 -4.37 -1.04 205.83 0.00 214.29 -27.34 206.88 -4.37 213.25
C'D' 0.42 -4.08 -1.04 90.69 0.00 29.25 73.16 91.11 -4.08 28.20
D'E' 0.42 -3.79 -1.04 100.39 0.00 77.76 47.73 100.81 -3.79 76.72
E'F' 0.42 -3.50 -1.04 110.09 0.00 77.76 73.16 110.51 -3.50 76.72
F'G' 0.63 -2.94 -0.63 20.79 0.00 29.25 -27.34 21.42 -2.94 28.62
G'H' 0.21 -2.10 -0.63 325.17 0.00 214.29 252.29 325.38 -2.10 213.66
H'I' 0.21 -1.26 -0.63 343.93 0.00 302.84 219.14 344.14 -1.26 302.21
I'J' 0.21 -0.42 -0.63 338.62 0.00 278.82 227.15 338.83 -0.42 278.19
124
MN 0.67 -5.60 -2.00 341.24 0.00 286.68 227.15 341.91 -5.60 284.67
NO 0.67 -5.07 -2.00 335.93 0.00 278.82 219.14 336.60 -5.07 276.82
OP 0.67 -4.54 -2.00 354.69 0.00 302.84 252.29 355.36 -4.54 300.83
PQ 2.00 -4.00 -2.00 205.83 0.00 214.29 -27.34 207.84 -4.00 212.29
QR 0.80 -3.47 -2.00 90.69 0.00 29.25 73.16 91.49 -3.47 27.24
RS 0.80 -2.94 -2.00 100.39 0.00 77.76 47.73 101.19 -2.94 75.76
ST 0.80 -2.40 -2.00 110.09 0.00 77.76 73.16 110.89 -2.40 75.76
TU 2.00 -1.87 -2.00 20.79 0.00 29.25 -27.34 22.79 -1.87 27.24
UV 0.67 -1.33 -2.00 325.17 0.00 214.29 252.29 325.84 -1.33 212.29
VW 0.67 -0.80 -2.00 343.93 0.00 302.84 219.14 344.60 -0.80 300.83
WX 0.67 -0.27 -2.00 338.62 0.00 278.82 227.15 339.29 -0.27 276.82
COLUMN
AM 0.69 1.15 1.37 0.00 835.19 840.06 0.00 0.69 836.34 841.44
MY 0.42 0.49 0.63 0.00 549.76 553.39 0.00 0.42 550.24 554.02
YK' 0.28 0.14 0.41 0.00 264.32 266.71 0.00 0.28 264.46 267.12
BN 1.37 0.00 2.75 0.00 1649.57 0.00 0.00 1.37 1649.57 2.75
NZ 0.84 0.00 1.26 0.00 1086.63 0.00 0.00 0.84 1086.63 1.26
ZL' 0.55 0.00 0.83 0.00 523.70 0.00 0.00 0.55 523.70 0.83
CO 1.37 0.00 2.75 0.00 1720.15 0.00 0.00 1.37 1720.15 2.75
OA' 0.84 0.00 1.26 0.00 1133.14 0.00 0.00 0.84 1133.14 1.26
A'M' 0.55 0.00 0.83 0.00 546.13 0.00 0.00 0.55 546.13 0.83
DP 1.37 2.31 2.75 0.00 1337.66 0.00 0.00 1.37 1339.97 2.75
125
PB' 0.84 0.97 1.26 0.00 881.07 0.00 0.00 0.84 882.04 1.26
B'N' 0.55 0.28 0.83 0.00 424.47 0.00 0.00 0.55 424.75 0.83
EQ 1.37 -2.08 2.75 0.00 224.71 0.00 0.00 1.37 222.63 2.75
QC' 0.84 -0.88 1.26 0.00 148.67 0.00 0.00 0.84 147.80 1.26
C'O' 0.55 -0.25 0.83 0.00 72.63 0.00 0.00 0.55 72.38 0.83
FR 1.37 0.00 2.75 0.00 526.75 0.00 0.00 1.37 526.75 2.75
RD' 0.84 0.00 1.26 0.00 349.94 0.00 0.00 0.84 349.94 1.26
D'P' 0.55 0.00 0.83 0.00 173.13 0.00 0.00 0.55 173.13 0.83
GS 1.37 0.00 2.75 0.00 510.59 0.00 0.00 1.37 510.59 2.75
SE' 0.84 0.00 1.26 0.00 333.78 0.00 0.00 0.84 333.78 1.26
E'Q' 0.55 0.00 0.83 0.00 156.97 0.00 0.00 0.55 156.97 0.83
HT 1.37 1.25 2.75 0.00 233.19 -68.30 0.00 1.37 234.44 -65.55
TF' 0.84 0.05 1.26 0.00 157.16 -68.30 0.00 0.84 157.20 -67.04
F'R' 0.28 -0.17 0.41 0.00 81.12 -68.30 0.00 0.28 80.95 -67.89
IU 1.37 -1.76 2.75 0.00 913.19 0.00 0.00 1.37 911.44 2.75
UG' 0.84 -0.42 1.26 0.00 456.60 0.00 0.00 0.84 456.18 1.26
JV 1.37 0.00 2.75 0.00 1174.02 0.00 0.00 1.37 1174.02 2.75
VH' 0.84 0.00 1.26 0.00 587.01 0.00 0.00 0.84 587.01 1.26
KW 1.37 0.00 2.75 0.00 1125.88 0.00 0.00 1.37 1125.88 2.75
WI' 0.84 0.00 1.26 0.00 562.94 0.00 0.00 0.84 562.94 1.26
LX 0.69 -0.88 1.37 0.00 570.87 -573.36 0.00 0.69 569.99 -571.98
XJ' 0.42 -0.21 0.63 0.00 285.43 -286.68 0.00 0.42 285.22 -286.05
126
127
load, and live load that act through the wall of the
the total load prior to beam and column (see table 4.13).
