Est To Complete 26 12 2021
Est To Complete 26 12 2021
Est To Complete 26 12 2021
Logistics 100,000.00
4,700,000.00
3,584,600.00
Water Tank
4 nr 3 phase - 117,910.69 -
1nr Single phase 5.00 63,061.32 315,306.60
₦ 315,306.60
Item Description Qty Unit Rate Amount
A POP Ceiling 180.00 Sq.m 5,000.00 900,000.00
B Tiling 350.00 Sq.m 500.00 175,000.00
C Cement for Tiling 40.00 Nr 4,200.00 168,000.00
D Soak Away and Septic Tank Sum 500,000.00
E Internal Door installation 8.00 Nr 5,000.00 40,000.00
F Electrcial fittings and Internal Lighting 4.00 Nr 70,000.00 280,000.00