Steel Rolling Margin Register Final26 12 14

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 12

Project - Architectural Desinging Enginering and construction of office Building, Ahmedabad.

Gujarat
Package no.- : Contractor : Shayona Land Corporation
Location : GHB Site- Pragatinagar Consultant : SGS India Pvt. Ltd
Actual Std Unit
Sample Sample
Qty in Date of Challan Unit Weight Difference Average Average Remarks /
S.no Dia in mm Length in Weight in
MT receipt no/Lot no Weight Kg/m (+/-) Diff. % (-) Diff. % (+) Comments
m Kg
Kg/m IS 1786

MONTH: 2014
Acceptance criteria Asper IS : 1786 Up to and inculding 10 mm (+-) 8%, Over 10 mm to Including 16mm (+-)6% , Over mm (+-) 4%
0.998 0.377 0.378 0.395 -0.0172
1 8 MM 12.41 17/8/14 238-1415 0.996 0.372 0.373 0.395 -0.0215 -4.869 0.00
1.000 0.376 0.376 0.395 -0.0190
1.000 0.608 0.608 0.617 -0.0090
2 10 MM 12.71 17/8/14 238-1415 0.999 0.599 0.600 0.617 -0.0174 -2.998 0.00
0.995 0.585 0.588 0.617 -0.0291
1.000 0.872 0.872 0.888 -0.0160
3 12 MM 1.93 17/8/14 241-1415 0.996 0.860 0.863 0.888 -0.0245 -2.170 0.00
0.998 0.869 0.871 0.888 -0.0173
1.000 1.606 1.606 1.580 0.0260
4 16 MM 26.81 17/8/14 241-1415 0.998 1.598 1.601 1.580 0.0212 0.000 1.451
0.994 1.592 1.602 1.580 0.0216
1.000 2.452 2.452 2.469 -0.0170
5 20 MM 3 17/8/14 238-1415 1.004 2.456 2.446 2.469 -0.0228 -0.932 0.00
0.996 2.430 2.440 2.469 -0.0292
1.000 3.841 3.841 3.858 -0.0170
6 25 MM 8.15 17/8/14 241-1415 0.995 3.803 3.822 3.858 -0.0359 -0.563 0.00
0.998 3.838 3.846 3.858 -0.0123

SHYONA LAND CROP Sign. SGS Sign GHB Sign.

SHAYONA SGS GHB


SHAYONA SGS GHB
Project - Architectural Desinging Enginering and construction of office Building, Ahmedabad. Gujarat
Package no.- : Contractor : Shayona Land Corporation
Location : GHB Site- Pragatinagar Consultant : SGS India Pvt. Ltd
Actual Std Unit
Sample Sample
Qty in Date of Challan Unit Weight Difference Average Average Remarks /
S.no Dia in mm Length in Weight in
MT receipt no/Lot no Weight Kg/m (+/-) Diff. % (-) Diff. %(+) Comments
m Kg
Kg/m IS 1786

MONTH: 2014
Acceptance criteria Asper IS : 1786 Up to and inculding 10 mm (+-) 8%, Over 10 mm to Including 16mm (+-)6% , Over mm (+-) 4%
1.002 0.379 0.378 0.395 -0.0168
1 8 MM 3.93 26/9/14 16 1.000 0.372 0.372 0.395 -0.0230 -5.325 0.00
0.998 0.371 0.372 0.395 -0.0233
1.000 0.906 0.906 0.888 0.0180
2 12 MM 3.07 26/9/14 16 0.996 0.898 0.902 0.888 0.0136 0.000 1.854
0.998 0.904 0.906 0.888 0.0178
1.000 1.549 1.549 1.580 -0.0310
3 16 MM 14.96 26/9/14 16 0.998 1.543 1.546 1.580 -0.0339 -2.230 0.00
0.994 1.530 1.539 1.580 -0.0408

SHYONA LAND CROP Sign. SGS Sign GHB Sign.

SHYONA SGS GHB


Project - Architectural Desinging Enginering and construction of office Building, Ahmedabad. Gujarat
Package no.- : Contractor : Shayona Land Corporation
Location : GHB Site- Pragatinagar Consultant : SGS India Pvt. Ltd
Actual Std Unit
Sample Sample
Qty in Date of Challan Unit Weight Difference Average Average Remarks /
S.no Dia in mm Length in Weight in
MT receipt no/Lot no Weight Kg/m (+/-) Diff. %(-) Diff. %(+) Comments
m Kg
Kg/m IS 1786

MONTH: 2014
Acceptance criteria Asper IS : 1786 Up to and inculding 10 mm (+-) 8%, Over 10 mm to Including 16mm (+-)6% , Over mm (+-) 4%
1.000 0.581 0.581 0.617 -0.0360
1 10 MM 2.01 16/10/14 16 0.995 0.575 0.578 0.617 -0.0391 -5.873 0.00
1.001 0.584 0.583 0.617 -0.0336
1.001 2.519 2.516 2.469 0.0475
2 20 MM 6.16 16/10/14 16 0.994 2.501 2.516 2.469 0.0471 0.000 1.972
0.999 2.518 2.521 2.469 0.0515
1.000 3.882 3.882 3.858 0.0240
3 25 MM 15.41 16/10/14 16 1.000 3.883 3.883 3.858 0.0250 0.000 0.922
0.996 3.900 3.916 3.858 0.0577

SHYONA LAND CROP Sign. SGS Sign GHB Sign.

