Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

855429

research-article2019
WMR0010.1177/0734242X19855429Waste Management & ResearchVilventhan et al.

Original Article

Waste Management & Research

Value stream mapping for identification


2019, Vol. 37(8) 815­–825
© The Author(s) 2019
Article reuse guidelines:
and assessment of material waste in sagepub.com/journals-permissions
DOI: 10.1177/0734242X19855429
https://doi.org/10.1177/0734242X19855429

construction: A case study journals.sagepub.com/home/wmr

Aneetha Vilventhan1 , VG Ram2 and S Sugumaran3

Abstract
Construction sites are plagued with numerous problems, such as improper planning and management, high amounts of waste generation
and low awareness of waste reduction. Construction and demolition waste literature provides several best practises and prescriptive
strategies that help minimise waste during construction. However, it lacks in the systematic identification and minimisation approach
of all possibilities of waste. Therefore, studies focusing on principles and tools that help systematically analyse the inefficiencies of
on-site processes leading to waste generation and philosophies addressing waste minimisation are necessary. As eliminating waste is
one of the key lean principles, this article discusses the need and importance of integrating the lean construction with the construction
and demolition waste management. This article aims to estimate and assess the causes of waste generation in a high-rise building
construction through a case study in Chennai city (India) using value stream mapping, a key lean construction tool. Onsite monitoring
and measurement were performed to quantify the amount of waste generated. A waste generation rate of 66.26 kg m−2 was identified,
of which concrete, cement mortar and brick waste represented almost 90% of the total construction waste. Direct observation and
interviews of site personnel were conducted to understand the causes of waste generation. A strategic framework has been proposed
to improve construction and demolition waste minimisation depicting the synergy of combining lean construction principles with
construction and demolition waste management strategies. The proposed framework helps in the systematic identification, assessment
and minimisation of on-site construction waste generation.

Keywords
Construction waste, estimation, causes of waste generation, waste minimisation, lean construction principles, value stream mapping

Received 5th November 2018, accepted 13th May 2019 by Associate Editor David E. Ross.

Introduction C&D waste literature provides several best practises and pre-
scriptive strategies, including prefabrication, use of Building
Construction industry generates a large amount of waste all Information Modelling (BIM) regulations, incentives, etc., that
over the world. Waste generation rates in construction projects help minimise waste during construction (Esa et al., 2017; Saez
range between 17 kg m−2 to 158 kg m−2 and about 910 kg m−2 to et al., 2013; Wang et al., 2015).
1636 kg m−2 in the case of demolition projects (Ram and Kalidindi, However, construction projects are complex, fragmented and
2017). The sheer quantum of waste from construction industry known to pose a high amount of resistance to change in work prac-
being reported in literature substantiates the need for better ways tises (Bresnen and Marshall, 2001). Moreover, construction pro-
of managing them (Wu et al., 2014). Even today, a major quantity jects are so unique that there is some learning involved in every
of construction and demolition (C&D) waste generated is being project (Bresnen et al., 2005). A set of prescriptive strategies just
dumped in landfill or at open spaces or disposed of illegally in the undermines the uniqueness of construction projects and lacks guar-
waterbodies and roadsides in most of the countries (Mah et al., anteed identification and minimisation of all possibilities of waste
2016; Paz and Lafayette, 2016; Ram and Kalidindi, 2017; Saez
et al., 2015). C&D waste majorly consists of materials, such as
bricks, blocks, concrete debris, metal, wood and packaging 1National Institute of Technology Warangal, Telangana, India
2Indian Institute of Technology Madras, Chennai, India
wastes, which are reduceable, reusable and recyclable to a large 3Construction Engineering and Management, SRM University,
extent (Esa et al., 2017; Lau et al., 2008). Lack of awareness about Kattankulathur, India
C&D waste stream, cost concerns, influence of attitudes and other
Corresponding author:
people-related factors have been reported to be significant barriers
Aneetha Vilventhan, National Institute of Technology Warangal,
among several others in improving C&D waste management Telangana 506004, India.
(Al-sari et al., 2012; Rao et al., 2007; Teo and Loosemore, 2001). Emails: aneetha@nitw.ac.in; aneethavils@gmail.com
816 Waste Management & Research 37(8)