Figure 4.37. Frame 13 Lateral Load Analysis
128
Table 4.13. Summary Loads for Beams & Column (Frame-13)
130
B'N' 0.55 0.27 0.82 0.00 187.96 0.00 0.00 0.55 188.24 0.82
EQ 1.52 -2.22 3.04 0.00 396.14 0.00 0.00 1.52 393.92 3.04
QC' 0.90 -0.90 1.35 0.00 260.52 0.00 0.00 0.90 259.62 1.35
C'O' 0.55 -0.25 0.82 0.00 124.90 0.00 0.00 0.55 124.65 0.82
FR 1.52 0.00 3.04 0.00 724.66 0.00 0.00 1.52 724.66 3.04
RD' 0.90 0.00 1.35 0.00 478.49 0.00 0.00 0.90 478.49 1.35
D'P' 0.55 0.00 0.82 0.00 232.32 0.00 0.00 0.55 232.32 0.82
GS 1.52 0.00 3.04 0.00 709.22 0.00 0.00 1.52 709.22 3.04
SE' 0.90 0.00 1.35 0.00 463.05 0.00 0.00 0.90 463.05 1.35
E'Q' 0.55 0.00 0.82 0.00 216.87 0.00 0.00 0.55 216.87 0.82
HT 1.52 1.40 3.04 0.00 382.21 -93.15 0.00 1.52 383.61 -90.10
TF' 0.90 0.08 1.35 0.00 246.59 -93.15 0.00 0.90 246.67 -91.79
F'R' 0.27 -0.16 0.41 0.00 110.97 -93.15 0.00 0.27 110.80 -92.73
IU 1.52 -1.92 3.04 0.00 402.88 0.00 0.00 1.52 400.96 3.04
UG' 0.90 -0.45 1.35 0.00 201.44 0.00 0.00 0.90 200.99 1.35
JV 1.52 0.00 3.04 0.00 590.34 0.00 0.00 1.52 590.34 3.04
VH' 0.90 0.00 1.35 0.00 295.17 0.00 0.00 0.90 295.17 1.35
KW 1.52 0.00 3.04 0.00 562.01 0.00 0.00 1.52 562.01 3.04
WI' 0.90 0.00 1.35 0.00 281.00 0.00 0.00 0.90 281.00 1.35
LX 0.76 -0.96 1.52 0.00 285.66 -287.13 0.00 0.76 284.70 -285.60
XJ' 0.45 -0.23 0.68 0.00 142.83 -143.56 0.00 0.45 142.60 -142.89
131
132
load, and live load that act through the wall of the
the total load prior to beam and column (see table 4.14).
Figure 4.39. Frame 14 Lateral Load Analysis
134
OP 1.63 -12.82 -4.90 359.40 0.00 182.47 103.57 361.03 -12.82 177.57
PQ 4.90 -11.31 -4.90 162.28 0.00 120.30 -61.98 167.18 -11.31 115.40
QR 1.96 -9.80 -4.90 259.82 0.00 70.91 78.57 261.78 -9.80 66.01
RS 1.96 -8.30 -4.90 282.23 0.00 126.95 49.44 284.19 -8.30 122.05
ST 1.96 -6.79 -4.90 304.64 0.00 126.95 78.57 306.60 -6.79 122.05
TU 4.90 -5.28 -4.90 63.50 0.00 70.91 -61.98 68.41 -5.28 66.01
UV 1.63 -3.77 -4.90 317.95 0.00 120.30 103.57 319.59 -3.77 115.40
VW 1.63 -2.26 -4.90 344.29 0.00 182.47 80.02 345.92 -2.26 177.57
WX 1.63 -0.75 -4.90 336.85 0.00 165.64 85.63 338.48 -0.75 160.74
COLUMN
AM 1.72 2.63 3.45 0.00 497.96 501.37 0.00 1.72 500.59 504.82
MY 0.97 0.99 1.45 0.00 327.71 330.25 0.00 0.97 328.70 331.70
YK' 0.51 0.25 0.76 0.00 157.46 159.12 0.00 0.51 157.71 159.88
BN 3.45 0.00 6.89 0.00 981.38 0.00 0.00 3.45 981.38 6.89
NZ 1.94 0.00 2.91 0.00 646.42 0.00 0.00 1.94 646.42 2.91
ZL' 1.02 0.00 1.52 0.00 311.46 0.00 0.00 1.02 311.46 1.52
CO 3.45 0.00 6.89 0.00 1030.81 0.00 0.00 3.45 1030.81 6.89
OA' 1.94 0.00 2.91 0.00 678.97 0.00 0.00 1.94 678.97 2.91
A'M' 1.02 0.00 1.52 0.00 327.12 0.00 0.00 1.02 327.12 1.52
DP 3.45 5.25 6.89 0.00 704.17 0.00 0.00 3.45 709.42 6.89
PB' 1.94 1.99 2.91 0.00 464.05 0.00 0.00 1.94 466.04 2.91
B'N' 1.02 0.51 1.52 0.00 223.94 0.00 0.00 1.02 224.45 1.52
EQ 3.45 -4.73 6.89 0.00 472.12 0.00 0.00 3.45 467.39 6.89
QC' 1.94 -1.79 2.91 0.00 310.46 0.00 0.00 1.94 308.67 2.91
C'O' 1.02 -0.46 1.52 0.00 148.80 0.00 0.00 1.02 148.34 1.52
135
FR 3.45 0.00 6.89 0.00 863.66 0.00 0.00 3.45 863.66 6.89
RD' 1.94 0.00 2.91 0.00 570.22 0.00 0.00 1.94 570.22 2.91
D'P' 1.02 0.00 1.52 0.00 276.78 0.00 0.00 1.02 276.78 1.52
GS 3.45 0.00 6.89 0.00 845.25 0.00 0.00 3.45 845.25 6.89
SE' 1.94 0.00 2.91 0.00 551.82 0.00 0.00 1.94 551.82 2.91
E'Q' 1.02 0.00 1.52 0.00 258.38 0.00 0.00 1.02 258.38 1.52
HT 3.45 3.20 6.89 0.00 455.53 -110.97 0.00 3.45 458.73 -104.08
TF' 1.94 0.26 2.91 0.00 293.87 -110.97 0.00 1.94 294.13 -108.06
F'R' 0.51 -0.30 0.76 0.00 132.21 -110.97 0.00 0.51 131.90 -110.21
IU 3.45 -4.24 6.89 0.00 480.23 0.00 0.00 3.45 475.99 6.89
UG' 1.94 -0.97 2.91 0.00 240.12 0.00 0.00 1.94 239.15 2.91
JV 3.45 0.00 6.89 0.00 703.68 0.00 0.00 3.45 703.68 6.89
VH' 1.94 0.00 2.91 0.00 351.84 0.00 0.00 1.94 351.84 2.91
KW 3.45 0.00 6.89 0.00 669.91 0.00 0.00 3.45 669.91 6.89
WI' 1.94 0.00 2.91 0.00 334.96 0.00 0.00 1.94 334.96 2.91
LX 1.72 -2.12 3.45 0.00 340.50 -342.25 0.00 1.72 338.38 -338.81
XJ' 0.97 -0.48 1.45 0.00 170.25 -171.13 0.00 0.97 169.77 -169.67
136
137
load, and live load that act through the wall of the
the total load prior to beam and column (see table 4.15).
139
140
load, and live load that act through the wall of the
the total load prior to beam and column (see table 4.16).
142
143
480mm, and the column sizes for square tie are 330mm by
respectively.