SHAYONA SGS GHB


Project - Architectural Desinging Enginering and construction of office Building, Ahmedabad. Gujarat
Package no.- : Contractor : Shayona Land Corporation
Location : GHB Site- Pragatinagar Consultant : SGS India Pvt. Ltd
Actual Std Unit
Sample Sample
Qty in Date of Challan Unit Weight Difference Average Average Remarks /
S.no Dia in mm Length in Weight in
MT receipt no/Lot no Weight Kg/m (+/-) Diff. %(-) Diff. %(+) Comments
m Kg
Kg/m IS 1786

MONTH: 2014
Acceptance criteria Asper IS : 1786 Up to and inculding 10 mm (+-) 8%, Over 10 mm to Including 16mm (+-)6% , Over mm (+-) 4%
1.001 0.398 0.398 0.395 0.0026
1 8 MM 0.535 6/11/2014 1046 1.000 0.391 0.391 0.395 -0.0038 -0.582 0.658
0.998 0.393 0.394 0.395 -0.0008
0.999 0.585 0.586 0.617 -0.0314
2 10 MM 1.02 6/11/2014 1046 1.000 0.585 0.585 0.617 -0.0320 -5.294 0.00
1.020 0.594 0.582 0.617 -0.0346

SHYONA LAND CROP Sign. SGS Sign GHB Sign.

SHAYONA SGS GHB


Project - Architectural Desinging Enginering and construction of office Building, Ahmedabad. Gujarat
Package no.- : Contractor : Shayona Land Corporation
Location : GHB Site- Pragatinagar Consultant : SGS India Pvt. Ltd
Actual Std Unit
Sample Sample
Qty in Date of Challan Unit Weight Difference Average Average Remarks /
S.no Dia in mm Length in Weight in
MT receipt no/Lot no Weight Kg/m (+/-) Diff. %(-) Diff. %(+) Comments
m Kg
Kg/m IS 1786

MONTH: 2014
Acceptance criteria Asper IS : 1786 Up to and inculding 10 mm (+-) 8%, Over 10 mm to Including 16mm (+-)6% , Over mm (+-) 4%
1.000 0.374 0.374 0.395 -0.0210
1 8 MM 2.015 17/8/14 238-1415 1.005 0.391 0.389 0.395 -0.0057 -2.321 0.00
0.998 0.393 0.394 0.395 -0.0008
1.000 0.628 0.628 0.617 0.0110
2 10 MM 1.02 17/8/14 238-1415 0.998 0.611 0.612 0.617 -0.0048 -0.778 2.018
0.997 0.629 0.631 0.617 0.0139

SHYONA LAND CROP Sign. SGS Sign GHB Sign.

SHYONA SGS GHB


Project - Architectural Desinging Enginering and construction of office Building, Ahmedabad. Gujarat
Package no.- : Contractor : Shayona Land Corporation
Location : GHB Site- Pragatinagar Consultant : SGS India Pvt. Ltd
Actual Std Unit
Sample Sample
Qty in Date of Challan Unit Weight Difference Average Average
S.no Dia in mm Length in Weight in
MT receipt no/Lot no Weight Kg/m (+/-) Diff. %(-) Diff. %(+)
m Kg
Kg/m IS 1786

MONTH: 2014
Acceptance criteria Asper IS : 1786 Up to and inculding 10 mm (+-) 8%, Over 10 mm to Including 16mm (+-)6% , Over mm (+-) 4%
0.998 0.379 0.380 0.395 -0.0152
1 8 MM 11.52 4/12/2014 14 1.000 0.411 0.411 0.395 0.0160 -4.646 4.051
1.020 0.381 0.374 0.395 -0.0215
1.000 0.593 0.593 0.617 -0.0240
2 10 MM 4.99 4/12/2014 14 1.030 0.636 0.617 0.617 0.0005 -4.198 0.08104
0.998 0.588 0.589 0.617 -0.0278
0.996 1.537 1.543 1.580 -0.0368
3 16 MM 1.02 4/12/2014 14 0.999 1.545 1.547 1.580 -0.0335 -2.169 0.00
0.999 1.546 1.548 1.580 -0.0325
1.040 2.538 2.440 2.469 -0.0286
4 20 MM 5.08 4/12/2014 14 1.06 2.540 2.396 2.469 -0.0728 -2.053 0.008
1.07 2.642 2.469 2.469 0.0002
1.050 3.985 3.795 3.858 -0.0628
5 25 MM 12.42 4/12/2014 14 1.020 3.903 3.826 3.858 -0.0315 -1.222 0.010
1.010 3.897 3.858 3.858 0.0004

SHYONA LAND CROP Sign. SGS Sign GHB Sign.