(Bresnen et al., 2005). Therefore, studies focused on principles and has been reported to occur in all the stages of construction start-
tools that help systematically analyse the inefficiencies of on-site ing from conception, design, construction and operation. A large
processes leading to waste generation and philosophies addressing amount of research attention in the literature has been towards
waste minimisation is necessary in C&D waste literature. An estimating the amount of C&D waste generation in various
orthogonal stream of literature on lean construction, adapted from regions. Detailed reviews of estimation studies could be found in
lean manufacturing, is rich in terms of tools and methods that were articles by Mália et al. (2013) and Wu et al. (2014). While these
exclusively developed for identifying bottlenecks and inefficien- studies discussed a number of quantification tools that utilise dif-
cies in construction processes. ferent kinds of data for estimation and forecasting, systematic
The lean construction philosophy streamlines flow in activi- tools, such as those in lean literature, to study processes with
ties and minimises waste associated in the processes (Ballard focus on waste generation is lacking.
and Howell, 1994; Koskela, 1992). Establishing and enabling A source of waste framework, as proposed by Gavilan and
flow in a process gives a clear focus on waste in the processes. Bernold (1994), consisting of six categories of sources of
Thus, waste minimisation is the core concept of lean and flow waste – design, procurement, materials’ handling, operation,
visualisation aids in achieving that objective. While site person- residual and others – has been found to be very informative.
nel are accustomed to associate waste to material waste gener- Several studies have explored the sources of waste in con-
ated during the project, lean thinking advocates a holistic picture struction and the root causes of such waste generation. Tam
of waste to include other kinds, such as waiting time, non-value- (2008) had reported that the major source of construction
adding activities and transportation of materials (Koskela, waste is concreting works (almost 29% of the waste) followed
1992). This other non-value-adding processes has potential to by reinforcement works, formwork, scaffolding, material han-
lead to material waste generation if they are left unchecked. dling and finishing works. The results of the study conducted
Lean thinking could help us systematically screen out all the in 22 construction sites by Poon et al. (2004a) reported that
waste-producing processes and improve waste management per- formwork, finishing activities, concreting and masonry works
formance. Moreover, the role of lean principles and practises has contribute major amounts of construction waste. The order of
been studied in areas, such as improving coordination among magnitude of waste production in these processes have been
project participants, aiding in the adoption of technologies, such reported to be slightly different in different studies (Esin and
as BIM (Ballard and Howell, 2005; Mahalingam et al., 2015). Cosgun, 2007; Formoso et al., 2002; Li and Yang, 2014). This
But literature combining lean and construction waste manage- variation among construction projects is to be noted as they
ment is limited in the extant literature. represent the uniqueness of construction projects in a way.
There are several studies on the integration of lean/green man- Measures to achieve waste minimisation in retrofit projects
agement in the manufacturing sector (Dües et al., 2013; Fercoq were identified to be a reusable and flexible design, integrated
et al., 2016; Garza-Reyes, 2015; Martínez-Jurado and Moyano- waste management planning, proper documentation, including
Fuentes, 2014). In the construction industry, Hosseini et al. as-built drawings and establishment of benchmarks (Li and Yang,
(2012) has tried to implement lean construction theory to con- 2014). However, managerial problems in many stages before
struction waste management. However, research in the integra- production, such as design, planning and procurement, have been
tion of lean with construction material waste management is reported (Esin and Cosgun, 2007; Formoso et al., 2002). Formoso
limited. Hence, the objectives of this article are (1) to quantify et al. (2002) studied 74 building construction sites and concluded
and assess construction material waste on site (2) to develop a that a significant amount of waste was generated owing to flow
lean strategic framework for waste minimisation on site. activities, such as handling and transportation of inventories,
The article is organised as follows: The next section describes which are overlooked by site personnel.
the literature review covering both the literature on C&D waste Simulation techniques of waste handling processes have been
and lean construction literature and highlights the gap in the lit- advocated to improve waste optimisation methods. A waste
erature. Then, the research methodology adopted in this research management mapping model could assist in the planning of
has been introduced. The application of a value stream mapping operational strategies and thereby help solve weaker areas (Lu
(VSM) tool in the assessment of material waste in a building con- et al., 2006). Incorporation of new tools, such as BIM, has been
struction case study and the results have been presented in the shown to help in waste estimation as well as planning for waste
subsequent sections. A discussion on the proposed strategic management strategies and related equipment management
framework that integrates lean and waste management principles (Cheng and Ma, 2013). Thus, a transition from prescriptive strat-
precedes the main conclusions that are put forth in the end. egies to the need for a systemic and site-specific approach could
be inferred.
Literature review
C&D waste literature Lean construction literature
Construction industry is primarily driven by cost and time targets Lean construction principles focus on improving overall perfor-
with least priority towards waste management. Waste generation mance of a system with a holistic view rather than local optimal
Vilventhan et al. 817

solutions with specific activity focus (Gambatese et al., 2017).


