Pacific Pharmaceuticals Ltd.

CONFIDENTIAL
Performance Qualification Protocol for Liquid Manufacturing Revision 02
Tank (PRTK-107)

PERFORMANCE QUALIFICATION PROTOCOL

LIQUID MANUFACTURING TANK (PRTK – 107)

Protocol Number: TK-PQ-18-060

Protocol Date: January 10, 2018

Prepared by: Validations Department

Pacific Pharmaceuticals Ltd

Lahore-Pakistan

___________________________________________________________________________________
Date: Jan. 10, 2018 Page 1 of 8 protocol # TK-PQ-18-060
Pacific Pharmaceuticals Ltd. CONFIDENTIAL
Performance Qualification Protocol for Liquid Manufacturing Revision 02
Tank (PRTK-107)

AUTHOR:

Name: Ammar Ali Title: Validation Officer

Signature: ___________________ Date: ______________

APPROVAL

VALIDATION :

Name: M. Farhan Bhatti Title: Deputy Manager Validation

Signature: ___________________ Date: ______________

ENGINEERING:

Name: Naveed Iqbal Title: Plant Engineer

Signature: ___________________ Date: ______________

QUALITY ASSURANCE:

Name: Ghazi Mustansar Riaz Title: General Manager Quality Assurance

Signature: ___________________ Date: ______________

AUTHORIZED BY

DIRECTOR OPERATIONS:

Name: Afifa Irfan Title: Director Operations

Signature: ___________________ Date: ______________

___________________________________________________________________________________
Date: Jan. 10, 2018 Page 2 of 8 protocol # TK-PQ-18-060
Pacific Pharmaceuticals Ltd. CONFIDENTIAL
Performance Qualification Protocol for Liquid Manufacturing Revision 02
Tank (PRTK-107)

TABLE OF CONTENTS

No. TITLE PAGE #

1. OBJECTIVE-----------------------------------------------------------------------------------------4

2. SCOPE------------------------------------------------------------------------------------------------4

3. RESPONSIBILITY---------------------------------------------------------------------------------4

4. OPERATIONAL AND PERFORMANCE QUALIFICATION TESTS--------------------5

5. VARIATION/ DEVIATION/MAJOR MAINTENANCE SINCE LAST PQ--------------6

6. PROCEDURES--------------------------------------------------------------------------------------7

7. STATISTICAL ANALYSIS-----------------------------------------------------------------------8

___________________________________________________________________________________
Date: Jan. 10, 2018 Page 3 of 8 protocol # TK-PQ-18-060
Pacific Pharmaceuticals Ltd. CONFIDENTIAL
Performance Qualification Protocol for Liquid Manufacturing Revision 02
Tank (PRTK-107)

1.0 OBJECTIVE:

The objective of this protocol is to describe performance qualification (PQ) experiments


for Liquid Manufacturing Tank.

2.0 SCOPE

This scope of this PQ pertains to qualification of Liquid Manufacturing Tank, ID # PRTK


– 107

3.0 RESPONSIBILITY:

3.1 It is the responsibility of Liquid Section operator to perform PQ test as


described in this protocol according to the standard operating procedures #
PRSY/02/0017

3.2 It is the responsibility of Validation officer to collect raw data

3.3 It is the responsibility of validations department to prepare performance


qualifications protocol

3.4 It is the responsibility of validation, engineering and quality assurance managers


to approve the protocol

3.5 It is the responsibility of director operations to authorize the protocol

Instrument / Equipment / System : Liquid Manufacturing Tank


Location : Liquid
Department :Production ID # : PRTK-107
Section
To be performed after ,

Re-Operational Qualification Modification Relocation Out of Spec. Results or √ Re-Qualification


Reason for above selection: To qualify performance parameters of Liquid Manufacturing Tank after 5
years.

4.0 Operational and Performance Qualification Tests:

No Test to be performed Acceptance Criteria

___________________________________________________________________________________
Date: Jan. 10, 2018 Page 4 of 8 protocol # TK-PQ-18-060
Pacific Pharmaceuticals Ltd. CONFIDENTIAL
Performance Qualification Protocol for Liquid Manufacturing Revision 02
Tank (PRTK-107)

1 Speed Up to 500 RPM


(max)

2 Volume Up to 1000 Liter


(capacity)

3 Temperature 22°C -26°C (Room Temperature)

5.0 Variation/ Deviation/ Major maintenance Since Last PQ:

Description Of Deviation/ Performance Impact


Sr. No. Status last PQ
Change/Major Maintenance Assessment

1 Deviation/ Change/ Major

___________________________________________________________________________________
Date: Jan. 10, 2018 Page 5 of 8 protocol # TK-PQ-18-060
Pacific Pharmaceuticals Ltd. CONFIDENTIAL
Performance Qualification Protocol for Liquid Manufacturing Revision 02
Tank (PRTK-107)

2 Results Variation

3 Major Maintenance

6.0 Procedures:
To evaluate performance qualification of Liquid Manufacturing Tank (PRTK-107), the following
products were selected to perform the run.
Sr. Test 1
Test Parameters Acceptance Criteria
No. Product Information
Product Product 1
1 Speed (RPM) As per BMR
Name
2 Batch No Volume (Liter) As per BMR
Batch
3 Temperature (°C) As per BMR
Size
Date of
4
PQ
5 Stage

___________________________________________________________________________________
Date: Jan. 10, 2018 Page 6 of 8 protocol # TK-PQ-18-060
Pacific Pharmaceuticals Ltd. CONFIDENTIAL
Performance Qualification Protocol for Liquid Manufacturing Revision 02
Tank (PRTK-107)

Sr. Test 2
Test Parameters Acceptance Criteria
No. Product Information
Product Product 2
1 Speed (RPM) As per BMR
Name
2 Batch No Volume (Liter) As per BMR
Batch
3 Temperature (°C) As per BMR
Size
Date of
4
PQ
5 Stage

Sr. Test 3
Test Parameters Acceptance Criteria
No. Product Information
Product Product 3
1 Speed (RPM) As per BMR
Name
2 Batch No Volume (Liter) As per BMR
Batch
3 Temperature (°C) As per BMR
Size
Date of
4
PQ
5 Stage

7.0 Statistical Analysis


(Perform any calculation regarding test, if required on this page)

No. Statistical Analysis

___________________________________________________________________________________
Date: Jan. 10, 2018 Page 7 of 8 protocol # TK-PQ-18-060
Pacific Pharmaceuticals Ltd. CONFIDENTIAL
Performance Qualification Protocol for Liquid Manufacturing Revision 02
Tank (PRTK-107)

1 Mean

2 Standard deviation

3 Coefficient of Variance

___________________________________________________________________________________
Date: Jan. 10, 2018 Page 8 of 8 protocol # TK-PQ-18-060