PROJECT: The Vyne-Phase 3 JOB ACTIVITY: LIFTING WORK (MOBILE CRANE) LEGAL REQUIREMENT:
OSHA 1994, FMA 1967 (BOWEC Reg. 1986)
3 Ensure outriggers are - Crane Fatality / Ensure all 2 25 50 -Check for hydraulic oil
extended topple Major Injury outriggers are level and for leakages.
2
fully
- Loss of extended. - Out triggers are fully
load extended.
4 Ensure proper base Crane Fatality Use 2 25 50 Ensure operator check
plate topple timber/steel the level for stability.
2
plate as base
5 Ensure proper parking Crane Fatality Supervisor 2 25 50 2 Ensure operator check
level topple check prior to the level for stability.
start work.
6 Check supporting Loss of load Fatality / Supervisor 3 Check wire rope, limit
devices Major Injury check prior to switches hook, latch and
start work. checklist
1 - Elimination
AXVENTURE SDN BHD
JOB SAFETY ANALYSIS