Non-Conformance Report / Corrective Action Request

Project: TGESPL
NCR / CAR No: EHS/NCR/18
Date: 08-04-2024
To: ACPL
Attention: Mr. Dhananjay kumar
From: JLL
Description of Non Conformance: (Image attached) It has been observed that hadn't
conducted the necessary leak test for the oxygen & DA (Gas Cylinder) and
combusitable material placed nearby it.

Description of the problem which requires rectification:


Conduct a site inspection before commencing of any job for ensuring no combustible material is
present in the area.
Verify the gas cutting set's integrity through on-site leak testing prior to starting work.
Site in charge have reviewed and approved the daily checklist.
Replace the NRV if founds any leak while testing and submit the test report.
Provide the effective training to the operator & workers regarding the Gas Cutting check points
Ensure that the Pre-toolbox is been carried out in the premises.
Inspect the site conidition by the Project Manager & Safety Officer before start of the work.

Date by which action must be completed : 08/04/2024


Closure report has to submit with action plan and evidence of improvement.
Signed: Balu Nagendra Position: HSE Manager Date:08/04/2024

Action Taken: 1. Effective training conducted to the operator & workers regarding the Gas Cutting
work.
2. Flashback Arrestor replaced and Leakage test conducted.
3. Leakage test conducted & now no leakage found.
4. Combustible materials has been removed from the work area.

Does the Client need to approve the above Action? Yes No


If the Client needs to approve, has it been approved? Yes No
Follow-up review/report:
Has the Action taken been effective? Yes No (If No, a new Notice may need to be issued)

Signed: Position: Date:


The company on which this NCR is served is required to take action in order to rectify the substandard conditions
Should further action and/or costs be pursued against the company on which this notice is served? Yes No
Does the Project Site Set Up System require modification to prevent a recurrence? Yes No
Action required:

By Whom: Completed: