RFI Report

Id Status RFI ID Category Sub-Category Item Layer Side Chainage From Chainage To Activity Requested Date & Time Scheduled Date & Time Inspector Result Inspec
Date
Time

232308 RFI Raised N/01001/11006/ Structure New well Lift 1 LHS 116.898 116.898 Checking of 16/05/2024 17/05/2024 Mr Pending
By GJ/RFI/ Underpasses / foundation / reinforcement 10:43 PM 11:30 AM NIKESH
Contractor STRUCTURE/ Overpasses pile A1&A2 wall KUMAR
N/30 foundation / 1st lift of
open LVUP
foundation
232296 RFI Raised N/01001/11006/ Structure New minor Pier / Lift 1 LHS 126.392 126.392 Checking for 16/05/2024 17/05/2024 Mr Pending
By GJ/RFI/ bridges abutment pouring 10:38 PM 04:30 PM vivek
Contractor STRUCTURE/ Concrete kumar
N/29 Grade M-35 Sahani
Abutment
wall 1st lift of
MNB
232293 RFI Raised N/01001/11006/ Structure New minor Pier / Lift 1 LHS 126.392 126.392 Checking of 16/05/2024 17/05/2024 Mr Pending
By GJ/RFI/ bridges abutment shuttering for 10:36 PM 04:00 PM vivek
Contractor STRUCTURE/ Formwork kumar
N/28 Abutment Sahani
wall 1st lift of
MNB
232287 RFI Raised N/01001/11006/ Structure New Major Pier / Lift 1 LHS 126.392 126.392 Checking of 16/05/2024 17/05/2024 Mr Pending
By GJ/RFI/ Bridge abutment reinforcement 10:33 PM 11:00 AM vivek
Contractor STRUCTURE/ for Abutment kumar
N/27 wall 1st lift of Sahani
MNB
232284 RFI Raised N/01001/11006/ Structure New well Lift 2 RHS 106.330 106.330 Checking for 16/05/2024 17/05/2024 Mr Pending
By GJ/RFI/ Underpasses / foundation / pouring 10:30 PM 05:00 PM Pravin
Contractor STRUCTURE/ Overpasses pile Concrete Kumar
N/26 foundation / Grade M-30 Tiwari
open of A1 MCW &
foundation Median wall
2nd lift of
LVUP
232279 RFI Raised N/01001/11006/ Structure New well Lift 2 RHS 106.330 106.330 Checking for 16/05/2024 17/05/2024 Mr Pending
By GJ/RFI/ Underpasses / foundation / Formwork A1 10:28 PM 04:00 PM Pravin
Contractor STRUCTURE/ Overpasses pile MCW & Kumar
N/25 foundation / Median wall Tiwari
open 2nd lift of
foundation LVUP
Id Status RFI ID Category Sub-Category Item Layer Side Chainage From Chainage To Activity Requested Date & Time Scheduled Date & Time Inspector Result Inspec
Date
Time

232266 RFI Raised N/01001/11006/ Structure New well Lift 2 RHS 106.330 106.330 Checking of 16/05/2024 17/05/2024 Mr Pending
By GJ/RFI/ Underpasses / foundation / reinforcement 10:26 PM 03:00 PM Pravin
Contractor STRUCTURE/ Overpasses pile for A1 MCW Kumar
N/24 foundation / & Median wall Tiwari
open 2nd lift of
foundation LVUP
232186 RFI Raised N/01001/11006/ Highway Main Embankment Layer RHS 125.920 125.940 FDD checking 16/05/2024 17/05/2024 Mr Pending
By GJ/RFI/ Carriageway 15 of EMB 15th 09:58 PM 03:30 PM Prakash
Contractor HIGHWAY/N/23 (Rigid Layer Kumar
Pavement) Pandey
232169 RFI Raised N/01001/11006/ Highway Main Embankment Layer RHS 125.840 125.910 FDD checking 16/05/2024 17/05/2024 Mr Pending
By GJ/RFI/ Carriageway 15 of EMB 15th 09:55 PM 03:15 PM Prakash
Contractor HIGHWAY/N/22 (Rigid Layer Kumar
Pavement) Pandey
232168 RFI Raised N/01001/11006/ Highway Main Embankment Layer LHS 125.840 125.910 FDD checking 16/05/2024 17/05/2024 Mr Pending
By GJ/RFI/ Carriageway 15 of EMB 15th 09:53 PM 03:00 PM Prakash
Contractor HIGHWAY/N/21 (Rigid Layer Kumar
Pavement) Pandey