Daily Report For Construction

06.05.2024 Week: Wednesday Weather Sunny Prepared by: Handphone: 082113445513


Construction Date:
: Wang Qun

Project Name OKI Phase Ⅱ WHP

Supervision Unit OKI Phase Ⅱ Project WHP Team

Contractor PT.NEPC

Construction Embedded plate Installation

Tools Welding machine 4 set、Cutting machine 6 Pcs、fire cutting machine 2set、250t hoisting machine 、80t wooden handcart 、pickup truck 2 vehicles

Manpower Total Manpower 100 Management 26 Direct manpower 74

Safety Man*hours Safety total Man*hours 1480 Management safety 264 Direct manpower 1216

1、Temporary construction of life and production

2、Line 24 chipper foundation area installation&Edge iron

3、Line 17 area foundation installation

4、Line 15 chipper foundation alignment

5、Line 22 debarking drum foundation installation

6、3014 cover installation


Today Job Activities
7、Line 16 PF assembly

8、Line 14 Receiving deck installation

9、Material transportation

1、Temporary construction of life and production

2、Line24 chipper foundation area installation&Edge iron

3、Line 17 area foundation installation&

4、Line 15 chipper foundation alignment

5、Line 22 debarking drum foundation installation&

6、3014 cover installation

7、Line 14 Receiving deck installation

Next Day planning Job 8、Material transportation

Progress Summary

Project Job Quantity Unit Today Finish This Week Next Total Percentage Remarking

Accumulated Week Accumulated

Planning

WHP Mechanical Grand Total 26655231 Kg 107246 500 1929900 7.24%

Total 400000 Kg 500 500 131500 32.89%


Embedded plates
install

Main Equipment : 8540862 Kg 20000 0 0 714000 8.13%

220 Unit

Belt Conveyor: 5755421 Kg 0 0 0 280000 4.86%

130 Unit

Chain Conveyor: 2138909 Kg 0 0 0 0 0.00%

57 Unit

Screw Conveyor: 1276688 Kg 0 0 0 0 0.00%

83 Unit

Roll Conveyor: 603000 Kg 0 0 0 0 0.00%

10 Unit

Fan:3 Unit 750 Kg 0 0 0 0 0.00%

Steel Structures 7939601 Kg 0 0 0 822000 10.35%

&Conveyor Bridge:

123 Unit

Service 1017000 Kg 0 0 0 26000 25.56%

Platform(Walkway

and stairs):19 Unit

Welding of side Receiving deck

Material transportation

Activities Photos

Line 17 foundation plate

Line 24 receiving foundation installation


Equipment defects