Researchers have identified various lean design and lean con-
struction techniques, such as target value design, set based
design, pull scheduling, cross functional teams, integrated pro-
ject delivery (IPD), 5S’s, first-run study, PDCA (plan–do–check–
act), mistake-proofing, just-in-time (JIT), lean project delivery
system, Poka Yoke, last planner system (LPS), 5 why’s, spaghetti
chart, Andon, Kaizen, Kanban, kitting, work standardisation,
VSM and work structuring to reduce seven different types of
waste (Ballard et al., 2002; Gambatese et al., 2017; LCI, 2014;
Nesensohn et al., 2012).
Lean tools help decouple the expertise needed in screening
out waste and provides guidance for a systematic waste search in
the construction processes. VSM is one of the lean tools that has
a high potential to identify and reveal waste in a process. A value
stream is to be visualised as a sequential order of activities
involved in the transformation of a product or a service from the
raw initial state to the final state reaching the customer. VSM
represents the flow of material and information in a process,
identifying each value/non-value added in the process stage to its
Figure 1. Research methodology.
product stage (Rother and Shook, 1999). VSM could be viewed
as a quantitative tool to portray the current state of a process
using several process-related parameters and helps in future state strategic framework has been proposed to improve C&D waste
predictions (Yu et al., 2009). minimisation depicting the synergy of combining lean con-
A comparative study of lean and sustainability principles struction literature with C&D waste literature. This article con-
found that these two principles interact by a percentage of 13.5% tributes to lean/waste management research in two ways. First,
and applying lean always shows considerable achievement using VSM, this article measures and quantifies the construc-
towards sustainability (Khodeir and Othman, 2018). Lean plays a tion material waste generated in the process of construction.
greater role when non-value-adding activities exist in the pro- Second, it demonstrates the waste minimisation potential of
cesses (Ballard and Howell, 1994). Apart from the primary ben- integrating lean principles and waste reduction strategies
efit of waste reduction, several other benefits reported from through a lean strategic framework.
adopting lean techniques are productivity improvement, cost
benefits, construction time savings, reduction in labour require-
Research methodology
ment and costs, improved quality and safety, improved stake-
holder satisfaction and system flexibility (Ballard et al., 2002; A case study research methodology (Yin, 2003) has been adopted
Nesensohn et al., 2012). to study waste generation in a construction project in Chennai,
To sum up, a systematic methodology is needed to study and India. Real-time monitoring and measurement of waste is
screen out all the waste-producing processes and lean production required for assessment and quantification of waste on site.
paradigm provides excellent tools for the same. A lean-based Therefore, a case study research approach is appropriate for iden-
thinking could serve as a guide for all construction personnel to tifying, assessing and analysing the causes of waste generated on
anchor their thoughts and might help enable a cultural change site. Construction waste generated in each construction process
towards resource conservation. While the literature on lean con- in the case project was mapped using VSM tool. VSM was used
struction is rich, there are limited literature on the integration of in this article with the intention of capturing the percentage of
lean with C&D waste literature. Moreover, research addressing waste generated in each of the activities through mapping the
the applicability of lean tools to identify, assess and minimise current state of the processes.
material waste in the construction industry is negligible. VSM implementation in this research included the follow-
VSM being an effective tool, this article demonstrates the ing steps: (1) data collection and waste estimation of primary
usefulness of VSM in identifying the generation of material materials; (2) development of current state maps, identifying
wastes at different stages of the construction process and in the causes for waste generation and analysis of the current
doing so, it also investigates the waste generation rate for a state; (3) development of lean strategic framework through
reinforced concrete construction project. The article also dis- adopting lean construction principles and practises; and finally
cusses relevant lean principles, such as work standardisation, (4) the recommendations for implementing the lean strategic
5S and JIT, to improve waste management in construction framework. The research methodology adopted is depicted in
owing to their high relevance for construction projects. A Figure 1.
818 Waste Management & Research 37(8)

Figure 2. Value stream map showing waste evolution at the site.