Figure 4.45. Foundation Plan
144
Figure 4.46. First Floor Framing Plan 145
Table 4.17. Schedule of Ground Floor Slabs
DIMENSION (mm) SHORT DIRECTION LONG DIRECTION
TYPE
MARK OF RSB SPACING SPACING @ SPACING @ SPACING @
Length Width Height
SLABS @ MIDDLE COLUMN MIDDLE COLUMN
(Lb) (L) (t)
STRIP STRIP STRIP STRIP
RS-1 6000mm 3000mm 180mm T.W.S 12mm 140mm 140mm
RS-2 6000mm 3000mm 180mm T.W.S 12mm 140mm 130mm 140mm
RS-3 3000mm 3000mm 180mm T.W.S 12mm 140mm 140mm
RS-4 5000mm 3000mm 180mm T.W.S 12mm 140mm 140mm
RS-5 5000mm 2000mm 180mm O.W.S 12mm 140mm 200mm
RS-6 6000mm 2000mm 180mm O.W.S 12mm 140mm 200mm
146
Table 4.19 Schedule of Stair
RSB OF RSB OF
MARK LENGTH (L) WIDTH (B) HEIGHT (h)
MAIN BARS TEMPERATURE BARS
SW-1 2000mm 3000mm 180mm 16mm 10mm
SW-2 1750mm 3000mm 180mm 16mm 10mm
SW-3 1000mm 3000mm 18mm 16mm 10mm
147
148
by 480 mm, and the column sizes for square tie are 330 mm
149
Figure 4.48. Second Floor Framing Plan (Slab)
150
Table 4.21. Schedule of Second Floor Beam
LENGTH( WIDTH HEIGHT RSB&NO.OF RSB&NO.OF
MARK RSB&SPACING OF STIRRUPS
L) (b) (h) BARS@SUPPORT BARS@MIDSPAN
10ømm -1@50mm, 5@160mm,
RB-1 3000mm 280mm 480mm 4pcs-22ømm 2pcs-22ømm
REST@200mm
RB-2 6000mm 280mm 480mm 4pcs-22ømm 2pcs-22ømm 10ømm -1@50, REST@200mm
4pcs-32ømm
10ømm -1@50, 10@180mm,
RB-3 6000mm 280mm 480mm @top 4pcs-25ømm
REST@200mm
2pcs-16ømm
@bottom
RB-4 3000mm 200mm 250mm 2pcs-20ømm 3pcs-20ømm 10ømm -1@50, REST@100mm
151
Table 4.22. Schedule of Second Floor Column
NO.OF RSB@ SPACING
MARK LENGTH WIDTH HEIGHT RSB OF
BARS@MAIN LATERAL @LATERAL
(SQUARE TIED) (L) (b) (h) MAIN BARS
BARS TIES TIES
C3 340mm 340mm 3000mm 20mm 8pcs 10mm 320mm
C4 410mm 410mm 3000mm 28mm 6pcs 10mm 410mm
152
153
480mm, and the column sizes for square tie are 330 mm by
340mmx340mm. (see Figure 4.49 & 4.50 and Table 4.24, 4.25
& 4.26).
Figure 4.49. Third Floor Framing Plan (Beam)
154
Figure 4.50. Third Floor Framing Plan (Slab)
155
Table 4.24. Schedule of Third Floor Beam
4pcs-32ømm
10ømm -1@50, 10@180mm,
2RB-3 6000mm 280mm 480mm @top 4pcs-25ømm
REST@200mm
2pcs-16ømm
@bottom
2RB-4 3000mm 200mm 250mm 2pcs-20ømm 3pcs-20ømm 10ømm -1@50, REST@100mm
156
Table 4.26.Schedule of Third Floor Slab
DIMENSION (mm) SHORT DIRECTION LONG DIRECTION
TYPE SPACING
MARK OF RSB SPACING @ SPACING @ SPACING @
Length Width Height @
SLABS COLUMN MIDDLE COLUMN
(Lb) (L) (t) MIDDLE
STRIP STRIP STRIP
STRIP
RS-1 6000mm 3000mm 180mm T.W.S 12mm 140mm 140mm
RS-2 6000mm 3000mm 180mm T.W.S 12mm 140mm 130mm 140mm
RS-3 3000mm 3000mm 180mm T.W.S 12mm 140mm 140mm
RS-4 5000mm 3000mm 180mm T.W.S 12mm 140mm 140mm
RS-5 5000mm 2000mm 180mm O.W.S 12mm 140mm 200mm
RS-6 6000mm 2000mm 180mm O.W.S 12mm 140mm 200mm
157
158
4pcs-32ømm
10ømm -1@50, 10@180mm,
3RB-3 6000mm 280mm 480mm @top 4pcs-25ømm
REST@200mm
2pcs-16ømm
@bottom
161
Figure 4.53. Detailed Design of Beam (RB-1)
162
Figure 4.54. Detailed Design of Slab (S-1)
163
Figure 4.55. Detailed Design
of Column (C-1)
164
Figure 4.57. Typical Raft Footing
165
Figure 4.58. Raft Footing Detailed Section
166
167
B. Fajardo, 2000.
Contingency ₱152,636.40
SUBTOTAL ₱1,679,000.40
Labor ₱8,277,064.36
Contingency ₱2,896,972.53
SUBTOTAL ₱31,866,697.80
III-MASONRY WORKS
Unit
Quantity Units Description Total Cost
Price
16996 pcs #4 C.H.B. 14 ₱237,938.61
19225 pcs #6 C.H.B. 20 ₱384,503.20
Portland
6508 bags Cement 225 ₱1,464,333.49
cu.
231 m. Sand 900 ₱207,594.79
19574 kg 16mm Ø Bar 55 ₱1,076,596.37
Labor ₱917,748.03
Contingency ₱428,871.45
SUBTOTAL ₱4,717,585.94
IV-FORMWORKS
Unit
Quantity Units Description Total Cost
Price
339 sheets 4' x 8' Plywood 381 ₱129,159.00
2" x 3" x 8'
2445 kg Lumber 130 ₱317,850.00
43.4 kg #2 1/2 CWNails 140 ₱6,076.00
#1 Finishing
32.4 kg Nails 158 ₱5,119.20
Labor ₱183,281.68
Contingency ₱64,148.59
SUBTOTAL ₱705,634.47
169
VI-PAINTING WORKS
Unit
Quantity Units Description Total Cost
Price
617.5924 gal. Acrylic 1000 ₱617,592.40
ConcreteSealer
502.3715 gal. Acrylic Latex 1000 ₱502,371.55
Paint
447.9856 gal. Neutralizer 1000 ₱447,985.58
Labor ₱627,179.81
Contingency ₱219,512.93
170
SUBTOTAL ₱2,414,642.27
VII-SCAFFOLDINGS
Unit
Quantity Units Description Total Cost
Price
2" x 3" x 8'
8480 pcs Lumber 130 ₱1,102,400.00
263 kg #4 CWNails 130 ₱34,190.00
Labor 454636
Contingency ₱159,122.60
SUBTOTAL ₱1,591,226.00
VIII-TILE WORKS
Unit
Quantity Units Description Total Cost
Price
196.044 bags Cement Mortar 225 ₱44,109.89
1139.791 kg. White Cement 85 ₱96,882.19
6x6 Ceramic
5609.608 pcs. Tile 150 ₱841,441.25
3x3 Ceramic
3012.467 pcs. Tile 35 ₱105,436.33
Labor ₱435,147.87
Contingency ₱152,301.75
SUBTOTAL ₱1,675,319.29
IX-CEILING
Unit
Quantity Units Description Total Cost
Price
728.9987 Cement Board 500 ₱364,499.33
150.0667 Wall Angle 50 ₱7,503.33
2223.2 Metal Furring 120 ₱266,784.00
Carrying
239.1 Channel 115 ₱27,496.50
Labor ₱266,513.27
Contingency ₱93,279.64
SUBTOTAL ₱1,026,076.08
X GENERAL
Lumpsum ₱220,000.00
REQUIREMENTS
XI MOBILIZATION Lumpsum ₱16,500.00
XII STEEL MATTING Lumpsum ₱550,000.00
XIII ELECTRICAL Lumpsum ₱550,000.00
XIV PLUMBING Lumpsum ₱550,000.00
XV DEMOBILIZATION Lumpsum ₱16,500.00
XVI PROJECT
Lumpsum ₱550,000.00
CLOSEOUT
SUBTOTAL ₱2,453,000.00
171
labor cost.
