BBE Project Daily Activity Tracking sheet

Date Activities of Work SAFETY ABSERVATION Improvement points

1) Use impact gloves while doing rigging activity.


1)some workers using in american 2) Provide
11-May-24 Seggregation of Mechanical items in yard gloves 2) Rest shelter missing in the rest shelters near the work location.
location. 3) Arrange waste skips
3)No waste skips available
1).when new employee enter into the 1).All employee must wear PPE while enter
work location not wear the PPE. intothe workplace.
2)Slip trip Fall 2) Proper house keeping.
12-May-24 unloading activities in worksite 3) Rest shelter
missing in the location. 3) Provide rest shelters near the work
4).Some of the websling was not location. 4).All lifting equipment should be
certified by thirdparty certified by Thirdparty
1) Housekeeping 1)keep following 5s method.unwanted metrial
2)Drinking water is not good. remove from the site..
3)Rigging chargehand not here 2)provide RO filtter
13-May-24 Bed preparation and electrial works in site.
3).provide one rigger chargehand.

Vimal Ravi Site Superviosr / Planning Site Incharge