Project selection The period of field observation was 9 months, which included
on-site observation and process mapping using a VSM approach
A high-rise reinforced concrete building construction project was with at least one visit to the site each week. To identify the causes
selected for this study. The characteristics of the selected project: of waste generated on site and waste minimisation strategies,
Reinforced concrete framed structure with pile foundation, brick- field monitoring and interviews with various participants of the
made partitioned wall interiors and flat roof. The total floor area projects, such as project manager, site engineers and site supervi-
of the project is about 1,41,000 ft2 (13,099.33 m2). The project sors, were conducted. A total of 16 interviews, each ranging
was selected based on the following parameters. between 45 min to 1 h were conducted with the case project par-
ticipants to identify causes of waste generation and strategies for
1. Construction process adopted in this project is very common mitigation. The qualitative data has been analysed using an open
and typical of many other construction projects in India. coding technique to understand causes of waste generation and
2. Project with job-site access for measuring waste generated on categorise strategies advocated (Strauss and Corbin, 1998). Later,
site. This was very crucial since waste management is a very an axial coding technique was employed to map the causes onto
shady concept in Indian construction sites presently and there the sources of waste framework and associate the minimisation
are several challenges in securing permission to study and strategies with the lean construction philosophies and principles.
measure waste in Indian construction sites. The waste generated in the process of construction was
3. Project with access to secondary data, such as bill of quanti- depicted using the lean tool VSM. Since the case project did not
ties (to cross validate the material required and material pur- implement lean principles/waste reduction strategies, material
chased) and the invoices of material purchases. waste evolved during the process of construction. The quantum
of waste generated and the causes of generation of waste in the
Data collection process of construction are explained. The benefits of using lean
principles in the management of waste in the construction pro-
A direct measurement and on-site volumetric estimation tech-
cess has been discussed in the following sections.
nique from stockpiled waste, as conducted by Lau et al. (2008),
was adopted in this study to calculate actual waste volume.
Heaped waste is reduced/categorised into one of the appropriate Results and discussion
standard mathematical shapes, such as rectangular prism or rec-
VSM
tangular base pyramid depending on the stockpile shape and vol-
ume formulae has been used with appropriate corrections to The current state map shows the processes involved and the evo-
estimate on-site waste volume. lution of material waste generation at the project site (refer to
Primary materials used in Indian construction are concrete, Figure 2). The current state map has been developed for all the
steel reinforcement, cement mortar, brick, asphalt sheet and floor- construction activities, including foundation, structural work and
ing materials like tiles, granites and marbles. In the chosen project, finishing. Waste generated in each process has been depicted in
concrete was used in the following elements or construction pro- the current state map. As the mapping process involved both
cess: Piling, raft footing, column, retaining wall, slab, beam, sun- direct observation and discussions with the site personnel, it
shade, loft, sunken filling and weathering course. Reinforcement helped us understand the causes of waste generation in each of
steel was used in roof slab, beam, column, piling, raft footing and the construction processes.
retaining wall. Asphalt sheets were used during raft footing con- The causes of waste generation in the project site studied
struction as water proofing members to prevent reinforcement bars could be broadly summarised as the following: Poor workman-
from corrosion. Bricks were used for external wall, sump internal ship of the labourers, improper storage of materials, improper
wall, partition wall and parapet wall construction. Flooring com- handling of materials, inadequate planning by the responsible
prised of materials, such as marbles, granite and tile works. personnel, errors in ordering and shipping, design and detailing
Vilventhan et al. 819

Table 1. Sources of waste generated in the construction site.

Classification of material wastes on site Sources of waste

Design Procurement Handling of materials Operation Residual


Reinforcement • •
Concrete • • • • •
Cement mortar • •
Bricks • •
Flooring tiles • • •
Asphalt sheet • •

Table 2. Details of waste generated in the project site.

Material Process description Purchased quantity Wasted quantity Material wastage Total wasted quantity
(m3 or *m2) (m3 or *m2) ratio (%) in project

kg %
Reinforcement Pile foundation 12.56 1.06 5.4 50,946.5 5.87
steel Pile cap 30.77 1.46
Raft foundation 2.05 0.08
Slab and Beam 60.01 2.89
Column 14.56 1.00
Concrete Reinforcement cement 4769.75 215.12 4.3 497,927 57.37
concrete
Plain cement concrete 80.71 0.67
Brick jelly concrete 190.00 0.70
Brick (burnt clay) Internal wall 1340.00 70.62 3.6 181,355 20.89
External wall 650.00 24.83
Cement mortar Brick masonry 682.12 5.66 2.0 114,370 13.18
Plastering 503.37 17.77
Foundation 26.00 0.16
Granite flooring 7.05 0.07
Tile flooring 746.33 4.55
Marble flooring 7.05 0.03
Granular flooring 650.71 24.66
Asphalt sheet Water proofing 1300* 35.49* 2.7 106.5 0.01
Flooring Marble flooring 100.00* 3.82* 7.2 23,277.7 2.68
materials Granite flooring 100.00* 5.28*
Tile flooring 15,802.19* 1144.08*
Total quantity of waste generated in kg 867,982.7 100
Waste generation rate in kg m−2 66.26

Starred items (*) are reported in the units of m2.


Material wastage ratio is calculated as wasted quantity relative to purchased quantity.

mistakes, and leftover material scraps originated from resizing composition in the form of percentages has also been shown in
materials to fit the design. These reasons were mapped into the Table 2. It can be inferred that concrete contributes a large por-
sources of waste framework (proposed by Gavilan and Bernold, tion of waste at about 57.37% of the total waste produced on site.
1994) consisting of the following categories: Design, procure- While the material wastage ratio of concrete is only about 4.3%,
ment, handling of materials, operation and residual as shown in the actual quantity of wastage is still huge and could have been
Table 1. The analysis indicated that a large proportion of material avoided if adequate measures have been taken, which will be dis-
waste occurred owing to improper handling of materials and left- cussed in the coming sections.
over material scraps in the project studied.
The amounts of waste generated in the case of major materials
Waste generated during the construction
are shown in Table 2. Volumetric estimations conducted at the
site have been converted to waste quantity in kilograms using the
of foundation
appropriate material densities of each material. The total quantity Concrete waste formed a major part of wastes that occurred
of waste generated at the site was found to be 66.26 kg m−2. Waste during the construction of the foundation. For instance, during
820 Waste Management & Research 37(8)

Figure 3. Concrete waste on site.

