Assignment NO 1

1.Explain the concept of cost of quality and value of quality by using suitable graph

2.List objectives of quality control

3.What is meant by ‘5S’?State meaning of each “s” in details

4.Describe any 3 principle element of TQM

5.Write any four advantages and disadvantages of ISO9000

6.Explain six sigma with suitable example.

7. Compare inspection and quality control

Assignment NO 2
1.What is SQC?State the benefits of SQC

2.State different SQC Tools and explain any one

3.Differentiate between variable and attribute inspection on any four parameters

4. The following are the results of 20 lots each lot contains 750 objects number of defective objects in each lot are as
follows 48, 83, 70, 85, 90, 56, 54, 71, 36, 49, 29, 51, 28, 33, 37, 80, 70, 48, 67, 57. Analyze the data on the base of
appropriate control chart. Calculate control limit and state whether the process is in control.

5. Draw a neat sketch of O.C curve,show the different region and explain the meaning of four region

6.Explain double sampling plan with suitable block diagram.

7.Compare 100% inspection with sampling inspection

8.Table given below shows number of defectives found in inspection of a lot for 100 plug each.Draw control chart and
check whether process is in control or not?

Lot number 1 2 3 4 5 6 7 8 9 10

Number of 6 4 2 3 11 0 3 8 7 9
defectives

9.Number of defects found in an inspection of 10 assemblies are 2,4,5,3,1,5,2,8,6,4 respectively.Draw appropriate control
chart and conclude

10.The components were taken in subgroup of 5 items,10 such subgroup were checked.The X Bar and R values noted are

Subgroup 1 2 3 4 5 6 7 8 9 10
number

X Bar 34 30.8 35 33 33.8 35.8 34 33.8 31.8 33

R 4 2 5 5 19 4 14 7 9 5

Draw appropriate control chart and conclude.Take A2=0.577,D3=0,D4=2.11