Program of Works/PERT-CPM
173
CHAPTER V
Summary
of the project.
2020.
174
175
time was the portal method and moment distribution method. The
Beams).
For stairs, the design for the thread of the stairs was
steel from the outermost fiber of concrete was 25 mm, and the
result was 16mm and 10mm for the main bars and temperature
Stair).
Conclusions
the works would made the network diagram for distinguished the
178
Recommendations
following recommendations:
building.
structure.
Foundation Engineering.
http://site.iugaza.edu.ps/ymadhoun/files/2016/09/Ch
apter-08.pdf
Today.
https://www.medicalnewstoday.com/articles/coronavir
us-prevention#summary
https://dictionary.cambridge.org/dictionary/english
/evacuee
https://www.pna.gov.ph/articles/1196379
https://childhope.org.ph/childhope-philippines-
klinikalye-medical-mission/
https://fo6.dswd.gov.ph/about-us/programs/
180
181
https://www.designingbuildings.co.uk/wiki/Lateral_l
oads#:~:text=Lateral%20loads%20are%20live%20loads,w
hich%20are%20vertical%2C%20downward%20forces
https://learnaboutstructures.com/Portal-Method
https://campus.extension.org/mod/book/view.php?id=6
418&chapterid=6747
Trading
2018.
https://www.dilg.gov.ph/PDF_File/issuances/memo_cir
culars/dilg-memocircular-201888_6862a1ddb0.pdf
Eastern Samar.
182
https://essc.org.ph/content/wpcontent/uploads/2014/
12/20140924-EC_BuildingDesignDevelopment.pdf
https://lpulaguna.edu.ph/wp-
content/uploads/2019/10/4.-Design-and-
Implementation-of-the-Proposed-Two-Storey-Multi-
Purpose-Green-Building-at-Brgy.-Bagong-Pook-Malvar-
Batangas.pdf
https://boeingconsult.com/tafe/structures/Loads/Loa
ds.HTM
https://www.dswd.gov.ph/issuances/MCs/MC_2018-
019.pdf
https://neda.gov.ph/national-priority-plans/
from
https://archive.org/details/NSCP2015/page/n7/mode/2
up
(2022). https://www.dhs.gov/natural-disasters
http://roxascity.gov.ph/agatonph-brgy-bago-to-
arcabalo-bolo-road-still-passable-as-of-950am-
water-level-
rising/?utm_source=rss&utm_medium=rss&utm_campaign=
agatonph-brgy-bago-to-arcabalo-bolo-road-still-
passable-as-of-950am-water-level-rising
https://doh.gov.ph/persons-with-disabilities
184
https://www.philatlas.com/visayas/r06/capiz/roxas-
city.html
Japan Earthquake.
https://elibrary.worldbank.org/doi/full/10.1596/978
-1-4648-0153-2_ch18
of structures 1. Scribd.
https://www.scribd.com/document/487042158/Definitio
ns-and-Terminologies-in-Theory-of-Structures-1#
livelihood-program-
slp/#:~:text=Sustainable%20Livelihood%20Program%20(
SLP),improve%20their%20socioeconomic%20well%2Dbeing
Agency. https://www.pna.gov.ph/articles/1166885
climate change.
https://www.preventionweb.net/news/impacts-super-
typhoons-and-climate-change
185
Kazakhstan. https://uil.unesco.org/case-
study/effective-practices-database-litbase-
0/community-learning-centres-kazakhstan
https://www.unicef.org/philippines/media/476/file/B
uilding%20Safe%20Spaces%20for%20the%20Community.pdf
Topics. https://www.sciencedirect.com/topics/earth-
and-planetary-sciences/human-induced-hazard
Projects. http://www.civilsimplified.com/
https://www.vocabulary.com/dictionary/resident
topics/coronavirus
https://mb.com.ph/2021/12/16/preemptive-
evacuation-starts-in-roxas-city-for-odette/
APPENDICES
186
187
APPENDIX A
Gantt Chart
Months
Activities 2022 2023
Aug Sept Oct Nov Dec Jan Feb Mar April May June
Collection
of
materials,
library
research,
and online
research
Oral defense
of title and
objectives
Gathering of
data
Start of
structural
analysis and
design
computations
Pre-oral
defense
Final
Packaging
Final oral
defense
Finalization
of the study
188
APPENDIX B
Project Description
building.
190
APPENDIX C
Working Plans
PERSPECTIVE
NOT TO SCALE 189
SITE DEVELOPMENT PLAN
NOT TO SCALE `
190
191
FIRST FLOOR PLAN
192
SECOND FLOOR PLAN 193
THIRD FLOOR PLAN
194
ROOFTOP FLOOR PLAN
195
FRONT ELEVATION
196
REAR ELEVATION
197
LEFT SIDE ELEVATION
198
RIGHT SIDE ELEVATION
199
FOUNDATION PLAN
200
FIRST FLOOR FRAMING PLAN
201
202
SECOND FLOOR FRAMING PLAN (SLAB)
SECOND FLOOR FRAMING PLAN (BEAM)
203
THIRD FLOOR FRAMING PLAN (BEAM)
204
THIRD FLOOR FRAMING PLAN (SLAB)
205
ROOF SLAB FRAMING PLAN (BEAM)
206
ROOF SLAB FRAMING PLAN (SLAB)
DETAIL OF BEAM (RB-1)
207
DETAIL OF SLAB (S-1)
208
DETAILED DESIGN OF COLUMN (C-1)
ELEVATION OF COLUMN-FOOTING(F1-C1,C3,C5)
209
TYPCAL RAFT FOOTING
210
RAFT FOOTING DETAILED SECTION
211
DETAIL OF STAIR
212
213
214
10mmꬾ HORIZONTAL
BARS
SPACED @ 230 MM O.C
16mmꬾ VERTICAL
ELEVATION OF STAIR BARS
SPACED @ 210 MM
O.C
215
216
217
218
219
220
APPENDIX D
A. FOR WALL
Computation:
ZB= 4+3+3=10m
221
222
condition)
For
Velocity pressure:
P=qh(GCpf-GCpi)
G=0.85
223
Wind Pressure:
surface.
At Frame 1
a a
b b
c c
COMPUTATION:
Tributary Area:
Section a-
a
S1 2S1 2S1 2S1 2S1 S1
2S1 2S1
[Fh=0]
10.05-14S1=0 S1=0.7179KN
Section b-
2S1 2S1
b
S1 2S1 2S1 2S1 2S1 2S1 2S1 S1
[FH=0]
10.05+15.08-14S2=0 S2=1.795KN
Section c-c
[FH=0]
10.05+15.08+17.59-14S3=0 S3=3.05KN
Isolated Frame Used Analysis Of Portal Method:
227
228
FG, GH, HI and IJ, also in the column member the load that
resist the great capacity are members GB, HC, and ID.