Remarks /
Comments

+-) 4%
Project - Architectural Desinging Enginering and construction of office Building, Ahmedabad. Gujarat
Package no.- : Contractor : Shayona Land Corporation
Location : GHB Site- Pragatinagar Consultant : SGS India Pvt. Ltd
Actual Std Unit
Sample Sample
Qty in Date of Challan Unit Weight Difference Average Average
S.no Dia in mm Length in Weight in
MT receipt no/Lot no Weight Kg/m (+/-) Diff. %(-) Diff. %(+)
m Kg
Kg/m IS 1786

MONTH: 2014
Acceptance criteria Asper IS : 1786 Up to and inculding 10 mm (+-) 8%, Over 10 mm to Including 16mm (+-)6% , Over mm (+-) 4%
0.994 0.405 0.407 0.395 0.0124
1 8 MM 5.08 13-Nov-14 6 1.010 0.417 0.413 0.395 0.0179 -2.835 3.835
1.003 0.385 0.384 0.395 -0.0112
1.012 0.598 0.591 0.617 -0.0261
2 10 MM 18.45 13-Nov-14 6 1.030 0.636 0.617 0.617 0.0005 -3.331 0.08104
1.000 0.602 0.602 0.617 -0.0150
1.000 1.537 1.537 1.580 -0.0430
3 16 MM 2.54 13-Nov-14 6 1.002 1.570 1.567 1.580 -0.0131 -2.002 0.00
1.020 1.572 1.541 1.580 -0.0388
1.000 2.521 2.521 2.469 0.0520
4 20 MM 2 13-Nov-14 6 1.027 2.538 2.471 2.469 0.0023 0.000 0.908
1.015 2.542 2.504 2.469 0.0354

SHYONA LAND CROP Sign. SGS Sign GHB Sign.


Building, Ahmedabad. Gujarat
Shayona Land Corporation
SGS India Pvt. Ltd

Remarks /
Comments

0 mm (+-) 8%, Over 10 mm to Including 16mm (+-)6% , Over mm (+-) 4%

GHB Sign.
Project - Architectural Desinging Enginering and construction of office Building, Ahmedabad. Gujarat
Package no.- : Contractor : Shayona Land Corporation
Location : GHB Site- Pragatinagar Consultant : SGS India Pvt. Ltd
Actual Std Unit
Sample Sample
Qty in Date of Challan Unit Weight Difference Average Average Remarks /
S.no Dia in mm Length in Weight in
MT receipt no/Lot no Weight Kg/m (+/-) Diff. %(-) Diff. %(+) Comments
m Kg
Kg/m IS 1786

MONTH: 2014
Acceptance criteria Asper IS : 1786 Up to and inculding 10 mm (+-) 8%, Over 10 mm to Including 16mm (+-)6% , Over mm (+-) 4%
1.015 0.623 #DIV/0! 0.617 #DIV/0!
1 10 MM 4.8 18-Dec-14 9237 1.020 0.627 0.615 0.617 -0.0023 #DIV/0! 0.00
1.000 0.615 0.615 0.617 -0.0020
1.000 0.879 0.879 0.888 -0.0090
2 12MM 7.09 18-Dec-14 9237 0.998 0.874 0.876 0.888 -0.0122 -1.306 0.00
0.995 0.870 0.874 0.888 -0.0136
1.000 1.606 1.606 1.580 0.0260
3 16MM 12.01 18-Dec-14 9237 1.000 1.610 1.610 1.580 0.0300 1.772 0.000
0.994 1.595 1.605 1.580 0.0246

SHYONA LAND CROP Sign. SGS Sign GHB Sign.

#VALUE!
Project -
Package no.- : Contractor :
Location : Consultant :
Actual Std Unit
Sample Sample
Qty in Date of Challan Unit Weight Difference Average Average Remarks /
Sr.no Dia in mm Length in Weight in
MT receipt no/Lot no Weight Kg/m (+/-) Diff. %(-) Diff. %(+) Comments
m Kg
Kg/m IS 1786
1 2 3 4 5 6 7 8 9 10 11 12 13
MONTH:
Acceptance criteria Asper IS : 1786 Up to and inculding 10 mm (+-) 8%, Over 10 mm to Including 16mm (+-)6% , Over mm (+-) 4%

Clinet Consulant Contract