Project Network Diagram
Project Network Diagram
1_2_3 7
1_2_4_6_7_8_9_10 17
1_2_5_6_7_8_9_10 16
So, the critical path is 1_2. it means that Any delay in gathering information or
writing the project book would directly delay the project's overall completion .
Therefore, they represent critical steps that need to be carefully managed to ensure
the project stays on schedule.
Table 2 Show the tabular form.