At Frame 1
Computation:
Dead loads
a. Stone concrete = 0.023KPa
b. electrical & mechanical= 0.20KPa
duct allowance
c. solid flat tile = 1.1KPa
1.243KPa
Live Loads
229
a. Roof Slab(theater,
assembly areas and auditorium) = 7.2KPa
Other Loads
Weight of the slab=(23.54KN/m3)(0.18m)=4.24KN/m2
Weight of the beam=(23.54KN/m3)(0.28m)(0.48m)= 3.16KN/m
W1= 31KN/m
230
B. For W2:
FEM= WL2/12
K = I/L
ƩK = K1+K2
DF= K / ƩK
231
MEMBER K ƩK DF
YZ I/3 I/3+∞ 0
ZY I/3 0.5
2I/3
ZA' I/3 0.5
A'Z I/3 0.4
5I/6
A'B' I/2 0.6
B'A' I/2 0.6
5I/6
B'C' I/3 0.4
C'B' I/3 0.5
2I/3
C'D' I/3 0.5
D'C' I/3 0.4
5I/6
D'E' I/2 0.6
E'D' I/2 0.6
5I/6
E'F' I/3 0.4
F'E' I/3 I/3+∞ 0
Moment Distribution of frame bay 1:
JOINT A B C D E F G H
MEMBER AB BA BC CB CD DC DE ED EF FD FG GF GH HG
D.F. 0.00 0.50 0.50 0.40 0.60 0.60 0.40 0.50 0.50 0.40 0.60 0.60 0.40 0.00
FEM 23.30 -23.30 23.30 -23.30 10.36 -10.36 23.30 -23.30 23.30 -23.30 10.36 -10.36 23.30 -23.30
0.00 0.00 5.18 7.76 -7.76 -5.18 0.00 0.00 5.18 7.76 -7.76 -5.18
0.00 0.00 2.59 0.00 -3.88 3.88 0.00 -2.59 2.59 0.00 -3.88 3.88 0.00 -2.59
-1.29 -1.29 1.55 2.33 -2.33 -1.55 0.00 0.00 1.55 2.33 -2.33 -1.55
-0.65 0.00 0.78 -0.65 -1.16 1.16 0.00 -0.78 0.78 0.00 -1.16 1.16 0.00 -0.78
-0.39 -0.39 0.72 1.09 -0.70 -0.47 0.00 0.00 0.47 0.70 -0.70 -0.47
-0.19 0.00 0.36 -0.19 -0.35 0.54 0.00 -0.23 0.23 0.00 -0.35 0.35 0.00 -0.23
-0.18 -0.18 0.22 0.33 -0.33 -0.22 0.00 0.00 0.14 0.21 -0.21 -0.14
-0.09 0.00 0.11 -0.09 -0.16 0.16 0.00 -0.11 0.07 0.00 -0.10 0.10 0.00 -0.07
-0.05 -0.05 0.10 0.15 -0.10 -0.07 0.02 0.02 0.04 0.06 -0.06 -0.04
-0.03 0.00 0.05 -0.03 -0.05 0.08 0.01 -0.03 0.02 0.01 -0.03 0.03 0.00 -0.02
-0.03 -0.03 0.03 0.05 -0.05 -0.03 0.01 0.01 0.01 0.01 -0.02 -0.01
-0.01 0.00 0.02 -0.01 -0.03 0.02 0.00 -0.02 0.00 0.00 -0.01 0.01 0.00 -0.01
-0.01 -0.01 0.02 0.02 -0.02 -0.01 0.01 0.01 0.00 0.00 0.00 0.00
SUM 22.33 -25.25 25.25 -16.45 16.45 -15.79 15.79 -27.02 27.02 -15.90 15.90 -15.91 15.91 -26.99
232
233
A. Beam
For member YZ W1
Y Z
3.0
My= 22.33KN.m
Mz= -25.25KN.m
Ry= 45.62KN
Rz= 47.57KN
Midspan moment=45.62(1.47)(0.50)-
22.33
MA’= -16.45KN.m
16.45
RZ= 49.53KN
RA’= 43.66KN
25.25
234
= 14.23KN.m
MA’= 16.45KN.m
MB’= -15.79KN.m
RA’= 31.40KN
RB’= 30.73KN
= -0.59KN.m
MB’= 15.79KN.m
MC’= -27.02KN.m
RB’= 46.60KN
RC’= 50.34KN
= 17.81KN.m
MC’= 27.02KN.m
MD’= -15.90KN.m
RC’= 50.30KN
RD’= 42.89KN
= 13.71KN.m
MD’= 15.90KN.m
ME’= -15.91KN.m
RD’= 31.07KN
RE’= 31.07KN
= -0.37KN.m
ME’= 15.91KN.m
MF’= -26.99KN.m
RE’= 42.90KN
RF’= 27.96KN
= 23.05KN.m
236
FEM= WL2/12
K = I/L
ƩK = K1+K2
DF= K / ƩK
MEMBER K ƩK DF
YZ I/3 I/3+∞ 0
ZY I/3 0.5
2I/3
ZA' I/3 0.5
A'Z I/3 0.4
5I/6
A'B' I/2 0.6
B'A' I/2 0.6
5I/6
B'C' I/3 0.4
C'B' I/3 0.5
2I/3
C'D' I/3 0.5
D'C' I/3 0.4
5I/6
D'E' I/2 0.6
E'D' I/2 0.6
5I/6
E'F' I/3 0.4
F'E' I/3 I/3+∞ 0
Moment Distribution of frame bay 2 & 3:
JOINT Q R S T U V W X
MEMBER QR RQ RS SR ST' TS TU UT UV VU VW WV WX XW
D.F. 0.00 0.50 0.50 0.40 0.60 0.60 0.40 0.50 0.50 0.40 0.60 0.60 0.40 0.00
FEM 31.79 -31.79 31.79 -31.79 14.13 -14.13 31.79 -31.79 31.79 -31.79 14.13 -14.13 31.79 -31.79
0.00 0.00 4.42 13.25 -13.25 -4.42 0.00 0.00 4.42 13.25 -13.25 -4.42
0.00 0.00 2.21 0.00 -6.62 6.62 0.00 -2.21 2.21 0.00 -6.62 6.62 0.00 -2.21
-1.10 -1.10 1.66 4.97 -4.97 -1.66 0.00 0.00 1.66 4.97 -4.97 -1.66
-0.55 0.00 0.83 -0.55 -2.48 2.48 0.00 -0.83 0.83 0.00 -2.48 2.48 0.00 -0.83
-0.41 -0.41 0.76 2.28 -1.86 -0.62 0.00 0.00 0.62 1.86 -1.86 -0.62
-0.21 0.00 0.38 -0.21 -0.93 1.14 0.00 -0.31 0.31 0.00 -0.93 0.93 0.00 -0.31
-0.19 -0.19 0.28 0.85 -0.85 -0.28 0.00 0.00 0.23 0.70 -0.70 -0.23
-0.09 0.00 0.14 -0.09 -0.43 0.43 0.00 -0.14 0.12 0.00 -0.35 0.35 0.00 -0.12
-0.07 -0.07 0.13 0.39 -0.32 -0.11 0.01 0.01 0.09 0.26 -0.26 -0.09
-0.04 0.00 0.07 -0.04 -0.16 0.20 0.01 -0.05 0.04 0.01 -0.13 0.13 0.00 -0.04
SUM -0.03 -0.03 0.05 0.15 -0.15 -0.05 0.00 0.00 0.03 0.09 -0.10 -0.03
30.88 -33.61 33.61 -25.38 25.38 -24.65 24.65 -35.33 35.33 -24.73 24.73 -24.73 24.73 -35.31
