DAILY REPORT

Project : Installation Electrical Fiber Recovery Day : Wednesday


Location : PT Dayasa Aria Prima, Driyorejo, Kabupaten Gresik, Jawa Timur 61177 Date : November,01, 2023
Contractor : PT. LAROS MULTI INDOTEKNIK Hours : 08.00 - 17.00
P/O No. : 3300003990

MANPOWER DESCRIPTION WORK & LOCATION VOLUME PROGRESS


I. MANAGEMENT Yesterday Today
Site Manager : Utomo Sunarko 1 Stock Preparation SP2,3
PIC : Habib 1 I. Pulling Cable
- Pulling cable 150mm for power from panel ACB to panel Fiber recovery 3 unit 3 unit @ 158 mtr 100% -
- Pulling cable 150mm for power from panel ACB to panel Fiber recovery 4 unit 4 unit @ 158 mtr - -
- Pulling cable 8 core For Digital Input & Digital Output (DO&DI) from MCC to PLC 18 unit @37 mtr 100% -
- Pulling cable Analog Input & Analog Output (AI & AO) from MCC to PLC 10 unit @ 37 mtr 100% -
- Pulling Cable Grounding PE (MCC Panel to JB Grounding) 23 mtr 100% -
- Pulling Cable Grounding IE (PLC Panel to JB Grounding) 25 mtr 100% -
- Pulling Cable Grounding PE (Body PLC to Busbar Grounding MCC Panel) 11 mtr 100% -
- Pulling Cable Power from UPS to PC Desktop Fiber Recovery 32 mtr 100% -
- Pulling Cable Ethernet from PLC to PLC 40 mtr 100% -
Sub Total I 2
II. DIRECT Pulling Cable MCC to Motor
Construction : 1. WW make up from Tower to DAF feed chest 96 mtr 100% -
Syaiful 1 2. Sludge Pump A (Pulling New Cable N2XY 4 Core) 42 mtr 100% -
Abdul Ghoni 1 3. DAF Recirculation pump A (motor start delta) 51 mtr 100% -
Subagyo 1 4. 1st Stage strainer feed pump (Conus) 43 mtr 100% -
Eko Mauludin 1 5. 2nd Stage strainer feed pump 42 mtr 100% -
Maskur 1 6. HP shower pump 44 mtr 100% -
Nofi 1 7. Sealing make up pump 42 mtr 100% -
Nasihin 1 8. LP shower make up pump 43 mtr 100% -
9. DAF Scoope motor (Pulling New Cable N2XY 4 Core) 41 mtr 100% -
10. DAF Carriage motor (Pulling New Cable N2XY 4 Core) 44 mtr 100% -
11. Conus strainer motor 41 mtr 100% -
12. Auto pressure strainer 46 mtr 100% -
13. Coagulant feeding unit feeder 44 mtr 100% -
14. Polymer feeding unit feeder 46 mtr 100% -
15. Air compressor 43 mtr 100% -
16. Spare breaker and space for starter 37kW - -
17. Spare breaker and space for starter 3.7kW - -
18. Feeder 63A - -
19. Feeder 32A (UPS PLC) 37 mtr 100% -

II. Termination Cable


- Termination Cable DI DO at PLC Panel 1 set 100% -
- Termination Cable DI DO at MCC Panel 1 set 100% -
- Termination Cable AI AO at PLC Panel 1 set 100% -
- Termination Cable AI AO at MCC Panel 1 set 100% -
- Termination Cable Power 150mm at Panel Feeder ACB Fiber recovery 7 Unit 45% -
- Termination Cable Grounding PE & IE 1 set 50% -
- Termination Cable Grounding PE (Body PLC to Busbar Grounding MCC Panel) 1 set 100% -
- Termination Output UPS for PC Desktop (Side UPS) 1 set 100% -
- Termination Cable Ethernet PLC to PC 1 set 100% -
- Termination Cable Motor VFD 1 set 100% -

PROBLEM

---

SOLUTION
---
Sub Total II 7
Total Man Power 9
Material Unit Qt Tools Unit Qty Tools Unit Qty
Gloves set 1
Body Hardness set 3

Ra Note :
Referensi (Drawing/Information) : Weather Bright Cloudy
in
Morning ✔
Midday ✔
Afternoon ✔
Night
Approved By,

