Inspection Activities for 16/05/2024 (Activity Day)
S/N Work Items Site Location RFI Time Remark
Daily Notice
No.
Axis/ WTG KP
Execution
Morning/
1 Foundation Rebar placing and bottom Rebar Inspection WTG-23 -
Afternoon
Bottom, Top, Auxiliary Flange Installation and Level Morning/
2 WTG-20 -
Checking Afternoon
Trench/sunk excavation, MVL/FO pipe installation and Morning/
3 WTG-19 -
Concreting Afternoon
Morning/
4 Ditch Preparation and concreting 2 -
Afternoon
Daily Notice
WTG- Morning/
5 Grounding Work -
04/06/08 Afternoon
6 Component Storage area Geotextile and Subbase placing WTG-05 - Morning
7 Visual Inspection to start Backfill Work WTG-06 - Afternoon
8 Main crane Hardstand Bed Preparation WTG-16 - Morning
Morning/
9 Material Dumping for Subgrade Correction 5 0+500-2+000
Afternoon
Quality and Tests
Facility Area
1 Sand Calibration for FDT Test - Morning
Lab
Daily Notice