Figure 4. Steel waste on site.

pile concreting, to maintain a uniform pile length of 15 m, a por- Waste generated during the construction
tion of approximately 3 m in each pile was cut (total length of of structural elements
pile that was cast is 18 m and design length of pile up to pile cap
is 15 m) and discarded on site, as shown in Figure 3, leading to Construction of structural elements includes the construction of
wastage of concrete. A portion of the activities in casting, cut- columns, beams and roof slab. Concrete wastage in these pro-
ting and handling the wastes could be visualised as non-value cesses were primarily because of the excess quantity that remained
adding and resources, such as time, material and labour, were on-site owing to errors in estimation of requirement. The site per-
unnecessarily spent. During concreting for the raft slab, level- sonnel over-ordered the concrete quantity owing to his lack of
ling operations of plain cement concrete (PCC) surfaces were judgement and improper planning skills, which lead to wastage of
not found to be proper and uneven PCC surface led to wastage concrete. Both fresh concrete and brick jelly concrete were wasted
of reinforced cement concrete (RCC) poured above it. Asphalt in the site. Apart from over-ordering waste, leakages in formwork
sheets were also wasted to some extent owing to improper han- and rework owing to poor concrete placement were also observed,
dling on site. PCC was used to cover the asphalt sheet layer leading to concrete wastages. Sometimes, overfilling of form-
before laying the reinforcement cage over the surface. works leads to skimming operations on site, that is, levelling the
It is observed from the case analysis that sources of waste in concrete surface generates wastes.
the construction of the foundation was owing to improper design Steel reinforcement waste was generated during cutting of pro-
and improper handling of materials. For work standardisation, a cured steel rods as per the required design length and produced
lean technique could have been adopted for the minimisation of short unusable pieces. These cut pieces generally ended up as
material waste in the construction. Standardisation in design, use waste in the storage place (Figure 4) and rusting of steel bars was
of modular designs and standard procedures could be incorpo- also observed to contribute to waste. The total steel waste was
rated at the organisational level in order to minimise material about 50 t. While these steel rods are discarded from getting uti-
waste on site owing to improper design and material handling. lised in this project, they usually end up being sold to scrap dealers
Vilventhan et al. 821

Figure 5. Brick waste on site.

and are never landfilled or disposed in unauthorised locations in


Indian cities. Excess of cement mortar arising because of improper
judgement of required quantity by construction personnel and
improper handling were generally disposed in the site. Spillage
during transportation of mortar using wheelbarrows on uneven
road surfaces in the site increases wastage. Labour’s attitude also
plays a major role in influencing careful handling of materials.
Cement mortar wastage amounts to about 114 t in the whole pro-
ject, forming 13.18% of the total waste from the project.
From the case analysis, it was also found that excessive ordering Figure 6. Tile waste on site.
and storing was the main cause of waste in the construction of struc-
tural elements. If the lean principle JIT was incorporated, steel
waste and concrete material waste could have been avoided.
Resources that are required are recommended to be made available
only at the time of execution or production (Ballard et al., 2002).
Wastages owing to improper storage of materials, over-ordering
and other downstream effects of these sources could be eliminated.

Waste generated during the finishing


activities
The finishing activities involve laying weathering course and
flooring materials. Brick jelly concrete was used as weathering Figure 7. Use of 5S principle in stacking of bricks for
construction.
course material. Incorrect estimations of required quantity
resulted in excess or shortage of material at times. Moreover, bro-
ken bricks during handling were not properly segregated and become high. In such cases of revisions, the tile would be cut to
stored on site (Figure 5). If they had been segregated and stored, match the floor size leading to wastage. However, a major amount
they could have been consumed during laying of bricks in the of tile wastage in this project occurred because of improper han-
corners of the wall. Lack of such planning leads to the consump- dling on site and little quantity because of resizing to match the
tion of unbroken bricks as they were cut for usage on the corners floor size. Tile waste scattered on site is shown in Figure 6.
of the wall. This activity of breaking again, as well as improper The use of 5S (sort, set in order, shine, standardise, sustain)
handling during transportation, resulted in considerable wastage. lean principles (refer to Figure7) would considerably reduce the
Breakage of brick walls for installing services, such as electrical waste owing to improper handling. As shown in Figure 7, bricks
wirings and plumbing, also leads to a considerable amount of stacked based on the required quantity on each floor will help in
brick waste. Brick wastage amounts to about 20.89% of the total efficient usage of bricks, reduce breakage and thereby minimise
material waste generated in the project. brick wastages. The effective implementation of the 5S purely
Flooring materials are usually procured based on the measure- depends on the workers’ commitment. The need for sense of
ment indicated in the initial drawings. If there had been any responsibility and commitment has also been reported in C&D
change in designs later, wastages during installation might waste literature (Li and Yang, 2014; Teo and Loosemore, 2001).
822 Waste Management & Research 37(8)

Figure 9. Stacking of plywood on site.