237
238
A. Beam
For member QR W1
Q R
3.0
MQ= 30.88KN.m
MR= -33.61KN.m
RQ= 62.66KN
RR= 64.48KN
Midspan moment=62.66(1.48)(0.50)-
30.88
For member RS W1
R S
MR= 33.61KN.m 3.0
MS= -25.38KN.m
25.38
RR= 66.31KN
RS= 60.83KN
33.61
= 18.27KN.m
239
For member ST
MS= 25.38KN.m
MT= -24.65KN.m
RS= 42.75KN
RT= 42.01KN
= -3.82KN.m
For member TU
MT= 24.65KN.m
MU= -35.33KN.m
RT= 63.57KN
RU= 67.13KN
= 21.73KN.m
For member UV
MU= 35.33KN.m
MV= -24.73KN.m
RU= 67.11KN
240
RV= 60.03KN
= 17.79KN.m
For member VW
MV= 24.73KN.m
MW= -24.73KN.m
RV= 42.38KN
RW= 42.38KN
= -3.54KN.m
For member WX
MW= 24.73KN.m
MX= -35.31KN.m
RW= 60.04KN
RX= 38.14KN
= 30.34KN.m
B. Column
241
For member YQ
Moment= 22.33KN.m
Shear=0
Axial= 45.62 KN
For member QI
Shear=0
For member IA
Shear=0
Moment=moment (PK DUE TO WIND LOAD) +Moment (MI DUE TO WIND LOAD)+
Shear=Shear (PK DUE TO WIND LOAD) +Shear (MI DUE TO WIND LOAD)+
=0.51+0.44+0+0
Shear= 0.91 KN
Axial=Axial (PK DUE TO WIND LOAD) +Axial (MI DUE TO WIND LOAD)+
242
Axial=109.01 KN
APPENDIX E
Design of Slabs
a. Slab – 1
b. Slab – 2
d. Slab – 3
e. Slab – 4
f. Slab – 5
g. Slab – 6
243
244
h. Slab – 1
i. Slab – 2
k. Slab – 3
l. Slab – 4
m. Slab – 5
n. Slab – 6
.̇
. Adopt 170.20 mm say 180 mm thickness of slab
Two-way Slab
DATA:
ALLOWABLE
ROOF SLAB DIMENSION(mm)
STRESS(Mpa)
Width Height
MARK Length(Lb) fc' fy
(Ls) (t)
S-2 6000mm 3000mm 180mm 20.7Mpa 276Mpa
Effective
Clear Cover Depth Dead Load Live Load
(mm)
RSB
25 155mm 5.5kpa 7.2kpa 12mm
COMPUTATION:
FOR BOTH END CONTINUOUS:
a. Coefficients for negative moments in slabs
ROOF SLABS(S-2)
W=1.2DL+1.6LL KPa 18.12
W=(CONSIDER 1m Strip)KN/m 18.12
RATIO: m=Ls/Lb 0.5
USED: m(ratio) 0.5
CASE: 4
Cs 0.094 cb 0.006
.ADOPT
.̇ SPACING @ COLUMN STRIP 140mm
3. Middle Strip:
Mu= Mapos 22.18
Mu=fc'bd^2(2); w=? 0.0511
fc'/fy 0.00383
max=0.75b 0.027836
min=1.4/fy 0.005072
max>>min; used 0.005072
As=bd (mm2) 786.2319
Ad=(/4)(d^2) (mm2) 113.0973
SPACING=Ad(1000)/As 142.8571
.̇
. ADOPT SPACING @ MIDDLE STRIP 140mm
.ADOPT
.̇ SPACING @ CUT BARS 140mm
3.Column Strip:
Mu= Mbpos 5.87
Mu=fc'bd^2(-0.592); w 0.013218
247
=fc'/fy 0.000991
max=0.75b 0.027836
min=1.4/fy 0.005072
max>>min; used 0.005072
As=rbd (mm^2) 786.2319
Ad=(/4)(d2) (mm^2) 113.0973
SPACING=Ad(1000)/As 142.8571
.ADOPT
.̇ SPACING @ MAIN BARS 140mm
One-way slab
ALLOWABLE
ROOF SLAB DIMENSION(mm)
STRESS(Mpa)
Width Height
MARK Length(Lb) fc' fy
(Ls) (t)
S-2 5000mm 3000mm 180mm 20.7Mpa 276Mpa
Effective
Clear Cover Depth Dead Load Live Load
(mm)
RSB
25 155mm 5.5kpa 7.2kpa 12mm
COMPUTATION:
FOR BOTH END CONTINUOUS:
T = L/28(0.40+Fy/700) 141.84
USED: thickness of slabs(t) 180
W = 1.2DL + 1.6LL Kpa 18.12
W = (CONSIDER 1m Strip)KN/m 18.12
Mu =(WuL )/28
2 16.18
Mu = φfc'bd^2(ω-0.59ω ); w= 2 0.036955
ρ = ωfc'/fy 0.004742
ρmax = 0.75ρb 0.00277
ρmin = 1.4/fy 0.005072
ρmax>ρ>ρmin; used ρ 0.005072
As = ρbd (mm^2) 786.2319
Ad=(π/4)(d ) 2 (mm^2) 113.0973
SPACING = Ad(1000)/As 142.8571
.ADOPT SPACING @ MAIN BARS
.̇ 140mm
Ad = (π/4)(d ) (mm^2)
2 78.54
SPACING = Ad(1000)/As 242.41
.ADOPT SPACING @ TEMPERATURE BARS
.̇ 200mm
DATA:
f'c Effective
(Mpa) fy (Mpa) φ covering (mm)
28 400 0.9 40+dia./2
Mmax at support Mmax at midspan d
beam
(kN-m) (kN-m) b (mm) (mm)
B-1 185.06 93.24 280 429
B-2 178.62 97.7 280 429
CALCULATION:
CALCULATION:
3RB-1
A. Reinforcement at the support
Mu=Mn(KN.m) 185.06
Mu = fc’bd2(-0.592); 0.15706
249
C. Design of Stirrups:
Ru 351.51
bd>Vs 423.74
>Smax
S=(Av fy d)/Vs 139 maximum
spacing
Vs< bd 211.87
.̇
.Smax=d/2 214.5
x1 1.11 x2 1.30
250
CALCULATION:
3RB-2
A. Reinforcement at the support
Mu = Mn(KN.m) 178.62
Mu = fc’bd2(-0.592);= 0.15218
= fc'/fy 0.01065
max= 0.75b 0.0228
min= 1.4/fy 0.0035
max>>min; used 0.01065
As = bd (mm2) 1274.81
Ad = (/4)(d2) (mm2) 380.13
No. of Bars =As/Ad 3.35
.̇
.ADOPT NO. OF BARS. @ SUPPORT 4 pcs
C. Design of Stirrups:
Ru 176.64
Vc = bd (KN) 108.05