Utomo S.
DAILY REPORT
Project : Installation Electrical Fiber Recovery Day : Wednesday
Location : PT Dayasa Aria Prima, Driyorejo, Kabupaten Gresik, Jawa Timur 61177 Date : November,01, 2023
Contractor : PT. LAROS MULTI INDOTEKNIK Hours : 08.00 - 17.00
P/O No. : 3300003990

MANPOWER DESCRIPTION WORK & LOCATION VOLUME PROGRESS


I. MANAGEMENT Yesterday Today
Site Manager : Utomo Sunarko 1 Stock Preparation SP2,3
PIC : Eko Iswanto 1
Termination Cable Motor at MCC Panel & Motor
1. WW Make Up from Tower to DAF Feed Chest 1 set 100% -
2. Sludge pump A 1 set 100% -
3. DAF Recirculation pump A (motor start delta) 1 set 50% -
Sub Total I 2 4. 1st Stage strainer feed pump (Conus) 1 set 50% -
II. DIRECT 5. 2nd Stage strainer feed pump 1 set 50% -
Construction : 6. HP shower pump 1 set 50% -
Syaiful 1 7. Sealing make up pump 1 set 50% -
Abdul Ghoni 1 8. LP shower make up pump 1 set 50% -
Subagyo 1 9. DAF Scoope motor 1 set 100% -
Eko Mauludin 1 10. DAF Carriage motor (Side Motor) 1 set 100% -
Maskur 1 11. Conus Strainer motor 1 set 50% 100%
Nofi 1 12. Auto pressure strainer 1 set 50% -
Nasihin 1 13. Coagulant feeding unit feeder 1 set 50% -
14. Polymer feeding unit feeder 1 set 50% -
15. Air compressor 1 set 50% -
16. Spare breaker and space for starter 37kW 1 set - -
17. Spare breaker and space for starter 3.7kW 1 set - -
18. Feeder 63A 1 set - -
19. Feeder 32A (UPS PLC) 1 set 50% -

III. Installation
- Install ACB c/w Acc 1 set 100% -
- Loading MCC & PLC Panel 1 lot 100% -
- Installation MCC & PLC Panel 1 lot 100% -
- Tapping Busbar Power Feeder 1 lot 100% -
- Install Tray Cable 300mm for Feeder Fiber Recovery 1 lot 100% -
- Install Tray Cable 200mm For Daf Carriage Motor (Repair) 1 lot 100% -
- Install Tray Cable 200mm For Conus Strainer Motor 1 lot 100% -
- Fabrication Support Tray Motor WW Make Up From Tower To DAF Feed Chest 1 lot 100% -
- Install Tray Cable 200mm For Motor WW Make Up From Tower To DAF Feed Chest 1 lot 100% -
- Fabrication Support Tray Motor Sludge Pump A 1 lot 100% -
- Fabrication Support Steel Conduit for Conus Strainer Motor 1 lot 100% -

IV. SAT PLC Panel 1 lot 100% -


- Internal Function Test 1 lot 50% 75%

PROBLEM

---

SOLUTION
---
Sub Total II 7
Total Man Power 9
Material Unit Qt Tools Unit Qty

Ra Note :
Referensi (Drawing/Information) : Weather Bright Cloudy
in
Morning ✔
Midday ✔
Afternoon ✔
Night
Approved By,

Utomo S.
DAILY REPORT
Project : Installation Electrical Fiber Recovery Day : Wednesday
Location : PT Dayasa Aria Prima, Driyorejo, Kabupaten Gresik, Jawa Timur 61177 Date : November,01, 2023
Contractor : PT. LAROS MULTI INDOTEKNIK Hours : 08.00 - 17.00
P/O No. : 3300003990

