J & S -AFRIKA CONTRACTORS LTD

P.O. BOX 1343-00502


KAREN, KENYA.
info@jsafrikacontractors.com
TEL: 0732 517209 or 0735210166

VIENNA COURT WALL PARTITIONING , POWER SEPERATION & HVAC RETICULATION WORKS
NO DESCRIPTION QTY UNIT UNIT RATE TOTAL
*1.0 DEMOLITION
Carefully Demolish the existing Acoustic Ceiling (approx. size 2 X 7.78 m) at the Reception Area as per Client's
1 ITEM 10,000.00 10,000.00
1.01 instruction and approval . Make good disturbed areas and cart away arising debris
Carefully disassemble the existing light fixtures to be impacted by the partitioning works, make good disturbed
1 ITEM 7,000.00 7,000.00
1.02 areas and cart away arising debris from site.
Carefully disassemble existing HVAC System as instructed by the Client and make good disturbed areas to be
1 ITEM 10,000.00 10,000.00
1.03 reinstalled latter
1.1 BUILDERS WORKS
Supply and fix new 100mm thick Aqua Panel /Fiber Cement dry wall partition , including Isover Cavity fiber
glass wool infill for A1 fire rating the walls; OSB Sheathing where necessary ,taped and filled at joints on and
32 SQM 8,000.00 256,000.00
including proprietary pressed metal brandering system, including all cutting and trimming to socket fittings
where appropriate for the Office Room.
1.11

Allow provisional sum for separation for replacement and re installation of any noted damaged False Acoustic 1 ITEM 40,000.00 40,000.00
1.12 Panel Ceiling ; including metal support and railing , to Client's Instructions and Approval

Supply and install plain white, PVC floor skirting to newly installed dry wall partition (both sides) including 20 LM 1,000.00 20,000.00
1.13 associated clips and accessories and paint skirtings to match existing wall skirtings (both sides)

Prepare surface, skim, supply and apply undercoat + two (2) coats of brilliant white, Crown or equivalent and
64 SQM 600.00 38,400.00
approved vinyl matt emulsion paint to all new dry wall partitions , false ceiling
1.14

Allow provisional sum for supply and installation of new wiring and power seperation for the space - including
new power seperation from the existing electrical distrubution installation, isolation and creation of new routing, 1 ITEM 100,000.00 100,000.00
power cables, circuit breakers, light switches and accessories, sockets where appropriate and proper power board
labelling done to isolated distribution boards. (Fixed Sum) ( Location of the Switchboard to be within the current
1.15 electrical duct)
Allow provisional sum for separation of HVAC provisions for the office space - including new power supply and
1.16 ducting 1 ITEM 100,000.00 100,000.00
1.17 Allow sum for acquisition of NCC permits and all statutory documents required for conducting the works. 1 ITEM 15,000.00 15,000.00
1.18 Allow sum for cleaning and making good carpet flooring 1 ITEM 5,000.00 5,000.00
SUB - TOTAL 601,400.00
VAT 96,224.00
TOTAL 697,624.00