Vc (KN) 91.85
Vc/2 (KN) 45.82
Vu = Ru-Wud 162.57
Vu>Vc (KN) .̇
.NEED TO DESIGN STIRRUPS
Vs = Vu/-Vc 83.21
251
bd>Vs 423.74
S = (Av fy d)/Vs 323
maximum spacing
Vs< bd 211.38
.̇
.Smax=d/2 214.5
x1 1.44 x2 2.22
Vu 143.85 >Vc/2 Vu 120.90 >Vc/2
Vs 52.00 Vs 29.05
S 518 >214.5mm S 927 >214.5mm
Computation:
Area required:
Pu
445.06
Ag=Pu/(0.80[0.85fc’(1-pg)+fypg] 26978.86
(h^2)=Ag
164.25
Computation:
For Column-1
RSB@ LONGITUDINAL 20
RSB@ LATERAL TIES 10
1.Longitudinal Bars
Mu=Mn 165.58
Pu=Pn 445.06
e(actual)=Mu/Pn 241.826
e/h 0.82221
e(allowable)=0.10h 0.033
Column having large eccentricity e(actual) >e(allowable)
Solving for reinforcements:
ρg 0.02
As=ρgh2 2178
Ad=(∏/4)(d2) 314.16
No. of Bars=As/Ad 6.9328
.:ADOPT NO. OF BARS 8pcs
2.Lateral Ties
253
Computation:
For Column (C3)square tied column
Area required:
Pu 1117.68
Ag=Pu/(0.80[0.85fc’(1-pg)+fypg]
110210.69
(h^2)=Ag
331.97996
Note: consider the beam dimension 280mm
.:Adopt Dimension 340mm x 340mm
1.Longitudinal Bars
Mu=Mn 225.63
Pu=Pn 1117.68
e(actual)=Mu/Pn 131.122
e/h 0.397
e(allowable)=0.10h 0.034
Column having large eccentricity e(actual) >e(allowable)
Computation:
For Column (C5)square tied column
Area required:
Pu 1795.16
Ag=Pu/(0.80[0.85fc’(1-pg)+fypg] 68617.79
(h^2)=Ag
261.95
Note: consider the beam dimension 280mm
.:Adopt Dimension 340mm x 340mm
1.Longitudinal Bars
Mu=Mn 350.60
Pu=Pn 1795.16
e(actual)=Mu/Pn 126.947
e/h 0.37337
e(allowable)=0.10h 0.034
Column having large eccentricity e(actual) >e(allowable)
Data:
Q= ΣQ 105735.24 kN
x'= 28.5 m
y'= 10.5m
x̅= 25.60 m
ȳ= 9.45 m
ex= x'- 2.8990 m
ey= y'-ȳ 1.0499 m
A= 1080 m²
Ix= 42342 mm⁴
Iy= 35829 mm⁴
Mx= Qey 111014.1426 kN.m
My=Qex 306528.9553 kN.m
Pressure at any point:
3000m
410mm
3000m
x410mm
v= Pu/Bod
d= 0.50m
C= 0.10m
D= 0.60m
y
A C E G I
x x
L
B D F H J
y
257
M=QL²/10
MAB= 299.86 kN.m
MCD= 253.66 kN.m
MEF= 207.46 kN.m
MGH= 161.26 kN.m
MIJ= 145.86 kN.m
MKL= 107.36 kN.m
note: use 32mm dia. Bars @ 325mm O.C spacing run 50% of steel
V= 648.00 m³
W= 15253.92 kN
Design of Stair:
T = 0.25 m = 9.84 in
Rise = 3.30 m;
Cover = 25 mm
Allowable stresses:
fy = 414 Mpa
Figure:
259
Loadings:
Computation:
2R + T = 24”
1.) R + T 430
2.) 2R + T 635
3.) RT 48400
4.) R 200
Weight of steps:
W= 21.72 KN/m
M= = = N–mm
261
ф= 0.90
ρ=ωfc'/fy 0.004306
ρmin=1.4/fy 0.003382
ρ>ρmin .:Use ρ
Temperature bars:
(Detail of reinforcement )
Data:
T = 0.25 m = 9.84 in
Rise = 3.00 m;
262
Cover = 25 mm
Allowable stresses:
fy = 414 Mpa
Figure:
Loadings:
Computation:
2R+T = 24”
6.) R + T 430
7.) 2R + T 635
8.) RT 48400
9.) R 200
264
Weight of steps:
W= 21.72 KN/m
M= = = N–mm
ф= 0.90
ρ=ωfc'/fy 0.004306
ρmin=1.4/fy 0.003382
ρ>ρmin .:Use ρ
Temperature bars:
(Detail of reinforcement )
SW-3:
Data:
T = 0.25 m = 9.84 in
Rise = 1.00 m;
Cover = 25 mm
Allowable stresses:
Figure:
Loadings:
Computation:
2R + T = 24”
11.) R + T 430
12.) 2R + T 635
13.) RT 48400
14.) R 200
Weight of steps:
W= 19.60 KN/m
M= = = N–mm
ф= 0.90
ρ=ωfc'/fy 0.00050
ρmin=1.4/fy 0.00338
Temperature bars:
(Detail of reinforcement )
Design of Ramp
RS-1:
Data:
L = 6m
Rise = 0.5m
n = 9
fy = 414 Mpa
fs = 248 Mpa
Figure:
Computation:
Minimum t =
t= 300mm
Steel Area:
As =
271
54.47 kN
Temperature bars
272
RS-2:
Data:
L = 12m
Rise = 1m
n = 9
fy = 414 Mpa
fs = 248.4Mpa
Figure:
Computation:
Minimum t =
t= 600mm
Steel Area:
As =
274
54.40kN
Spaced at 50 mm on centers.
Temperature bars
Fajardo Jr.)
I-EARTHWORKS
Unit
Quantity Units Description Total Cost
Price
cu.
2268 Backfill 285 ₱646,380.00
m.
cu.
1080 Excavation 390 ₱421,200.00
m.
cu. Gravel
21.6 1050 ₱22,680.00
m. Bedding
Labor ₱436,104.00
Contingency ₱152,636.40
SUBTOTAL ₱1,679,000.40
276
277
Contingency ₱2,896,972.53
SUBTOTAL ₱31,866,697.80
III-MASONRY WORKS
Unit
Quantity Units Description Total Cost
Price
16996 pcs #4 C.H.B. 14 ₱237,938.61
19225 pcs #6 C.H.B. 20 ₱384,503.20
Portland
6508 bags Cement 225 ₱1,464,333.49
cu.