Figure 8. Lean strategic framework for waste minimisation
on site.

Thus, lean tools and principles would augment waste minimi-


sation strategies in the minimisation of the material waste on site.
Hence a lean strategic framework has been proposed for con-
struction waste management. The application of these lean tools
and principles for waste minimisation is discussed in the follow-
ing section.

Lean strategic framework for waste


minimisation on site Figure 10. Stacking of bricks on site.
Lean construction principles and practises would prove to be highly
useful as they can complement C&D waste literature in providing a delays. Moreover, in the case of construction, basic materials
structured framework for waste minimisation as discussed in the (sand, cement, bricks and reinforcement) and tools are dis-
earlier sections. A lean strategic framework (Figure 8) has been pro- tinctly identifiable. Hence, application of 5S will help in defin-
posed for identification and minimisation of waste generation ing the way of storing and handling of materials and tools on
through incorporating lean construction principles and practises. site. The materials, such as bricks, tiles, marble, steel, cement
Construction companies should be aware of the magnitude of waste bags and plywood, could be placed in an orderly manner (refer
generated at their sites to understand the focus areas for improve- to Figures 9 and 10). For example, instead of disposing of all
ment initiatives. A combination of tools, such as sources of waste the plywood wastes in a random manner, those that are of
framework and estimation methods from C&D waste literature, acceptable quality for reuse are carefully segregated and stacked
along with the process lens of VSM, a tool from lean construction separately for facilitating reuse (Figure 9). Sand can be heaped
literature, would be beneficial in improving quantification and in a conical shape and covered when not in use, to prevent being
assessing causes of waste generation. The need for contractors to carried away by external factors and thereby control wastage.
maintain records on the actual delivery, storage and consumption of Several other strategies mentioned in C&D waste literature that
materials need not be overstated. Awareness of the current state falls under this lean principle includes proper planning, collec-
helps in determining effective strategies to improve the future state. tion and on-site sorting of waste materials, and 3R (reduce,
The 5S lean tool is one of the most commonly adopted tools reuse and recycle) activities for continuous improvement (Ajayi
in all manufacturing units and is reported to be highly relevant et al., 2017; Poon et al., 2004b; Yuan et al., 2013).
for the construction industry as well. It helps to visualise the ben- The next tool, JIT ordering was developed with the idea that
efits of lean in a short period of time (Yu et al., 2011). Application keeping inventories are not beneficial and should be consid-
of 5S would result in a neat and clean workspace. The 5S implies, ered as waste if JIT is practised effectively in construction
‘first Sort out the tools, materials needed and not needed, Set in sites. Reductions in the amounts of stockpiled materials have
order or organise the sorted-out items, Shine or clean the area been reported to reduce pollution, resource consumption, time
regularly, Standardise the work routine, Sustain the changes savings and cost savings (Ballard et al., 2002; LCI, 2014). A
made by creating responsibility among workers’. good logistics agreement with suppliers, and appropriate order-
Meetings on site should incorporate 5S knowledge to the ing to minimise cutting wastes, could also contribute to waste
workers, and monitoring of the 5S needs to be conducted regu- minimisation.
larly till it becomes inculcated in routine practise. The 5S advo- The next tool, work standardisation, contributes to consistency
cates due consideration of workers’ opinion as they are the ones in quality and shifts focus from a people-centric to a process-centric
better situated to make work easier, without any confusions and approach (Yu et al., 2011). Work standardisation considers task
Vilventhan et al. 823

Figure 11. Storage yards for material wastes on site.

time and work sequence to establish work standards. Standard Conclusion, limitations and future
worksheets can be used to determine the task sequence, workforce scope
requirements, materials used and quantity of material wasted on
site. To serve as guidelines for planning material requirements, A waste generation rate of 66.26 kg m−2 was identified from a
Builders Association of India have released databases containing building construction case study. Concrete, cement mortar and
information, such as adequacy of cement, reinforcement steel and brick waste represented almost 90% of the total construction
other common building materials, for various works packages that waste. Lack of on-site waste management planning has been
ensures a minimum standard in the performance with regard to observed to be one of the primary causes of waste generation.
strength, density, etc. Such initiatives and awareness of the informa- The findings are from a single case study and therefore should be
tion needs to be publicised among contractors to have a widespread treated with caution in terms of their generalisability. The appli-
impact in the construction industry. The use of prefabricated ele- cation and benefits of lean tools for waste minimisation has been
ments, modular designs and use of recycled materials could all be discussed. A lean strategic framework has been developed show-
standardised as part of standard procedures at the organisational ing synergistic benefits to be gained in combining lean construc-
level (Wang et al., 2015). tion literature with the C&D waste literature. The developed
Standard waste management plans to be adopted in all pro- framework is generic, which can be applied to any type of con-
ject sites could be enforced at the organisational level (Tam, struction projects.
2008). Separate storage yards for storing the different types of This article contributes to lean/waste management research in
material wastes can be provided on site, as shown in Figure 11. two ways. First, using VSM, this article measures and quantifies
The worksheet will enable the site personnel to calculate and the construction material waste generated in the process of con-
plan for the activity to be performed. Benchmarked indices struction. Second, it demonstrates waste minimisation potential
could represent the expected work performance for each activ- of integrating lean principles and waste reduction strategies
ity. Adoption of tools, such as BIM, could be made as a part of through a lean strategic framework. This research is useful to
a standardised design process to improve waste management practitioners because they can implement the lean practises to
(Cheng and Ma, 2013). minimise construction waste and use VSM to visually map the
Visual representation, such as usage of three-dimensional waste generation on site.
architectural designs, and structural models would improve There are several limitations that are to be noted in this study.
communication and help stakeholders visualise the exact While it is argued that borrowing lean construction principles are
requirements. Mid-level managers might be assigned with roles beneficial, actual implementation of those strategies have not
to monitor variations, investigate the root causes, ensure imme- been shown on site owing to difficulties in securing permissions
diate remedy steps and re-establish work standardisation. Thus, for implementation. However, examples of lean tools implemen-
integrating lean construction principles with construction waste tation referred to from other Indian sites add merit to the discus-
management literature has a huge potential for significant waste sion. Moreover, it is not meant that only the three lean construction
minimisation. principles that are discussed in this article have high potential to
824 Waste Management & Research 37(8)