MANPOWER DESCRIPTION WORK & LOCATION VOLUME PROGRESS


I. MANAGEMENT Yesterday Today
Site Manager : Utomo Sunarko 1 Stock Preparation SP2,3
PIC : Eko Iswanto 1
V. Insulation & Winding Motor Test
- Motor HP Shower Pump 1 lot 100% -
- Motor LP Shower Make Up Pump 1 lot 100% -
- Motor Sludge Pump A 1 lot 100% -
Sub Total I 2 - Motor WW Make Up From Tower To DAF 1 lot 100% -
II. DIRECT - Conus Strainer Motor 1 lot 50% -
Construction : - DAF Scoope Motor 1 lot 50% -
Syaiful 1 - DAF Carriage Motor 1 lot 100% -
Abdul Ghoni 1 - 1st Stage Strainer Feed Pump (Conus) Motor 1 lot 100% -
Subagyo 1 - 2nd Stage Strainer Feed Pump Motor 1 lot 100% -
Eko Mauludin 1 - DAF Recirculation Pump A Motor 1 lot 100% -
Maskur 1
Nofi 1 VI. Insulation Cable Test
Nasihin 1 - Motor WW Make Up From Tower To DAF Feed Chest 1 lot 100% -
- Sludge pump A 1 lot 100% -
- 1st Stage strainer feed pump (Conus) 1 lot 100% -
- 2nd Stage strainer feed pump 1 lot 100% -
- Sealing make up pump 1 lot 100% -
- LP shower make up pump 1 lot 100% -
- DAF Scoope motor 1 lot 100% -
- DAF Carriage motor (Side Motor) 1 lot 100% -
- DAF Recirculation Pump A 1 lot 100% -
1
1 VII. Tidy Up Cable
- Tidy Up Cable Feeder Coagulant & Polymer 1 lot 100% -
- Tidy Up Cable Power from UPS to PC Desktop Fiber Recovery 1 lot 100% -
- Tidy Up Cable DAF Carriage Motor & DAF Scoope Motor 1 lot 100% -

VIII. Engineering PC Desktop 1 set 100% -


- Set Engineering PC Desktop Fiber Recovery on Table 1 set 100% -
- Install Stop Contact for PC Desktop 1 set 100% -

PROBLEM
---

SOLUTION
---
Sub Total II 7
Total Man Power 9
Material Unit Qt Tools Unit Qty

Ra Note :
Referensi (Drawing/Information) : Weather Bright Cloudy
in
Morning ✔
Midday ✔
Afternoon ✔
Night
Approved By,

Utomo S.
DAILY REPORT
Project : Installation Electrical Fiber Recovery Day : Wednesday
Location : PT Dayasa Aria Prima, Driyorejo, Kabupaten Gresik, Jawa Timur 61177 Date : November,01.2023
Contractor : PT. LAROS MULTI INDOTEKNIK Hours : 08.00 - 17.00
P/O No. : 3300003990

MANPOWER DESCRIPTION WORK & LOCATION VOLUME PROGRESS


I. MANAGEMENT Yesterday Today
Site Manager : Utomo Sunarko 1 Stock Preparation SP2,3
PIC : Eko Iswanto 1
IX. Installation Grounding
- Installation Steel Conduit & Flexible Conduit to Box Panel Grounding PE & IE 2 Lot 75% 85%
- Finishing Grounding Root 2 Lot 75% 80%

Sub Total I 2
II. DIRECT
Construction :
Syaiful 1
Abdul Ghoni 1
Subagyo 1
Eko Mauludin 1
Maskur 1
Nofi 1
Nasihin 1
Planning Next Day (Thursday, 01 Nov 23)
1. Finishing Grounding Root
2. Priparation Pulling Cable Power Layer to 2 R.S.T.N
3. Pulling Cable Instrument (Equipment Mechanic Finish)

PROBLEM
---

SOLUTION
---
Sub Total II 7
Total Man Power 9
Material Unit Qt Tools Unit Qty

Ra Note :
Referensi (Drawing/Information) : Weather Bright Cloudy
in
Morning ✔
Midday ✔
Afternoon ✔
Night
Approved By,

Utomo S.
DOCUMENTATION DAILY REPORT

Project : Installation Electrical Fiber Recovery Day : Wednesday


Location : PT Dayasa Aria Prima Driyorejo, Kabupaten Gresik, Jawa Timur 61177 Date : November,01.2023
Contractor : PT. LAROS MULTI INDOTEKNIK Hours : 08.00 - 17.00
P/O No. : 3300003990

1. Daily TBM PT. LAROS MULTI INDOTEKNIK

2.Finishing Grounding Root

3. Installation Steel Conduit & Flexible Conduit to Box Panel Grounding