231 m. Sand 900 ₱207,594.79
19574 kg 16mm Ø Bar 55 ₱1,076,596.37
Labor ₱917,748.03
Contingency ₱428,871.45
SUBTOTAL ₱4,717,585.94
IV-FORMWORKS
Unit
Quantity Units Description Total Cost
Price
4' x 8'
339 sheets Plywood 381 ₱129,159.00
2" x 3" x 8'
2445 kg Lumber 130 ₱317,850.00
278
VI-PAINTING WORKS
Unit
Quantity Units Description Total Cost
Price
617.5924 gal. Acrylic 1000 ₱617,592.40
ConcreteSealer
502.3715 gal. Acrylic Latex 1000 ₱502,371.55
Paint
447.9856 gal. Neutralizer 1000 ₱447,985.58
Labor ₱627,179.81
Contingency ₱219,512.93
SUBTOTAL ₱2,414,642.27
VII-SCAFFOLDINGS
Unit
Quantity Units Description Total Cost
Price
2" x 3" x 8'
8480 pcs Lumber 130 ₱1,102,400.00
263 kg #4 CWNails 130 ₱34,190.00
Labor 454636
Contingency ₱159,122.60
SUBTOTAL ₱1,591,226.00
VIII-TILE WORKS
Unit
Quantity Units Description Total Cost
Price
196.044 bags Cement Mortar 225 ₱44,109.89
1139.791 kg. White Cement 85 ₱96,882.19
6x6 Ceramic
5609.608 pcs. Tile 150 ₱841,441.25
3x3 Ceramic
3012.467 pcs. Tile 35 ₱105,436.33
Labor ₱435,147.87
Contingency ₱152,301.75
SUBTOTAL ₱1,675,319.29
IX-CEILING
Unit
Quantity Units Description Total Cost
Price
728.9987 Cement Board 500 ₱364,499.33
150.0667 Wall Angle 50 ₱7,503.33
280
X GENERAL
Lumpsum ₱220,000.00
REQUIREMENTS
XI MOBILIZATION Lumpsum ₱16,500.00
XII STEEL MATTING Lumpsum ₱550,000.00
XIII ELECTRICAL Lumpsum ₱550,000.00
XIV PLUMBING Lumpsum ₱550,000.00
XV DEMOBILIZATION Lumpsum ₱16,500.00
XVI PROJECT
Lumpsum ₱550,000.00
CLOSEOUT
SUBTOTAL ₱2,453,000.00
PERSONAL INFORMATION
Nickname: Diel
Sex: Male
Civil Status: Single
Age: 22 yrs. old.
Height: 5’4’’
Weight: 48 kg.
Birth date: September 05, 2000
Religion: Born Again Christian
Father’s Name: Danny A. Alcones
Mother’s Name: Ma. Luz A. Alcones
Siblings: Danluis A. Alcones
Donard A. Alcones
EDUCATIONAL ATTAINMENT
TERTIARY Bachelor of Science in Civil Engineering
Capiz State University, Main Campus
Fuentes Drive, Roxas City, Capiz
2023
SKILLS
Computer literate (Microsoft Word, Excel, Power
Point)
Proficient in Computer Aided Design (CAD)
Graphic design
Sketching and painting
SPORTS AND HOBBIES
Drawing and painting
Playing instruments
ACHIEVEMENTS/SEMINARS/TRAININGS/ORGANIZATION
Quiz Bowl Champion (2020)
MTAP Bronze Medal Division Level (2014)
With Honor, Senior High School
Salutatorian, Junior High School
Kabscout Member (2006 – 2009)
Boyscout Member (2009 – 2012)
Philippine Institute of Civil Engineers Member
(2019-2023)
PHILOSOPHY
PERSONAL INFORMATION
Nickname: N/A
Sex: Male
Civil Status: Single
Age: 22 yrs. old.
Height: 5’8’’
Weight: 68 kg.
Birth date: November 13, 2000
Religion: Roman Catholic
Father’s Name: Noel C. De Felipe
Mother’s Name: Iyren A. De Felipe
Siblings: Nicole A. De Felipe
Jemwell A. De Felipe
Jerick A. De Felipe
EDUCATIONAL ATTAINMENT
SKILLS
Computer Literate (Microsoft Word, Excel, Power
Point)
Proficient in Computer Aided Design (CAD), and
Sketch Up (SKP)
SPORTS AND HOBBIES
Playing Basketball, and Chess
Watching movies and internet surfing
Playing online games
ACHIEVEMENTS/SEMINARS/TRAININGS/ORGANIZATION
With Honor, Senior High School (2018 – 2019)
Champion and MVP during National Private Schools
Athletic Association Meet at Iba, Zambales (2017)
Athletics Varsity Player, High School (2015 -2019)
Children of Mary, High School (2013 – 2017)
Altar Server, High School (2013 – 2019)
Supreme Student Pastoral Council, High School (2017-
2019)
Leadership Seminar, High School (2017)
Philippine Institute of Civil Engineers Member
(2019-2023)
PHILOSOPHY
PERSONAL INFORMATION
Nickname: Daisy
Sex: Female
Civil Status: Single
Age: 22 yrs. old.
Height: 5’3’’
Weight: 48 kg.
Birth date: May 19, 2001
Religion: Roman Catholic
Father’s Name: Jonathan A. Fuentes
Mother’s Name: Mery Jean-Jean D. Fuentes
Siblings: Shania Marie D. Fuentes
Julia Stephan D. Fuentes
EDUCATIONAL ATTAINMENT
SKILLS
Drawing and capable of using Photoshop
Proficient in Computer Aided Design (CAD)
Computer Literate (Microsoft Word, Excel, Power
Point)
SPORTS AND HOBBIES
Playing Basketball, and Chess
Watching movies and internet surfing
Playing online games
ACHIEVEMENTS/SEMINARS/TRAININGS/ORGANIZATION
With Honor, Senior High School (2018 – 2019)
Girl’s Scout Member (2009-2017)
Science Club Mmber (2014 – 2017)
Altar Server, High School (2013 – 2019)
Red Cross Member (2016 – 2017)
Philippine Institute of Civil Engineers Member
(2019-2023)
PHILOSOPHY
PERSONAL INFORMATION
Nickname: Inday
Sex: Female
Civil Status: Single
Age: 22 yrs. old.
Height: 5’3’’
Weight: 43 kg.
Birth date: December 20, 2000
Religion: Roman Catholic
Father’s Name: Jose Ruel V. Panuncio
Mother’s Name: Elizabeth M. Panuncio
Siblings: Joebet M. Panuncio
Cyron Jade M. Panuncio
Francisderyl M. Panuncio
EDUCATIONALATTAINMENT
SKILLS
Computer Literate (Microsoft Word, Excel,
PowerPoint, etc.)
Proficient in Computer Aided Design(2D)
Proficient in 3D rendering using SketchUp
ACHIEVEMENTS/SEMINARS/TRAININGS/ORGANIZATION
6th Honorable Mention, Elementary School Level (2012-
2013)
With High Honor, Junior High School Level (2016-
2017)
With High Honor, Senior High School Level (2018-
2019)
Consistent MTAP 2nd and 3rd Placer, Division Level
(2013-2016)
Champion, Math Quiz Bee, Division Level (2018-2019)
Department of Science and Technology (DOST) Scholar
(2019-2023)
Philippine Institute of Civil Engineers Member
(2019-2023)
Participant, Application of Building Information
Modeling Technology Open Course by SEAMEO Technical
Education Development (August 30, 2022)
PHILOSOPHY