contribute to construction process improvement and waste mini- Gavilan RM and Bernold LE (1994) Source evaluation of solid waste in build-
ing construction. Journal of Construction Engineering and Management
misation. The relevance and merits of all the other lean construc-
120: 536–552.
tion principles in contributing to C&D waste minimisation and Garza-Reyes JA (2015) Lean and green—a systematic review of the state of
better management could be undertaken in the future studies and the art literature. Journal of Cleaner Production 102: 18–29.
the framework could be enhanced to make it more holistic. Hosseini SA, Nikakhtar A, Wong KY, et al. (2012) Implementing lean construc-
tion theory into construction processes’ waste management. In: International
Objective evaluation of the synergy obtained in combining the Conference on Sustainable Design and Construction (ICSDC) 2011 23–25
two distinct bodies of literature and actual implementation of March 2011, Kansas City, Missouri: Integrating Sustainability Practices in
those principles and strategies on sites through action research the Construction Industry, ASCE 2012, pp. 414–420.
Khodeir LM and Othman R (2018) Examining the interaction between lean
methods could be valuable topics for research in the future
and sustainability principles in the management process of AEC industry.
studies. Ain Shams Engineering Journal 9: 1627–1634.
Koskela L (1992) Application of the New Production Philosophy to
Declaration of conflicting interests Construction. CIFE Tech. Rep. No.72. Center for Integrated Facility
Engineering, Stanford Univ, Stanford, CA.
The authors declared no potential conflicts of interest with respect to Lau HH, Whyte A and Law PL (2008) Composition and characteristics of
the research, authorship, and/or publication of this article. construction waste generated by residential housing project. International
Journal of Environmental Research 2: 261–268.
Funding LCI (2014) LCI Lean Project Delivery Glossary. Lean Construction Institute.
Available at: https://www.leanconstruction.org/learning/lean-articles/
The authors received no financial support for the research, author-
(accessed 25 September 2018).
ship, and/or publication of this article. Li M and Yang J (2014) Analysis of interrelationships between critical waste
factors in office building retrofit projects using interpretive structural mod-
ORCID iD elling. International Journal of Construction Management 14: 15–27.
Lu M, Poon CS and Wong LC (2006) Application Framework for Mapping
Aneetha Vilventhan https://orcid.org/0000-0001-5614-3500
and Simulation of Waste Handling Processes in Construction. Journal of
Construction Engineering and Management 132: 1212–1221.
Reference Mah CM, Fujiwara T and Ho CS (2016) Construction and demolition waste
Ajayi SO, Oyedele LO, Bilal M, et al. (2017) Critical management practices generation rates for high-rise buildings in Malaysia. Waste Management
influencing on-site waste minimization in construction projects. Waste & Research 34: 1224–1230.
Management 59: 330–339. Mahalingam A, Yadav AK and Varaprasad J (2015) Investigating the role
Al-sari MI, Al-khatib IA and Avraamides M (2012) A study on the atti- of lean practices in enabling BIM adoption: Evidence from two Indian
tudes and behavioural influence of construction waste management cases. Journal of Construction Engineering and Management 141: 1–12.
in occupied Palestinian territory. Waste Management & Research 30: Mália M, Brito JDe and Pinheiro MD (2013) Construction and demolition
122–136. waste indicators. Waste Management & Research 31: 241–255.
Ballard G and Howell G A (1994) Implementing lean construction: Stabilizing Martínez-Jurado PJ and Moyano-Fuentes J (2014) Lean management, sup-
work flow. In: Balkema AA (ed.) Implementing Lean Construction. ply chain management and sustainability: A literature review. Journal of
Rotterdam, Netherlands, pp. 101–110. Cleaner Production 85: 134–150.
Ballard G and Howell GA (2005) Relational contracting and lean construc- Nesensohn C, Demir ST and Bryde DJ (2012) Developing a ‘True north’ best
tion. Lean Construction Journal 2: 1–4. practice lean company with navigational compass. In: 20th Conference
Ballard G, Tommelein ID, Koskela L, et al. (2002) Chapter 15: Lean of the International Group for Lean Construction, 18–20 July 2012, San
construction tools and techniques. In: Best R and de Valence G (eds) Diego, USA.
Design and Construction: Building in Value. Routledge, London, Paz DH and Lafayette KP (2016) Forecasting of construction and demolition
pp.211–226. waste in Brazil. Waste Management & Research 34: 708–716.
Bresnen M, Goussevskaia A and Swan J (2005) Implementing change in con- Poon CS, Yu ATW and Jaillon L (2004a) Reducing building waste at con-
struction project organizations: Exploring the interplay between structure struction sites in Hong Kong. Construction Management and Economics
and agency. Building Research and Information 33: 547–560. 22: 461–470.
Bresnen M and Marshall N (2001) Understanding the diffusion and applica- Poon CS, Yu ATW, Wong SW, et al. (2004b) Management of construc-
tion of new management ideas in construction. Engineering, Construction tion waste in public housing projects in Hong Kong. Construction
and Architectural Management 8: 335–345. Management and Economics 22: 675–689.
Cheng JCP and Ma LYH (2013) A BIM-based system for demolition and Ram VG and Kalidindi SN (2017) Estimation of construction and demolition
renovation waste estimation and planning. Waste Management 33: 1539– waste using waste generation rates in Chennai, India. Waste Management
1551. & Research 35: 610–617.
Dües CM, Tan KH and Lim M (2013) Green as the new lean: How to use lean Rao A, Jha KN and Misra S (2007) Use of aggregates from recycled con-
practices as a catalyst to greening your supply chain. Journal of Cleaner struction and demolition waste in concrete. Resources, Conservation and
Production 40: 93–100. Recycling 50: 71–81.
Esa MR, Halog A and Rigamonti L (2017) Strategies for minimizing con- Rother M and Shook J (1999) Learning to See. The Lean Enterprise Institute,
struction and demolition wastes in Malaysia. Resources, Conservation MA, USA.
and Recycling 120: 219–229. Saez PV, del Río Merino M, San-Antonio González A, et al. (2013) Best
Esin T and Cosgun N (2007) A study conducted to reduce construction waste practice measures assessment for construction and demolition waste
generation in Turkey. Building and Environment 42: 1667–1674. management in building constructions. Resources, Conservation and
Fercoq A, Lamouri S and Carbone V (2016) Lean/green integration focused on Recycling 75: 52–62.
waste reduction techniques. Journal of Cleaner Production 137: 567–578. Saez PV, Porras-Amores C and del Rio Merino M (2015) New quantification
Formoso CT, Soibelman L, De Cesare C, et al. (2002) Material waste in proposal for construction waste generation in new residential construc-
building industry: Main causes and prevention. Journal of Construction tions. Journal of Cleaner Production 102: 58–65.
Engineering and Management 128: 316–325. Strauss A and Corbin J (1998) Basics of Qualitative Research. Thousand
Gambatese JA, Pestana C and Lee HW (2017) Alignment between lean prin- Oaks, CA, USA: SAGE Publishing.
ciples and practices and worker safety behavior. Journal of Construction Tam VWY (2008) On the effectiveness in implementing a waste-manage-
Engineering and Management 143: 51–60. ment-plan method in construction. Waste Management 28: 1072–1080.
Vilventhan et al. 825

Teo MMM and Loosemore M (2001) A theory of waste behaviour in the con- Yu H, Al-Hussein M, Al-Jibouri S, et al. (2011) Lean transformation in a
struction industry. Construction Management and Economics 19: 741–751. modular building company: A case for implementation. Journal of
Wang J, Li Z and Tam VWY (2015) Identifying best design strategies for Management in Engineering 29: 103–111.
construction waste minimization. Journal of Cleaner Production 92: Yu H, Tweed T, Al-hussein M, et al. (2009) Development of lean model for
237–247. house construction using value stream mapping. Journal of Construction
Wu Z, Yu ATW, Shen L, et al. (2014) Quantifying construction and demo- Engineering and Management 135: 782–790.
lition waste: An analytical review. Waste Management 34: 1683–1692. Yuan H, Lu W and Jianli Hao J (2013) The evolution of construction
Yin RK (2003) Case Study Research – Design and Methods. Thousand Oaks, waste sorting on-site. Renewable and Sustainable Energy Reviews 20:
CA, USA: SAGE Publishing. 483–490.

You might also like